J. A. Wynne Co. v. R. D. Phillips Construction Co.

468 F. Supp. 5, 43 A.F.T.R.2d (RIA) 1173, 1977 U.S. Dist. LEXIS 16781
CourtDistrict Court, M.D. Florida
DecidedMarch 22, 1977
Docket77-141-ORL-CIV-Y
StatusPublished
Cited by4 cases

This text of 468 F. Supp. 5 (J. A. Wynne Co. v. R. D. Phillips Construction Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Wynne Co. v. R. D. Phillips Construction Co., 468 F. Supp. 5, 43 A.F.T.R.2d (RIA) 1173, 1977 U.S. Dist. LEXIS 16781 (M.D. Fla. 1977).

Opinion

MEMORANDUM OPINION

GEORGE C. YOUNG, Chief Judge.

This cause came before the Court for hearing on plaintiffs’ motion for summary judgment against the United States of America, on the cross motion of the United States for summary judgment against plaintiffs, on defendant Keene’s motion for summary judgment against plaintiffs, and on the plaintiffs’ motion for default judgment against R. D. Phillips Construction Company, Inc. The cause arises under the Wrongful Levy Statute, 26 U.S.C. § 7426(a).

FACTUAL BACKGROUND

On April 1, 1976 the defendant Tenneco Oil Company entered into a written agreement with plaintiff J. P. Wynne Company, Inc. (Wynne), a general contractor, for the construction of a combination service station and convenience food store in Orange County, Florida (Exhibit “A” of the complaint). Under the terms of the agreement *7 Wynne was required to secure a performance and payment bond and it obtained such a bond from the plaintiff, Ohio Casualty Insurance Company (See Exhibit “B” of the complaint).

Wynne subcontracted with the defendant, R. D. Phillips Construction Company, Inc. (Phillips) for the concrete and asphalt paving portions of the project. Under their written agreement (Exhibit “H” of the complaint), Phillips was entitled to monthly progress payments calculated on the basis of invoices it submitted to Wynne.

In order to perform its side of the bargain, Phillips entered into subcontracts with the defendants Southern Paving Company and Keene Hauling, Inc. (Keene). Southern Paving did the asphalt work, and Keene supplied and delivered the necessary paving material.

In July Wynne received a progress payment from Tenneco. Under the subcontract, Wynne was obligated to pay a portion of the money received from Tenneco to Phillips as a progress payment. On July 12, 1976, Keene sent a cautionary notice to the owner indicating its intention to pursue its rights under the Florida Mechanics Lien Law. Fla.Stat. § 713.06(2)(a). Keene began work on July 13 and Southern Paving on July 22. Keene completed its work on July 20. On July 23, the Internal Revenue Service served Wynne with notice of levy of the $10,675.54 progress payment that Wynne was holding for Phillips. The IRS was seeking to satisfy Phillips’ unpaid tax assessments and penalties. Wynne surrendered said amount.

On August 2, Southern Paving completed its work and sent constructive notice to the owner under Florida Mechanics Lien Law. When Phillips did not pay Keene or Southern Paving, they filed mechanics liens on the Tenneco Oil construction site. Wynne and its surety, Ohio Casualty Insurance Company, transferred these liens to bonds pursuant to Fla.Stat. § 713.24 and then brought this action under the Wrongful Levy Statute.

WYNNE’S MOTION FOR SUMMARY JUDGMENT

Plaintiffs and the IRS have filed cross motions for summary judgment. It appears that there is no genuine issue as to material fact under Fed.R.Civ.P. 56. The basic issue that must be resolved is whether the levy of the IRS was wrongful under 26 U.S.C. § 6331(a). Section 6321 of the Internal Revenue Code of 1954 (26 U.S.C. § 6321) creates a lien in favor of the United States upon “all property and rights to property” belonging to the person who is liable for the unpaid tax. Section 6331(a) authorizes the Secretary of the Treasury to levy upon all property or rights to property on which there is such lien. The question in this case is whether the money that Wynne was holding and which Wynne admits was due to Phillips was property or a right to property belonging to Phillips, the delinquent taxpayer.

Wynne asserts that the money was not property of Phillips because Wynne was withholding the funds pursuant to paragraph 6 of their contract:

“Subcontractor covenants and agrees with Owner that Subcontractor will promptly pay all obligations for work, labor, services and/or materials incurred by the Subcontractor in the doing of the work required by the terms of this subcontract before any of such obligations become in default. If a person claiming under, by, through, or against the Subcontractor gives the Contractor or the Owner a cautionary notice, Contractor shall have the right to withhold from the progress payments hereinafter referred to so much of them as in the judgment of the Contractor and approved by the Architects is proper.” (emphasis added)

This provision plainly empowers Wynne to withhold progress payments due and owing to Phillips upon the filing of a cautionary notice by a sub-subcontractor. It gives Wynne, in other words, a kind of contractual set-off against Phillips. Compare Fostmeier Construction Co. v. United States, 327 F.Supp. 589, 591-2 (N.D.Cal.1971).

*8 Contractual provisions such as these are commonly found in construction contracts because they afford the general contractor some measure of protection from double liability. The contractor will typically be obligated to the owner to see that sub-subcontractors are paid and he will usually have secured a payment and performance bond conditioned upon his payment of such obligations. See Fla.Stat. § 713.02(6); 22 Fla.Jur., Mechanics Liens, § 54 (1977 Supp.). The general contractor, then, will ultimately bear the loss if his subcontractor does not pay sub-subcontractors. Such was the case here, as the surety bonds and Wynne’s contract with Tenneco demonstrate.

Wynne was exercising its right to withhold progress payments when, on July 23, the IRS notice of levy was served. Prior to that date, Tenneco had paid Wynne a sum of money for partial completion of the project. A portion of this money was owed to Phillips but before Wynne could make payment, one of Phillips’ subcontractors, Keene, filed on July 20 a cautionary notice pursuant to the Mechanic’s Lien Law. Keene’s notice triggered the right under the subcontract to “withhold from the progress payments ... so much of them as in the judgment of the Contractor and approved by the Architects is proper.” Wynne had the right to refuse to pay Phillips to avoid the possibility of double liability should Phillips be unable to pay its subcontractors. It was for this reason that Wynne was in possession of the money on July 23.

Since Wynne had exercised its contractual right, the question is whether that right gave it a sufficient interest in the funds seized to entitle it to bring a recoupment action under the Wrongful Levy Statute. The Court concludes that it did.

One’s interest in property seized by the IRS need not be that of an owner in order to sue for its repossession under the Wrongful Levy Statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
468 F. Supp. 5, 43 A.F.T.R.2d (RIA) 1173, 1977 U.S. Dist. LEXIS 16781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-wynne-co-v-r-d-phillips-construction-co-flmd-1977.