Its v. Com., Dept. of Env. Res.
This text of 406 A.2d 1020 (Its v. Com., Dept. of Env. Res.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
INTERSTATE TRAVELLER SERVICES, INC. a/k/a Tri-County Oil Company, Inc., the Township of Boggs and Boggs Township Authority, Appellants,
v.
COMMONWEALTH of Pennsylvania, DEPARTMENT OF ENVIRONMENTAL RESOURCES and Mid-Centre County Authority, Appellees.
Supreme Court of Pennsylvania.
*537 *538 Ronald M. Katzman, Harrisburg, for appellant Interstate Traveller Services, Inc., etc.
David A. Flood, Bellefonte, for appellant Tp. of Boggs, etc.
John P. Krill, Jr., Asst. Atty. Gen., Harrisburg, for Dept. of Environmental Resources.
Robert Moore, Harrisburg, for Mid-Centre County Authority.
Before EAGEN, C.J., and O'BRIEN, ROBERTS, NIX, MANDERINO and LARSEN, JJ.
OPINION
PER CURIAM.
The Court being equally divided, the order is affirmed.
LARSEN, J., filed an opinion in support of affirmance in which EAGEN, C.J., and O'BRIEN, J., join.
MANDERINO, J., filed an opinion in support of reversal in which ROBERTS and NIX, JJ., join.
OPINION IN SUPPORT OF AFFIRMANCE
LARSEN, Justice.
On January 17, 1977, appellants, Interstate Traveller Services (ITS), Township of Boggs (township) and Boggs Township Authority (township authority) filed a complaint in *539 equity in the Commonwealth Court seeking, inter alia, to enjoin appellees, the Department of Environmental Resources (DER) and the Mid-Centre County Authority (regional authority) from compelling the township to participate in the construction of a regional sewage facility. The complaint alleged that appellees were conspiring to interfere with contractual rights of appellants and were engaged in a course of conduct calculated to harass, threaten and coerce appellants into a breach of the contract entered into among themselves and DER.
Appellees filed preliminary objections to the complaint, one of which was that appellants had failed to exercise or exhaust statutory remedies existing at law and were therefore precluded from seeking redress of their alleged injuries through a complaint in equity. Commonwealth Court agreed and dismissed the suit. That court found the gravamen of the complaint was that appellants had been aggrieved by two official actions of DER, namely: (1) an order issued on October 12, 1973 compelling the township and other local governmental bodies in the area to negotiate and enter into agreements to provide for a regional sewage system, and (2) a permit issued by DER to the regional authority authorizing construction of a regional facility. The Commonwealth Court ruled that it had no jurisdiction to entertain the suit since appellants did not appeal to the Environmental Hearing Board (EHB) from said order and permit[1]; thus, they failed to exhaust their statutory remedies. I agree, and would affirm the dismissal.
For the purpose of determining whether the lower court properly sustained DER's preliminary objections, the reviewing court must assume the truth of the facts averred in the petition for review. Feingold v. Bell of Pennsylvania, 477 Pa. 1, 383 A.2d 791 (1977). Moreover, a case should be dismissed on preliminary objections only where the dismissal *540 is clearly warranted and free from doubt. Baker v. Brennan, 419 Pa. 222, 213 A.2d 362 (1965). The facts as summarized from the petition for review are as follows:
Some time prior to October 10, 1973, appellant ITS filed an application with DER for a permit to construct a sewer plant to service certain enterprises in the area of the Exit Interchange of Route 80 in Centre County. DER insisted that any sewer treatment facility erected in the area should be under the control and supervision of Boggs Township. Thus, the township became involved in the negotiations.
On October 10, 1973, ITS, DER and the township entered into an agreement which provided that ITS would construct a sewer plant according to the plans and specifications approved by DER and the township.[2] The agreement also provided that, upon completion, the plant be conveyed by ITS to the township or a newly created township authority. On October 16, 1973, DER issued a permit to ITS allowing construction of the local facility to begin. Pursuant to the terms of the written agreement, ITS conveyed the completed facility to the township authority on October 7, 1975, subject to the payment of a $250,000 note. The township authority then leased the facility to the township. As required by the written agreement, the township adopted the necessary enabling ordinances imposing user charges and making mandatory connection to the sewage collection system of all properties within the required distances.
On October 12, 1973, DER issued an order requiring the township and other area municipalities to participate in *541 regional sewage planning.[3] Thereafter, in 1975 or 1976, DER issued a permit to the regional authority approving construction of a regional sewage facility.[4] After this permit was issued, the regional authority decided to change the location of the regional facility to a site which is less than one mile from the ITS facility. Appellants argue that the effect of constructing a sewage facility at this location would be to render the ITS facility and its lines useless.
I have carefully analyzed appellant's complaint in equity and am convinced, as was the Commonwealth Court, that the gist of the conduct complained of was official DER actions conducted pursuant to its statutory authority.[5] Although the complaint speaks in terms of harassment, coercion and interference with contractual rights, it is clear from the complaint that DER (and the regional authority) exercised *542 administrative judgment that was allegedly injurious to appellants, and it is this judgment which is being collaterally challenged by means of the complaint in equity. Whether or not DER's authority was exercised improperly is a matter that could have and should have been heard by the EHB, the body with the requisite administrative expertise to competently resolve the matter in the first instance.
The Administrative Code of 1929, as amended (see note 2, supra) provides, in relevant part:
(a) The Environmental Hearing Board shall have the power and its duties shall be to hold hearings and issue adjudications . . . on any order, permit, license or decision of the Department of Environmental Resources.
.....
(c) Anything in any law to the contrary notwithstanding, any action of the Department of Environmental Resources may be taken initially without regard to the Administrative Agency Law, but no such action of the department adversely affecting any person shall be final as to such person until such person has had the opportunity to appeal such action to the Environmental Hearing Board; provided, however, that any such action shall be final as to any person who has not perfected his appeal in the manner hereinafter specified. 71 P.S. § 510-21(a) and (c) (emphasis added).
Free access — add to your briefcase to read the full text and ask questions with AI