Irwin v. Odyssey Contracting Corp.

61 F. App'x 150
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 13, 2003
DocketNo. 01-2014
StatusPublished

This text of 61 F. App'x 150 (Irwin v. Odyssey Contracting Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irwin v. Odyssey Contracting Corp., 61 F. App'x 150 (6th Cir. 2003).

Opinion

GWIN, District Judge.

With this appeal, we examine two issues. First, we review whether the district court erred in granting Appellee Odyssey Contracting Corporation’s (“Odyssey”) motion for summary judgment. In granting the summary judgment motion, the district court held that Appellant Irwin could not establish causation beyond mere speculation and conjecture. Second, we decide whether the district court misconstrued the res ipsa loquitor doctrine under Michigan law. Specifically, we determine whether the district court erred when it held that Irwin did not satisfy the exclusive control element of the res ipsa loquitor doctrine.

We find that Appellant Irwin failed to establish causation beyond mere speculation. We also find that the district court properly rejected Irwin’s attempt to use the res ipsa loquitor doctrine to presume causation. Therefore, we affirm the district court’s grant of summary judgment to Appellee Odyssey.

I. Procedural Background

On November 19, 1998, Plaintiff Irwin suffered severe spinal injuries when a piece of falling plywood struck him while he was working on a bridge construction project. On August 6,1999, Irwin brought this personal injury action against Odyssey alleging that Odyssey negligently left plywood on the bridge deck, resulting in severe injury to Irwin.

On January 30, 2001, Odyssey moved for summary judgment, arguing that Irwin’s evidence was insufficient to satisfy the causation element of negligence. Specifically, Odyssey contended that a jury could not determine, without speculation and conjecture, that Odyssey was responsible for the plywood that blew off the bridge and struck Irwin.

On June 13, 2001, the district court granted Odyssey’s motion “because Plaintiffs evidence would require a jury to speculate regarding the source of the plywood.” In addition, the district court held that Irwin “faffed to show that his theory of causation was more likely than others.” The district court reasoned that “a jury would have to guess whether the plywood at issue came from Odyssey.”

The district court also rejected Irwin’s reliance on the res ipsa loquitor doctrine to presume causation in fact, reasoning that he could not establish that Odyssey had exclusive control over the plywood that struck Irwin. Specifically, the district court held that “no one knows where the plywood in this case was located before it hit Plaintiff and no one knows whether Odyssey was the source of that plywood.”

On July 11, 2001, Irwin filed a timely notice of appeal.

II. Factual Background

S.E. Johnson Corporation, Inc. (“S.E.Johnson”), a construction contractor, employed Irwin as a laborer. S.E. Johnson was the general contractor on the Blue Water Bridge Project, a restoration project involving the Blue Water Bridge, a major international crossing between Michigan and Ontario.

Four unions, carpenters, laborers, cement masons, and ironworkers, worked for S.E. Johnson on the bridge project. Additionally, S.E. Johnson employed Defendant Odyssey as a subcontractor to do sand[152]*152blasting and painting on the bridge. While doing this work, Odyssey constructed containment areas made of scaffolding and enclosed with tarps. To keep the tarps from blowing around on the bridge deck, Odyssey generally secured the tarps with two-by-four furring strips. All the other various workers used plywood to secure their tarps. Further, they all used plywood of the same type and size. Regardless of the type of material used to secure the tarps, neither Odyssey nor the other trades working for S.E. Johnson could nail it down because union regulations required that union carpenters do this job.

On November 19, 1998, Irwin was underneath the bridge, on the south side, rolling up an extension cord. He was facing south while the wind was blowing from the southwest. The bridge was sixty feet overhead. As he was working underneath the bridge, a fifteen-pound piece of plywood flew off the bridge and struck Irwin in the neck, severely injuring his spinal column.

Irwin claims that at the time of the accident. Odyssey’s employees were working on the bridge directly overhead him. Conversely, Odyssey says that its workers had begun work on the north side of the bridge, not on the south side. Irwin, however, asserts that the Odyssey workers moved their materials to another part of the bridge after the accident, not before. Irwin further alleges that Odyssey’s employees were the only subcontractors working on the bridge that day. It is undisputed, however, that plywood and debris littered the bridge.

James Pike, Michigan Construction Safety Officer, investigated the accident the day after it happened. According to his report, no one at the site saw the plywood leave the bridge. S.E. Johnson’s internal investigation confirms this fact. Also, no one identified the plywood as belonging to Odyssey. In fact, Pike’s investigation revealed that many workers, including Odyssey, secured their tarps with plywood of the same size and type as the plywood that struck Irwin. Moreover, pieces of that type of plywood littered the entire bridge deck, resulting in Pike’s noting that the bridge deck was “messy.” Pike attributed the messy bridge to layoffs in the segment of S.E. Johnson’s staff responsible for clearing the bridge of plywood debris. These layoffs occurred before the accident. After Pike’s investigation, the Michigan Occupational Safety and Health Department cited unsafe working conditions created by the labor disputes involving S.E. Johnson as the cause of the accident. It did not cite Odyssey.

On August 6,1999, Irwin brought a negligence claim against Odyssey.1

III. Summary of Arguments

Irwin’s appeal rests on two grounds. First, he contends that he presented sufficient evidence to satisfy the cause-in-fact prong of his negligence claim. Second, Irwin argues that the district court improperly applied the Michigan law of res ipsa loquitor when it rejected his attempt to use the doctrine to create an inference of causation. According to Irwin, contrary to the district court’s decision, the res ipsa loquitor doctrine does not require exclusive control over the instrumentality of the injury.

TV. Analysis

A. Standard of Review

“This Court reviews a district court’s grant of summary judgment de novo.” [153]*153Davis v. McCourt, 226 F.3d 506, 511 (6th Cir.2000).

Fed.R.Civ.P. 56(c) provides that summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Celotex v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Thus, as long as the movant has met its initial burden of “demonstrat[ing] the absence of a genuine issue of material fact,” id. at 323, 106 S.Ct. 2548, the nonmoving party then “must set forth specific facts showing that there is a genuine issue for trial.” Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Rose v. McMahon
158 N.W.2d 791 (Michigan Court of Appeals, 1968)
Jones v. Porretta
405 N.W.2d 863 (Michigan Supreme Court, 1987)
Selph v. Evanoff
184 N.W.2d 282 (Michigan Court of Appeals, 1970)
Skinner v. Square D Co.
516 N.W.2d 475 (Michigan Supreme Court, 1994)
Buckeye Union Fire Insurance v. Detroit Edison Co.
196 N.W.2d 316 (Michigan Court of Appeals, 1972)
Haliw v. City of Sterling Heights
627 N.W.2d 581 (Michigan Supreme Court, 2001)
Babula v. Robertson
536 N.W.2d 834 (Michigan Court of Appeals, 1995)
Jordan v. Whiting Corp.
240 N.W.2d 468 (Michigan Supreme Court, 1976)
Dedes v. Asch
590 N.W.2d 605 (Michigan Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
61 F. App'x 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irwin-v-odyssey-contracting-corp-ca6-2003.