Isakson v. Vincequere

598 N.E.2d 1140, 33 Mass. App. Ct. 281, 1992 Mass. App. LEXIS 760
CourtMassachusetts Appeals Court
DecidedSeptember 9, 1992
Docket90-P-1136
StatusPublished
Cited by4 cases

This text of 598 N.E.2d 1140 (Isakson v. Vincequere) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Isakson v. Vincequere, 598 N.E.2d 1140, 33 Mass. App. Ct. 281, 1992 Mass. App. LEXIS 760 (Mass. Ct. App. 1992).

Opinion

Perretta, J.

This appeal arises' out of an action brought in the Housing Court for damages for breach of contract and a violation of G. L. c. 93A. A jury awarded damages to the plaintiff on the contract claim, and the trial judge, finding and concluding that the breach was an unfair act which was both knowing and wilful, doubled the jury’s award and assessed fees and costs. The question of subject matter jurisdiction is raised for the first time on appeal and we conclude that the Housing Court lacked subject matter jurisdiction over the controversy and order that the judgment be vacated.

1. The controversy. There was evidence to show that the plaintiff hired the defendant to build and frame the outer structure of an addition to his house, a garage and family-room. The foundation for the addition had been in place at the time the plaintiff purchased his house several years ear- *282 Her. The parties agreed that the plaintiff would be responsible for providing the materials for the project, which was to be completed within four weeks. The contract price was $8,400, to be paid to the defendant for his labor in four weekly installments of $2,100.

Two weeks into the project a dispute arose as to whether certain work was covered under the contract or whether it was “additional.” The defendant was of the view that certain items, such as a four-foot overhang and windows in the rear of the structure, were extras for which he was entitled to additional compensation. The plaintiff claimed that these items were included within the contract and refused to pay anything above the contract price.

Work came to a halt. The plaintiff sent the defendant a demand letter under G. L. c. 93A, § 9. The defendant responded that he would do the extra work if the plaintiff either paid him additional compensation or renegotiated the contract. The plaintiff then hired a second contractor to complete the addition to the house. Because of other commitments, this contractor and his assistants could work for the plaintiff only at night and on weekends and holidays. It took over two months for the addition to be finished at a cost of almost $10,000.

In instructing the jury on the contract claim, the trial judge stated that, if they found that the defendant was in breach of his obligation, the plaintiff would be entitled to the “reasonable cost of completing the contract less such part of the contract price as has not been paid.” After the jury awarded the plaintiff $3,200, the trial judge took up the count brought under c. 93A. He found and concluded that the defendant’s breach was an “unfair act since he knew the difficulty the plaintiff would have finding a replacement and that the exposure of the incomplete job to the elements could well produce irreparable damage” and that the breach was “both knowing and willful.”

2. Subject matter jurisdiction. To determine whether the Housing Court had jurisdiction over this controversy, we look *283 to G. L. c. 185C, § 3, as appearing in St. 1987, c. 755, § 3. 1 The plaintiff argues that three bases for jurisdiction can be found in the statute which, as relevant, reads: “The . . . housing court . . . shall have . . . jurisdiction ... of all civil actions . . . under the provisions of common law and of equity ... as is concerned directly or indirectly with [1] the health, safety, or welfare, of any occupant of any place used, or intended for use, as a place of human habitation ... [2] the possession, condition, or use of any particular housing ac-comodations ... or services . . . furnished in connection therewith ... [3] ... all housing problems, including all contract and tort actions which affect the health, safety and welfare of the occupants or owners thereof. . . .”

Conceding from the outset that his claim does not involve any issue of “health” or “safety,” the plaintiff focuses on “welfare.” He argues that the inconvenience of the off-hours work on the addition and the apprehension concerning the exposure of the unfinished project to the elements created a “very tense situation in the household” which, in turn, affected his and his family’s “welfare.”

We do not minimize the disruption and inconvenience that can be caused by a contractor’s refusal or inability to complete a project in accordance with the terms of a contract. The question before us, however, is not whether the plaintiff has stated a cause of action. Rather, it is whether he has brought his action in the correct forum.

In asserting that his claim was properly brought in the Housing Court, the plaintiff relies upon an overly broad definition of “welfare” as “the state of faring or doing well[;] ... a state characterized ... by good fortune, happiness, well-being, or prosperity [;] ... the state or condition (as of a person . . .) in regard to well-being. . . .” Webster’s Third New International Dictionary, Unabridged (1981), at 2594. As used in G. L. c. 185C, § 3, however, the words *284 “health, safety, or welfare” are to be construed narrowly in order to carry out the purpose for which the statute was enacted. See Police Commr. of Boston v. Lewis, 371 Mass. 332 (1976); Hass v. Breton, 377 Mass. 591 (1979); LeBlanc v. Sherwin Williams Co., 406 Mass. 888 (1990); Ryan v. Ke-hoe, 408 Mass. 636 (1990).

These cases lead us to conclude that, although the plaintiffs dispute with the defendant might have affected his “welfare” in the broad and general sense of his happiness and emotional state of well-being, that is not the type of housing claim which the Legislature intended the Housing Court to address. There was nothing about the physical condition of the unfinished addition which affected the plaintiffs “welfare.”

Additionally, the plaintiffs complaint is not concerned with the “possession, condition, or use of any particular housing accommodation [ ] ... or services . . . furnished in connection therewith.” The only issues raised on the pleadings were whether the plaintiff was entitled to recover the difference between the contract price and the reasonable cost of completing the addition and whether the defendant’s refusal to finish the project without additional payment was an unfair act. There was no question concerning the condition of the premises. It was undisputed that the defendant abandoned the project before the addition was finished and that the work had been completed by another before the suit was commenced.

Further, the fact that the subject of the contract was a house does not make a breach of that contract a “housing problem[]” within the comprehension of c. 185, § 3. To conclude on such a slim basis that jurisdiction could attach in the Housing Court “would be to dilute the expertise of that court and to delay the resolution of disputes properly before it.” Hass v. Breton, 377 Mass, at 601.

The legislative and judicial history of c. 185C, § 3, was discussed recently and at length in LeBlanc v. Sherwin Williams Co., 406 Mass. 888 (1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. Miller
913 N.E.2d 379 (Massachusetts Appeals Court, 2009)
Davignon v. Clemmey
176 F. Supp. 2d 77 (D. Massachusetts, 2001)
ROPT Ltd. Partnership v. Katin
729 N.E.2d 282 (Massachusetts Supreme Judicial Court, 2000)
McElligott v. Lukes
674 N.E.2d 1108 (Massachusetts Appeals Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
598 N.E.2d 1140, 33 Mass. App. Ct. 281, 1992 Mass. App. LEXIS 760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/isakson-v-vincequere-massappct-1992.