J. G. White & Co. v. Ball Engineering Co.

298 F. 709, 1924 U.S. App. LEXIS 2701
CourtCourt of Appeals for the Second Circuit
DecidedApril 7, 1924
DocketNo. 272
StatusPublished

This text of 298 F. 709 (J. G. White & Co. v. Ball Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. G. White & Co. v. Ball Engineering Co., 298 F. 709, 1924 U.S. App. LEXIS 2701 (2d Cir. 1924).

Opinion

HOUGH, Circuit Judge.

This writ is the latest step in a litigation now 13 years old. It grows out of a seizure by the United States of certain property used in building a lock and dam for the government, and found at the work place when the contractor defaulted, and the engineers in charge annulled his contract. Plaintiffs assert that this [710]*710property was theirs, and was neither owned by the contractor, nor leased to him. Defendants are sued for the conversion of the same, and bring this writ after judgment against them for its value, with 'many years’ interest added. Judgment resulted from the lower court’s decision reported in 283 Fed. 496, where reference to the lengthened earlier history of the litigation may be found.

Defendants once had judgment in their favor, which was reversed in 250 U. S. 46, 39 Sup. Ct. 393, 63 L. Ed. 835 - the present record results from a new trial, and the question before us is, in substance, whether this record so differs from that before the Supreme Court as to warrant departure from the conclusion there reached on the proceedings submitted to that tribunal. The case was tried by consent without a jury and before a referee or master, whose findings, on familiar principles, have the force of a verdict. The court below accepted all the fact findings, but (differing from the referee) drew from them the conclusion of law that plaintiff was entitled to judgment.

Most of the items of this story have never been doubted, and might have been agreed to years ago. The outline of the tale may be ■ thus told, according to its legal effect. Hubbard Company contracted to build this lock in 1906. It was a small local corporation, and became unable to proceed on its own capital. The contract contained the well-known seizure clause of such government agreements. See 250 U. S. at page 53, 39 Sup. Ct. 393, 63 L. Ed: 835. When the contractor ran short, one Epps took up the work by the device of becoming a shareholder in and taking charge of Hubbard Company. Epps grew tired, and was succeeded by White Bros., and they in turn yielded to Ball; each taking over a stockholder’s interest in Hubbard Company and transacting business with the government engineers as Hubbard Company. This method of carrying on was known to said engineers.

Ball procured the property in suit, used it in going forward with the work, and when in 1909-he quit work, and the United States annulled the contract (never changed from one with Hubbard Company, and never assigned nor subcontracted), the United States engineers in charge seized the property in suit, in assumed compliance with the cited contract clause. Then they advertised for bids to complete the lock and dam, and defendant was the unfortunate successful bidder. Its contract provided that, if defendant so requested, the United States would take possession of and retain said property, and defendant would be permitted to use the same in prosecuting the work, for which there would “be charged a fair rental or purchase value, to be determined by the engineer officer in charge.” This contract further provided that:

“Since the 'ownership of the” said machines, etc., “is not free from doubt, the United States does not undertake to transfer title, does not guarantee physical possession and uninterrupted use, and will not defend any action or writ that may be instituted against the contractor concerning the same.”

By this time the United States l^ad already kept possession of the property claimed by Ball for upwards of six months; there is no finding that defendant ever “requested” its delivery, but it was delivered to defendant as lessee of the United States; and defendants used it until substantial completion of lock and dam, paying the government' $380 [711]*711a month therefor. When the work was done it was returned to the custody of the United States officials, in what condition (it consisted of machines and tools) does not appear. The master’s report finds as facts the following: -

“There was at this time (when Ball was doing work) a desire and intention on the part of Ball to undertake the execution of the work called for in said government contract (of Huhbard Company), and in pursuance of such intention and desire did, as hereinafter stated enter upon such work, and did so with the knowledge and acquiescence of said Hubbard, and with the knowledge and acquiescence of the representatives of the government of the United States in charge of said work.”
“Ball during said period (i. e., his work period) acquired knowledge of the provisions of said government contract; and the master finds that said Ball acted under said government contract, and acquiesced in the provisions thereof and performed said work thereunder.”
“The parties (i. e., Ball et al.) so as aforesaid actually doing the work and furnishing the materials for said lock and dam No. 6 respectively claimed and took for themselves under said government contract, through the medium of said Hubbard, the benefits and compensations accruing from the doing of said work and the furnishing of said materials. Said parties were not inter-meddlers therein, and they acted in entire good faith, in undertaking the work under said government contract, and when so undertaking it they respectively intended to be bound by the terms and provisions of said contract.”

This suit was begun after defendant had finished its contract, and after the property in question had been returned to the physical possession of the United States officials; that is, on January 30, 1911, the engineer in charge notified the Hubbard Company (addressing his letter to one of the Ball party, who was then president) that defendant’s use of the property as the government’s lessee would end on the following day, and—

“you will be given until February 28th to take possession of the same; should the machinery not be removed (by that time), such action will be taken as an indication on your part of your intention to abandon same.”

Ball did nothing; but on February 3, 1911, the same officer, obeying orders from the Chief of Engineers, U. S.'A., withdrew his notice. The orders from higher authority were to “retain possession of all plant till further advised by this office.” There is no competent proof, as well as no finding, that defendant ever requested the United States officials to seize the property in question. It was seized and in governmental possession months before (so far as this record shows) defendant ever saw or heard of it.

Some two months before defendants made their contract, Ball in writing demanded the property, and the engineer in charge refused to give it up. That no request to seize was ever made by defendant may be safely said on this record, but it is equally plain that defendant received the property with full knowledge of Ball’s demands. There is no finding, and no evidence, to show any demand on defendant, prior to suit, and when the writ issued herein,- on May 17, 1911, plaintiff well knew that the property alleged to have been converted by defendant was in the possession of the United States, which intended to keep it, until further orders from the Chief of Engineers, and these orders have (so far as shown) never been given.

[712]*712Thus is the question of liability now presented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. District of Columbia
117 U.S. 615 (Supreme Court, 1886)
Ball Engineering Co. v. J. G. White & Co.
250 U.S. 46 (Supreme Court, 1919)
Castle v. . Corn Exchange Bank
42 N.E. 518 (New York Court of Appeals, 1895)
Castle v. Corn Exchange Bank
26 N.Y.S. 1035 (New York Supreme Court, 1894)
Ball Engineering Co. v. J. G. White, Inc.
283 F. 496 (D. Connecticut, 1922)
Carr v. Gale
5 F. Cas. 118 (U.S. Circuit Court for the District of Maine, 1847)

Cite This Page — Counsel Stack

Bluebook (online)
298 F. 709, 1924 U.S. App. LEXIS 2701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-g-white-co-v-ball-engineering-co-ca2-1924.