Irwin Company, Inc. v. 3525 Sage Street Associates, Ltd. v. Robert B. Reich, U.S. Department of Labor, Secretary of Labor, Third-Party

37 F.3d 212, 2 Wage & Hour Cas.2d (BNA) 647, 1994 U.S. App. LEXIS 30690, 1994 WL 574172
CourtCourt of Appeals for the Third Circuit
DecidedNovember 4, 1994
Docket92-2929
StatusPublished
Cited by1 cases

This text of 37 F.3d 212 (Irwin Company, Inc. v. 3525 Sage Street Associates, Ltd. v. Robert B. Reich, U.S. Department of Labor, Secretary of Labor, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irwin Company, Inc. v. 3525 Sage Street Associates, Ltd. v. Robert B. Reich, U.S. Department of Labor, Secretary of Labor, Third-Party, 37 F.3d 212, 2 Wage & Hour Cas.2d (BNA) 647, 1994 U.S. App. LEXIS 30690, 1994 WL 574172 (3d Cir. 1994).

Opinion

EDITH H. JONES, Circuit Judge:

A subcontractor who underpaid employees appeals the district court judgment ordering it to tender, to the Department of Labor for distribution to the underpaid employees, mo *213 nies that had been withheld by the general contractor, 826 F.Supp. 1067. We affirm,

BACKGROUND

The facts in this case are undisputed. 3525 Sage Street Associates, Ltd. (Sage) was the developer, and later prime contractor, on a federally-assisted construction project, whose loan was insured by the Department of Housing and Urban Development (HUD). Irwin Company was hired as a plumbing and air conditioning subcontractor. As part of its loan contract with the government, Sage agreed that laborers and mechanics would be paid prevailing wages as determined by the Secretary of Labor pursuant to the National Housing Act, 12 U.S.C. § 1715e(a) and the Davis-Bacon Act, 40 U.S.C. § 276a. Contractors and subcontractors hired by Sage agreed in their contracts to pay prevailing wages under these terms.

Irwin completed its contract May 23, 1986. On October 8, 1986, Sage paid off the HUD loan on the project. Pursuant to the terms of Irwin’s subcontract, however, Sage withheld approximately ten percent of the contract price as retainage pending Sage’s approval of Irwin’s work and its satisfaction that Irwin “ha[d] fully performed [its] obligations,” which included paying its laborers the requisite prevailing wages. For present purposes, the withheld payments equalled $107,522.

At some point — it is not clear when — the Department of Labor investigated Irwin’s employment practices under these subcontracts and determined that Irwin had underpaid its employees. On May 12, 1988 that Department sent Irwin and Sage notification letters regarding its findings. Sage, subject to joint and several liability for Irwin’s underpayments, did not request a hearing and the investigation findings became final as to it. Significantly, Sage agreed with DOL to release the retainage monies it was holding on Irwin’s subcontract, but Irwin resisted this solution. Irwin requested an administrative hearing to contest the findings. On November 1, 1990, the administrative law judge (ALJ) issued his decision and order finding Irwin liable for underpayments in an amount totalling $136,024.72. Irwin did not appeal this decision, which is now final and unappealable.

Meanwhile, in December 1986 Irwin had filed an action in Texas state court against Sage for release of the payments that Sage had retained. Sage tendered the disputed monies to the court, apparently in January 1988. Irwin then posted a combination of bonds and a letter of credit (which later expired) and obtained control of the tendered monies. In December 1991 Sage brought in the Secretary of Labor as a third-party defendant. In January 1992 the Secretary removed the case to federal court.

In district court, Irwin and the Secretary presented cross motions for summary judgment. The district judge held that Sage had retained the disputed money for the benefit of Irwin employees, that Irwin did not have a property interest in the money, and that the instant case was therefore essentially a collection suit based on liability found by the ALJ.

DISCUSSION

Irwin presents two grounds for reversal of the district court’s summary judgment. Irwin asserts that the Secretary is barred from claiming this money by the statute of limitations, and more broadly, that the Secretary has no statutory or regulatory authority to pursue this action.

Statute of Limitations

Actions for unpaid minimum wages brought under the Davis-Bacon Act are governed by section 6(a) of the Portal-to-Portal Act, which requires that a claim be commenced within two years after the cause of action accrued, except in a cause of action arising out of a willful violation, which must be commenced within three years after the cause of action accrued. 29 U.S.C. § 255(a). Because Irwin completed its contract by May 23, 1986, Irwin contends that any claim the Secretary had was proscribed after May 23, 1989 at the latest.

The Secretary asserts that this action technically is brought not under the Davis-Bacon Act, but under the National Housing Act pursuant to regulations issued by the Secre *214 tary. See 29 C.F.R. § 5.5 (1993). The Department issued these regulations pursuant to Reorganization Plan No. 14, prepared by President Truman in 1950 pursuant to a declaration by Congress. Under the Reorganization Plan, the President directed the Secretary to promulgate and coordinate administrative matters for the Davis-Bacon Act and its related statutes. This ease arises under one of those Related Acts, the National Housing Act of 1934. 12 U.S.C. § 1715e(a) (requiring as a prerequisite to obtaining federal loan or mortgage insurance that contractors certify that laborers and mechanics “have been paid not less than the wages prevailing in the locality ... as determined by the Secretary of Labor, in accordance within the Davis-Bacon Act”)

The only case cited to us discussing this issue is Glenn Electric Co. v. Donovan, 755 F.2d 1028 (3d Cir.1985), which held that the Portal-to-Portal Act applied to actions brought under the Davis-Bacon Act, but not to actions brought under the Related Acts, ie., those that refer to prevailing wages as determined under the Davis-Bacon Act. Glenn Electric rejected the argument that reference in the Related Acts to the Davis-Bacon Act incorporated the Davis-Bacon Act in toto and held that as a matter of statutory construction, the limitations provisions in the Portal-to-Portal Act did not extend to the Related Acts. Instead, the Third Circuit held that actions brought under the Related Acts are subject to the general limitations period for actions founded on contracts brought by the government, 28 U.S.C. § 2415, which is ordinarily six years. There is an exception to the six-year limitation where the government raises a claim against an opposing party which has itself brought a claim arising out of the same transaction or occurrence. 28 U.S.C. § 2415(f). The Secretary contends that we should follow the Third Circuit and apply § 2415.

Irwin presents sensible arguments for universal application of the Portal-to-Portal Act limitation period in all cases contesting Davis-Bacon prevailing wages. The regulations explicitly govern both the Davis-Bacon Act and Related Acts. 29 C.F.R. § 5.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicolas v. Deposit Guaranty National Bank
182 F.R.D. 226 (S.D. Mississippi, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
37 F.3d 212, 2 Wage & Hour Cas.2d (BNA) 647, 1994 U.S. App. LEXIS 30690, 1994 WL 574172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irwin-company-inc-v-3525-sage-street-associates-ltd-v-robert-b-ca3-1994.