Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission

172 F.3d 84, 335 U.S. App. D.C. 266, 1999 U.S. App. LEXIS 6959, 1999 WL 202470
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 13, 1999
Docket98-1081
StatusPublished

This text of 172 F.3d 84 (Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission, 172 F.3d 84, 335 U.S. App. D.C. 266, 1999 U.S. App. LEXIS 6959, 1999 WL 202470 (D.C. Cir. 1999).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

Iroquois built a pipeline to bring gas from the United States-Canadian border down to the New York City region. The pipeline was so constructed that its capacity could be expanded rather cheaply; adding compressor stations would (or at least *85 could) bring down average cost. In early 1996 Iroquois held an auction to find out whether demand was strong enough to justify such an expansion. At the time its maximum tariff rate was $0.695/dekatherm (“DTh”).- Iroquois set the minimum bid for the additional capacity at $0.50/DTh, which it says without contradiction is the minimum rate at which it could recover the cost of building the compressor and yield a surplus that could be used to reduce rates for existing shippers. The only shippers submitting viable bids that met the $0.50 threshold were Coastal Gas Marketing Co. and ProGas U.S.A., Inc., which bid $0.50 and $0.54, respectively, for the new service.

Iroquois applied in mid-1996 for the cer-tifícate of public convenience and necessity required for construction of the compressor station. It proposed use of the auction rates for the new shippers, and, as we understand from oral argument, committed in the application to include a modest reduction in rates for the earlier shippers — not down to the auction levels — in its next rate case under § 4 of the Natural Gas Act, 15 U.S.C. § 717c. The Federal Energy Regulatory Commission issued a certifícate in mid-1997, see Iroquois Gas transmission System, L.P., 79 FERC ¶ 61,394 (1997), but denied Iroquois’s request to discount the rates below those charged existing shippers. Iroquois petitioned for rehearing on the discount issue, FERC denied the petition for rehearing, see Iroquois Gas Transmission System, L.P., 82 FERC ¶ 61,086 (1998) (“Order on Rehearing”), and this appeal followed.

While this appeal was pending, Iroquois accepted the certifícate and constructed the facilities. While construction proceeded, a FERC rate order reduced the maximum tariff rate to $0.46/DTh, below the rejected discount price. See Iroquois Gas Transmission System, L.P., 84 FERC ¶ 61,086 (1998), reh’g denied in relevant part, 86 FERC ¶ 61,261 (1999). On November 2, 1998 Iroquois began service to Coastal and ProGas at the new maximum rate.

* * *

The Commission argues that Iroquois is not “aggrieved,” as required for our jurisdiction both under the Constitution and the statute. See Lujan v. Defenders of Wildlife, 504 U.S. 555, 560, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992) (holding “injury in fact” element of “irreducible constitutional minimum” for standing); 15 U.S.C. § 717r(b) (providing that any party “aggrieved by an order issued by the Commission” may obtain judicial review). Two of the theories of non-aggrievement are frivolous. First, FERC suggests that because Iroquois objects to a floor under its rates rather than a ceiling over them, it suffers no injury. This seems to rest on the assumption that a firm can always increase its profits by raising prices — a proposition which, if true, would cause every firm to charge an infinite price. 1 The second frivolous theory is that because Iroquois accepted the certificate, it follows that it is not harmed. But in practical terms it seems self-evident that a firm may be worse off (or may reasonably perceive itself as worse off) under a conditioned certificate than under the same certificate without conditions. Its acceptance of the conditioned certificate may show that it would be still worse' off with no certificate at all, but that comparison is irrelevant. We have in fact previously heard the claims of parties who accepted conditioned licenses from FERC and objected to the conditions. See Transcontinental Gas Pipe Line Corp. v. FERC, 54 F.3d 893, 895-96 (D.C.Cir.1995).

More serious is FERC’s argument that the rate order mentioned above, reducing the maximum rate to less than the proposed discount rate, removed any effective injury. FERC has not worded this theory *86 as one of mootness, though it appears in effect to be such a claim: a supervening event has, in FERC’s theory, rendered the apparent injury a nullity. Yet FERC itself seems unready even to assert the factual prediction necessary for this to be true. At oral argument it was unwilling to say that the rate order established mootness, evidently sharing Iroquois’s belief that there is considerable probability that over the course of the current contracts the contested no-discount ruling will constrain Iroquois. Indeed, such constraint seems highly probable, perhaps certain. Iroquois contemplates additional compressor stations like the one whose addition precipitated this dispute. The ability to price the additional capacity incrementally — to set rates for newly available service higher than incremental cost but lower than those for existing shippers — seems likely to be extremely valuable to Iroquois in its efforts to exploit the business opportunities inherent in such capacity expansions. See Great Lakes Gas Transmission v. FERC, 984 F.2d 426, 430-31 (D.C.Cir.1993) (pipeline presently injured by “at-risk” condition in certifícate because of impact on negotiating strategy).

On the merits, it is common ground that the Commission has embraced the theoretical soundness of allowing certain kinds of rate discounting and has in fact formally approved such discounting, both in the form of generic grants of authority and in specific cases. See FERC Regulation of Natural Gas Pipelines after Partial Wellhead Decontrol, (“Order No. 436”), 50 Fed.Reg. 42,408, 42,451-55 (1985); Associated Gas Distributors v. FERC, 824 F.2d 981, 1009-13 (D.C.Cir.1987); Southern Natural Gas Co., 67 FERC ¶ 61,155 at 61,456 (1994) (on rehearing); see also Alternatives to Traditional Cost-of-Service Ratemaking for Natural Gas Pipelines, 74 FERC ¶ 61,076 at 61,238-42 (1996) (expressing Commission readiness to entertain, on a shipper-by-shipper basis, requests to implement negotiated rates, even where the pipeline has market power, where customers retain the ability to choose cost-of-service based tariff rate). Pointing to Southern, Iroquois argues that FERC’s controlling principle has been that if a competitively justified discount transaction will benefit the non-discount customers by bringing about reduced rates for the capacity they use, FERC' will approve the discount. FERC’s contention is that Iroquois’s application for a certificate presented a completely new problem, that of injury to existing customers as sellers in end-use markets; thus, it says, Southern and its other pro-discounting acts are in no way precedents against its decision here. We will return to this, the core issue, after briefly pursuing a preliminary substantive matter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
172 F.3d 84, 335 U.S. App. D.C. 266, 1999 U.S. App. LEXIS 6959, 1999 WL 202470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iroquois-gas-transmission-system-lp-v-federal-energy-regulatory-cadc-1999.