J D DEVELOPMENT I, LLC v. ICS CONTRACTORS, LLC

District Court of Appeal of Florida·Decided September 30, 2022·No. 21-2759·Published

Opinion

DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT

JD DEVELOPMENT I, LLC,

Appellant,

v.

ICS CONTRACTORS, LLC,

Appellee.

No. 2D21-2759

September 30, 2022

Appeal from the Circuit Court for Collier County; Lauren L. Brodie, Judge.

David P. Fraser of Holmes Fraser, P.A., Naples, for Appellant.

Joseph A. Davidow and Krithika S. Venugopal of Willis & Davidow, LLC, Naples, for Appellee.

BLACK, Judge.

JD Development I, LLC, appeals from the final judgment entered in favor of ICS Contractors, LLC, for breach of contract following a jury trial. ICS Contractors asserted below that JD

Development had breached the parties' written contract—a bid for the performance of site development work—by failing to pay several invoices for work ICS Contractors had performed under the express provisions of the bid. On appeal, JD Development contends that because ICS Contractors failed to present any evidence establishing that the work identified in the unpaid invoices was within the scope of the bid, the trial court erred in denying its motion for directed verdict.1 We agree and therefore reverse the final judgment. JD Development raises several other issues on appeal, but because the trial court's failure to grant the motion for directed verdict is dispositive, we need not address those other issues.

1 JD Development uses the terms directed verdict and involuntary dismissal interchangeably. While the law applicable to motions for directed verdict and motions for involuntary dismissal is largely the same, see Thompson v. Fla. Cemeteries, Inc., 866 So. 2d 767, 769 (Fla. 2d DCA 2004) (citing Day v. Amini, 550 So. 2d 169, 171 (Fla. 2d DCA 1989)), when a case is tried before a jury, it is appropriate for a party to seek a verdict in its favor rather than to move for involuntary dismissal, see Tillman v. Baskin, 260 So. 2d 509, 510-11 (Fla. 1972); cf. George Anderson Training & Consulting, Inc. v. Miller Bey Paralegal & Fin., LLC, 313 So. 3d 214, 216 (Fla. 2d DCA 2021) (treating the directed verdict as an involuntary dismissal since the case was not tried before a jury).

On March 5, 2015, ICS Contractors submitted a unit price bid to JD Development for the performance of site development work in Collier County on a project called Legacy Estates. The bid was based on a site plan and two subsequent revisions to the site plan created by an engineering firm. The bid is comprised of eight categories of work plus a "Notes" section enumerating various work activities that were not included in the bid price. On May 6, 2015, JD Development accepted ICS Contractors' bid, and ICS Contractors began work on the project. On January 9, 2016, after ICS Contractors had completed three out of the eight categories of work set forth in the bid, JD Development terminated ICS Contractors from the project. Thereafter, ICS Contractors submitted an account statement, dated August 31, 2016, to JD Development reflecting a balance due to ICS Contractors in the amount of $182,827.15 for work that had been performed on the Legacy Estates project prior to ICS Contractors' termination. According to account statement, JD Development failed to remit full payment for several invoices that had been submitted by ICS

Contractors: invoice 1682, invoice 1699 (partially paid), invoice 1704, and invoices 1720 through 1725.

On September 12, 2019, after JD Development failed to pay ICS Contractors the outstanding balance set forth in the account statement, ICS Contractors filed a complaint against JD Development. The complaint was amended on March 10, 2020, and included five counts: breach of contract, account stated, open account, unjust enrichment, and quantum meruit. In the breach of contract claim, ICS Contractors alleged that JD Development breached the bid by failing to pay in full several invoices for work ICS Contractors had performed pursuant to the express written provisions of the bid. ICS Contractors sought $182,827.15 in damages. The bid was attached to the amended complaint, as was the account statement.2 A jury trial was held on July 27 and July 28, 2021. During trial, ICS Contractors conceded that invoices 1682 and 1704 had been paid by JD Development, leaving only invoice 1699 (to the

2 On May 26, 2020, JD Development filed its answer and affirmative defenses. It also raised three counterclaims which are not at issue in this appeal.

extent that a portion of it remained unpaid) and invoices 1720 through 1725 in dispute. As a result, the amount of damages sought by ICS Contractors was reduced to $105,214.84.3 Jason Clark, president of ICS Contractors, testified at trial.

During direct examination he explained that ICS Contractors had based its bid on the November 2014 site plan and two subsequent revisions to the site plan—dated January 2015 and February 2015, respectively. Although the site plan was revised several times after the bid had been prepared by ICS Contractors in March 2015— resulting in changes to the work to be completed by ICS Contractors—a subsequent, amended, or revised contract was never executed. As various work activities were completed on the project, ICS Contractors would submit invoices to JD Development. The account statement, which was admitted into evidence, reflected all of the invoices submitted by ICS Contractors to JD Development for the work ICS Contractors had completed on the Legacy Estates project prior to its termination. All of the invoices reflected in the

3 It is noted that the sum of the balances due in the disputed invoices is actually $105,213.95, not $105,214.84.

account statement—both paid and unpaid—were also admitted into evidence. Each invoice includes a brief description of what it is for under a heading titled "ACTIVITY."

Mr. Clark testified that the work activity identified in invoice 1699—crushing and removal of material followed by regrading—was performed pursuant to a "conversation on 8-26-2015."4 Invoices 1720 through 1725 include charges for renting equipment; invoice 1720 also includes a charge for hourly labor. Mr. Clark stated that the equipment was needed to perform additional work as a result of revisions to the site plan. An email sent by Mr. Clark to a representative of JD Development dated November 24, 2015, was admitted into evidence. According to Mr. Clark, he sent the email after Jim Drescher, the owner of JD Development, had requested that "the grades be raised on the retention ponds and . . . the rear berm." In the email, Mr. Clark confirmed that the additional work requested by Mr. Drescher was "not contract work." Mr. Clark explained that the work referenced in the email is reflected in the

4 Invoice 1699 states that the crushing, removal, and regrading was done pursuant to a conversation that occurred on August 28, 2015, not August 26, 2015.

November and December invoices, which would include invoices 1720 through 1723. No testimony was elicited during direct examination connecting the work activities set forth in the disputed invoices to any express provision of the bid.

Free access — add to your briefcase to read the full text and ask questions with AI

J D DEVELOPMENT I, LLC v. ICS CONTRACTORS, LLC, (Fla. Ct. App. 2022).

J D DEVELOPMENT I, LLC v. ICS CONTRACTORS, LLC (J D DEVELOPMENT I, LLC v. ICS CONTRACTORS, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Meruelo v. Mark Andrew of Palm Beaches, Ltd.
12 So. 3d 247 (District Court of Appeal of Florida, 2009)
Thompson v. FLORIDA CEMETERIES, INC.
866 So. 2d 767 (District Court of Appeal of Florida, 2004)
Day v. Amini
550 So. 2d 169 (District Court of Appeal of Florida, 1989)
Sims v. Cristinzio
898 So. 2d 1004 (District Court of Appeal of Florida, 2005)
Tillman v. Baskin
260 So. 2d 509 (Supreme Court of Florida, 1972)
Geico General Insurance Co. v. Hoy
136 So. 3d 647 (District Court of Appeal of Florida, 2013)
Amerifirst Federal Savings & Loan Ass'n v. Dutch Realty, Inc.
475 So. 2d 970 (District Court of Appeal of Florida, 1985)