J K Schlaegel v. Un. Twp. Bd. of Trustees, Unpublished Decision (6-9-2006)

2006 Ohio 2913
CourtOhio Court of Appeals
DecidedJune 9, 2006
DocketC.A. Nos. 2005-CA-31, 2005-CA-34.
StatusUnpublished
Cited by4 cases

This text of 2006 Ohio 2913 (J K Schlaegel v. Un. Twp. Bd. of Trustees, Unpublished Decision (6-9-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J K Schlaegel v. Un. Twp. Bd. of Trustees, Unpublished Decision (6-9-2006), 2006 Ohio 2913 (Ohio Ct. App. 2006).

Opinion

OPINION
{¶ 1} The Board of Trustees of Union Township appeals from a judgment rendered against it in litigation stemming from a public improvement construction contract. The Township contends that the trial court should have granted its motions for judgment on the pleadings, summary judgment, judgment notwithstanding the verdict and for a new trial. The Township also contends that the trial court erred with regard to the issue of prejudgment interest.

{¶ 2} The contractor, J J Schlaegel, Inc., has cross-appealed. Schlaegel contends that the trial court erred by granting the motion for judgment on the pleadings filed by Fereidoun Shokouhi, the Champaign County Engineer, and by dismissing the engineer from the litigation. Schlaegel further contends that the jury erred with regard to its calculations of damages, and that the trial court erred with regard to the issue of prejudgment and post-judgment interest.

{¶ 3} We conclude that the trial court erred by failing to render judgment on the pleadings in favor of the Township with regard to Schlaegel's claims against it. However, we conclude that it did not err by denying the motions for judgment on the pleadings and summary judgment with regard to the Township's counterclaim against Schlaegel. Instead, we conclude that the Township has raised an issue of fact with regard to its counterclaim which must be resolved via hearing or new trial. Finally, we conclude that, given the error in denying the motion for judgment on the pleadings, the trial court erred by assessing interest against the Township.

{¶ 4} On the matter of the cross-appeal, we find that the trial court did not err by dismissing the county engineer from the action. We further find that all issues regarding damage and interest calculations have been rendered moot.

{¶ 5} Accordingly, the judgment is reversed, in part, and this cause is remanded for further proceedings in accordance with this opinion.

I
{¶ 6} The Board of Trustees of Union Township entered into a construction contract with J J Schlaegel, Inc., for the improvement of a portion of South Ludlow Road located within the Township. The improvement consisted of the relocation and reconstruction of a curved section of the road, as well as construction of shoulders and drainage ditches on the portions of the road to the north and south of the curve.

{¶ 7} The contract between the parties provided, in part, that the Township would pay Schlaegel the "approximate sum of $361,897.62." The contract went on to state that "the actual sum to be paid, however, will be the aggregate total determined by the work actually performed by Schlaegel, calculated upon the unit price set out in" Schlaegel's bid form. Of particular relevance to this appeal are Sections Two and Three of the contract specifications, which state as follows:

{¶ 8} "2. Roadway Excavation including Embankment: Shall be in accordance with item 203 and to the lines and grades shown on the plans. All surplus and/or unsuitable excavated material shall be disposed of in accordance with 203.05 or as directed by the Township. Also consists of the removal and satisfactory disposal of the pavement to the line and grade shown on the plan and in accordance with item 303. Payment shall be at the contract price per cubic yard for roadway excavation.

{¶ 9} "3. Linear Grading: Shall be in accordance with item 203 and to the lines and grades shown on the plan. This shall include the needed embankment construction. Payment shall be the contract price per station graded along each side of the pavement."

{¶ 10} The parties agree that Section Two of the Specifications pertains to the curved portion of the project, while Section Three pertains to the remainder of the project. They also agree that the references to "item 203" in the Specifications relate to the State of Ohio, Department of Transportation Manual on Construction and Material Specifications, a copy of which is included in the record.

{¶ 11} The following provisions of that publication, relevant to this matter, are set forth below:

{¶ 12} "ITEM 203 ROADWAY EXCAVATION AND EMBANKMENT

{¶ 13} "203.01 Description. This work shall consist of preparation of areas upon which embankments are to be placed; excavation for the roadway and channel, including the removal of all material encountered not being removed under some other item; constructing embankments with the excavated material and material from other sources necessary to complete the planned embankments; furnishing and incorporating all water required for compacting embankment and subgrade; disposing of unsuitable and surplus material; preparing the subgrade; testing the stability and uniformity of compaction of the subgrade for areas specifically called for on the plans; finishing shoulders, slopes and ditches; all in accordance with these specifications and in reasonably close conformity with the lines, grades, thicknesses and cross sections shown on the plans. All excavation shall be considered as unclassified.

{¶ 14} "* * *

{¶ 15} "Where embankment is not a separate pay item, payment for roadway excavation shall be made under 203 Excavation Including Embankment Construction, which shall include payment for placing suitable excavated material in embankment. If borrow is needed to complete planned embankments, it shall be measured and paid for separately under 203 Borrow.

{¶ 16} "* * *

{¶ 17} "203.02 * * * Borrow. Material obtained from approved sources, outside the right-of-way, required for the construction of embankments or for other portions of the work.

{¶ 18} "203.04 * * * (g) Linear Grading. This work shall include all labor and equipment necessary to produce typical sections and profile grades as detailed in the plans. This shall include embankment construction if embankment area is with 1 km (½ mile) of material source. If additional material is required to obtain conformance to plan specified grades, and if it is required at a distance of more than 1 km (½ mile) from material source, then it shall be measured and paid for separately under 203 Borrow.

{¶ 19} "203.15 * * * (d) Measurement of Embankments. Where the contract does not specifically provide for payment for embankment, the work of embankment construction will not be paid as such, but will be considered incidental to the various items of excavation."

{¶ 20} Finally, the contract contained an eleven-page set of plans, which included an aerial view of the project, as well as drawings and elevation information.

{¶ 21} The project was commenced in July of 2000. On September 13, 2000, the Township provided Schlaegel with a document that was prepared prior to entering into the contract, which is identified in the record as "Plaintiff's Exhibit Four." That document contains calculations regarding the cubic yards to be excavated as well as the cubic yards of material needed for the embankment specified in Section Two, Excavation with Embankment, in the contract specifications. According to the document, the Township estimated that 10,696.16 cubic yards of material would be excavated from the curved section of the road and that the embankment in that area would require the use of 14,061 cubic yards of material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mentor v. Cleveland Elec. Illum. Co.
2024 Ohio 399 (Ohio Court of Appeals, 2024)
Re/Max Crossroads Properties v. Roberts
2013 Ohio 5575 (Ohio Court of Appeals, 2013)
Flaughers v. Thomas
2013 Ohio 1217 (Ohio Court of Appeals, 2013)
A.H. Sturgill Roofing, Inc. v. Robert W. Setterlin & Sons Co.
870 N.E.2d 240 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 2913, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-k-schlaegel-v-un-twp-bd-of-trustees-unpublished-decision-6-9-2006-ohioctapp-2006.