Iroquois Gas v. Candlewood Valley, No. Cv 91-0055194 (Jan. 30, 1991)

1991 Conn. Super. Ct. 119
CourtConnecticut Superior Court
DecidedJanuary 30, 1991
DocketNo. CV 91-0055194
StatusUnpublished

This text of 1991 Conn. Super. Ct. 119 (Iroquois Gas v. Candlewood Valley, No. Cv 91-0055194 (Jan. 30, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iroquois Gas v. Candlewood Valley, No. Cv 91-0055194 (Jan. 30, 1991), 1991 Conn. Super. Ct. 119 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM IN RE APPLICATION FOR IMMEDIATE ENTRY MOTION TO TERMINATE STAY The Petitioner Iroquois Gas Transmission System, L. P., a Delaware limited partnership, is a "natural gas company" within the meaning of Section 2(a) of the Federal Natural Gas Act,15 U.S.C. § 717a(6), and the holder of a certificate of public convenience and necessity, issued by the Federal Energy Regulatory Commission ("FERC") pursuant to that act, for the construction of a natural gas pipeline from the international border between the United States and Canada, through New York and Connecticut, and across Long Island Sound, to Long Island, New York where it will interconnect with an existing gas transportation system.

The Petitioner Iroquois Gas Transmission System, Inc. of CT Page 120 Connecticut ("Iroquois, Inc.") is a Delaware corporation wholly owned by Iroquois, which acts as Iroquois' agent, specifically with respect to acquisition of the Connecticut portion of the right-of-way. Iroquois, Inc. is a co-holder of the FERC certificate along with Iroquois for this purpose.

This petition is brought pursuant to C.G.S. Section 16-263 et seq. to acquire easement rights by eminent domain, and to gain immediate entry to the property in question. The respondents Candlewood Valley Country Club is the owner of the property over which the easement is sought. Iroquois has been refused permission to enter on the respondent's land to complete necessary preconstruction environmental and land surveys. It seeks immediate entry for this purpose, as well as for the purpose of constructing the pipeline. The gas will be transported to local distribution companies and power generators in the States of New York, Rhode Island, Massachusetts, New Hampshire, New Jersey, and Connecticut. The gas transported by Iroquois will be used for electric generation, cooking, space heating, industrial process energy, and for other purposes. Its fully operational capacity of 422,900 Mcf/d will provide the energy equivalent of 30 million barrels per year of imported oil.

The line is scheduled to be completed by January 1, 1992. To meet this completion date, construction must be underway in Connecticut by June 1, 1991. Delay of the start of construction beyond June 1st would mean that gas to be transported by Iroquois would not be available for the 1991-92 heating season in Connecticut. Connecticut's natural gas companies would be forced to increase their reliance on uneconomic substitutes, to the extent such substitutions are available, greatly increasing their ratepayer's costs; and might even be required to curtail deliveries to their customers. Moreover, any such delay could significantly increase the cost of building the pipeline, and therefore the ultimate cost of transporting the gas.

To begin construction by June 1, 1991, Iroquois must be able to complete its surveys and acquire the right to commence construction now. In this case, the landowner has refused to grant Iroquois even the access necessary to complete the environmental and centerline surveys, which Iroquois must complete before it can refine the location of its right-of-way and complete its construction planning. It is clear that access cannot await a determination of damages in these cases. Moreover, there will not be sufficient time for Iroquois to complete the proceedings for acquiring title by eminent domain to these and other properties which must be condemned, and for a court to determine the damages due, before construction must commence.

The Petitioner accordingly has invoked two state statutes CT Page 121 which provide two independent bases for the immediate relief it seeks — C.G.S. Sec. 16-267 and C.G.S. Sec. 16-50x(c). Each of these statutes authorizes this court, if it appears "that the public interest will be prejudiced by delay" to "determine that said applicant be permitted to enter immediately upon the property to be taken and devote it temporarily to the public use specified in such petition" upon deposit of a sum fixed by the court, to be applied to any assessment of damages which may be made1. This deposit is fixed by a preliminary estimate of the value of the property taken. Algonquin Gas Transmission Co. v. Coleman,17 Conn. Sup. 327, 332 (Super.Ct. 1951). (Id.)

The immediate entry right is available both to allow a condemnor access to a property for the purpose of completing surveys necessary to specifically identify the location of a right-of-way to be taken, Northeastern Gas Transmission Co. v. Benedict, 139 Conn. 36, 42, 43 (1952); and to allow it to actually construct the line while the eminent domain proceeding is under way. Algonquin Gas v. Coleman, 17 Conn. Sup. at 330 (1951). Since an appeal from a FERC certificate does not automatically stay its effectiveness, the statutory right of immediate entry is available notwithstanding that the FERC certificate may be subject to a motion for reconsideration or an appeal; only a federal court order staying the effectiveness of the certificate or setting aside the order issuing it will impair the condemnor's ability to resort to the immediate entry remedy, in which case the landowner will be entitled to compensation for damages from any exercise of the temporary rights which has by then occurred. Algonquin Gas Transmission Co. v. North Haven Fair Association, Inc., 20 Conn. Sup. 50 (Super.Ct. 1956).

The Connecticut portion of the Iroquois pipeline will be 24 inches in diameter, and made of one-half inch thick steel. Except for valves, sales meter stations, and some other appurtenant facilities, all of the pipeline facilities will be buried underground. The permanent right-of-way through Connecticut will generally be fifty feet wide. Iroquois will also required temporary construction rights for an additional twenty-five to fifty feet of right-of-way. Construction would involve nine sequential operations: clearing and grading of the right-of-way; trenching; stringing; pipe installation; backfilling; clean up and temporary erosion controls; hydrostatic testing; commissioning activities; and final clean-up and restoration. The full width of the construction right-of-way is necessary to accommodate these activities and to minimize or eliminate off right-of-way damages.

Pipelines can be constructed economically only if work crews can move along the length of a complete right-of-way, to perform their various operations in a smooth, continuous sequence. If the crews cannot move continuously along the right-of-way, but must CT Page 122 skip sections of it, and then return, the company pays a substantial penalty in time and expense.

Implicit in the issuance of FERC's Certification of Public Convenience and Necessity is a finding of public need for a supply of natural gas which the plaintiff is in a position to make available, and the economic feasibility of the project approved. Algonquin Gas Transmission Co. v. Coleman, 17 Conn. Sup. at 329. The Iroquois volumes are urgently needed not just to ameliorate the Northeast's dependence on foreign oil, but also to allow the Connecticut gas utilities to meet the needs of their existing customers. This need is an independently sufficient basis for immediate entry. Algonquin Gas Transmission Co. v. Coleman,17 Conn. Sup. at 330; Algonquin Gas Transmission Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northeastern Gas Transmission Co. v. Benedict
89 A.2d 379 (Supreme Court of Connecticut, 1952)
City of Glen Cove v. Utilities & Industries Corp.
216 N.E.2d 701 (New York Court of Appeals, 1966)
Algonquin Gas Transmission Co. v. North Haven Fair Ass'n
121 A.2d 872 (Connecticut Superior Court, 1956)
Algonquin Gas Transmission Co. v. Coleman
17 Conn. Super. Ct. 327 (Connecticut Superior Court, 1951)
City of Glen Cove v. Utilities & Industries Corp.
24 A.D.2d 766 (Appellate Division of the Supreme Court of New York, 1965)
Town of Massena v. Niagara Mohawk Power Corp.
87 Misc. 2d 79 (New York County Courts, 1976)
Tepper v. Tannenbaum
87 Misc. 2d 829 (New York Supreme Court, 1976)
Commissioner of Transportation v. V.A.S.T. Resources, Inc.
146 Misc. 2d 157 (New York Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iroquois-gas-v-candlewood-valley-no-cv-91-0055194-jan-30-1991-connsuperct-1991.