IRENE TABACHNIK & Another v. CT INSTALL AMERICA, LLC FRANCIS M. PANACHELLI & Another, Third-Party

CourtMassachusetts Appeals Court
DecidedFebruary 12, 2024
Docket23-P-0014
StatusUnpublished

This text of IRENE TABACHNIK & Another v. CT INSTALL AMERICA, LLC FRANCIS M. PANACHELLI & Another, Third-Party (IRENE TABACHNIK & Another v. CT INSTALL AMERICA, LLC FRANCIS M. PANACHELLI & Another, Third-Party) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IRENE TABACHNIK & Another v. CT INSTALL AMERICA, LLC FRANCIS M. PANACHELLI & Another, Third-Party, (Mass. Ct. App. 2024).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-14

IRENE TABACHNIK & another1

vs.

CT INSTALL AMERICA, LLC2; FRANCIS M. PANACHELLI & another,3 third-party defendants.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

In March 2018, the plaintiffs, Irene and Paul Tabachnik,

hired the defendant, CT Install America, LLC (CT Install), to

install new windows and sliding glass doors in their home. The

project did not go well. Six months later, in September 2018,

the Tabachniks filed this lawsuit alleging breach of contract,

negligence, and violations of G. L. c. 93A. CT Install then

brought a third-party complaint for, among other things,

indemnification and contribution, against the subcontractor,

Gerald Nolette, who CT Install had hired to do the work at the

1 Paul Tabachnik. 2 Doing business as Install America. 3 Jerry Nolette doing business as Nolette Construction. As is our custom, we use the spelling that appears on the complaint. Tabachniks' house.4 Following a jury-waived trial, a Superior

Court judge found in favor of the Tabachniks on all their

claims, and in favor of Nolette on CT Install's third-party

claims. CT Install appeals.

Background. We recite the facts, taken from the evidence

at trial, as follows. The Tabachniks purchased their home in

2016. The house was built in the 1950s and the Tabachniks

planned to renovate the house in stages. To this end, on March

3, 2018, the Tabachniks entered into a contract with CT Install

for the purchase and installation of new windows and patio

doors. The cost of the project was $16,000. The Tabachniks

paid a deposit of $5,000, with the remainder due on completion

of the work. With respect to the Tabachniks' den, the plan was

for CT Install to replace the existing windows with longer

windows. Although the Tabachniks believed that employees of CT

Install would perform the work, CT Install hired Nolette, a

local contractor, for the project. Soon after the project

began, the Tabachniks learned that the den wall was slanted due

to preexisting structural issues, and consequently, the new

windows could not be properly installed.

4 CT Install also brought counterclaims against the Tabachniks and additional third-party claims against Francis M. Panachelli, another subcontractor that had measured the windows. These claims have been dismissed, and no issues are raised as to them on appeal.

2 On May 23, 2018, Irene Tabachnik contacted CT Install,

expressed her concern that the longer windows would not be

appropriate due to the slant, and suggested that they instead

replace the windows with ones that would fit the current

openings. A representative from CT Install came out to the

Tabachniks' home and told Irene that CT Install could fix the

slant in the den wall and install the longer windows. The

Tabachniks agreed to proceed with the project, which now

included the additional work of fixing the den wall and the

removal of a stone floor in the den.

After improperly installing some windows, which were not

the same ones as the Tabachniks had originally ordered,5 and

having subcontractors begin demolition work to fix the slant,

which ultimately also involved the Tabachniks paying Nolette an

additional $2,000 to demolish the den floor they wanted to keep,

CT Install concluded that the structural issues were too

extensive to fix and abandoned the project.6

5 The contract called for the installation of new construction "677" windows. However, CT Install delivered a lesser grade of windows referred to as "177" windows. 6 There were also problems with the building permits and

workmanship. On August 22, 2018, the town's building inspector, Walter Avallone, conducted a site visit. He testified that he saw work that did not fall within the purview of the building permit for window replacement and that the windows that were installed were not done so properly. In addition, the windows did not have stickers on them, so Avallone could not verify whether they met the applicable energy code. As a result of his observations, Avallone rescinded the building permit. He

3 In September 2019, the Tabachniks hired a new contractor to

fix the problems. They asserted that they had incurred damages

in the following amounts: $50,000 paid to the new contractor;

$15,000 to replace a beam that CT Install had removed during the

demolition; the $5,000 deposit paid to CT Install; the $2,000 to

demolish the den floor; another $1,100 to rebuild the den floor;

and $2,750 for an architect.

The case proceeded to trial before a judge of the Superior

Court on August 22, 2022. On the first day of trial, the

parties filed a joint waiver of detailed findings of fact and

rulings of law, and, at the conclusion of the trial, the parties

submitted agreed on special questions for the judge to answer as

the finder of fact. In response to those questions, the judge

found that for each of the Tabachniks' claims, they suffered

damages in the amount of $76,650. Specifically, with respect to

the breach of contract claim, the judge answered "yes" to the

following two questions: (1) "Did the parties orally amend the

contract, Ex.1, to reframe the slanted wall in the den after the

discovery of the slanted wall?;" and (2) "Are the damages

incurred by the Plaintiffs to structurally repair the den,

consequential damages which the Plaintiffs are entitled to?"

The judge then doubled the damages after finding that the

testified that the "work was in violation of code. It was inferior. It wasn't workmanlike installed."

4 defendant's conduct was a willful or knowing violation of c.

93A. An amended judgment entered for $153,300, plus attorney's

fees, costs, and prejudgment interest.

Discussion. a. Breach of contract claim. CT Install

argues that the judge erred in finding that there was a valid

oral modification of the parties' contract requiring CT Install

to reframe the slanted wall because the modification was not

supported by proper consideration.7 This argument ignores the

$2,000 payment made by the Tabachniks to Nolette to demolish the

den floor, which CT Install maintained had to be done in order

to fix the wall, and the demolishment of the floor itself, which

the Tabachniks wanted to keep. Thus, while it is true, as CT

Install states, that the Tabachniks were not required to pay

additional money to CT Install to fix the den wall, the oral

modification was supported by adequate -– valuable --

consideration. See A.L. Prime Energy Consultant, Inc. v.

Massachusetts Bay Transp. Auth., 479 Mass. 419, 433 (2018).

b. Negligence claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wyman v. Ayer Properties, LLC
11 N.E.3d 1074 (Massachusetts Supreme Judicial Court, 2014)
EventMonitor, Inc. v. Leness
44 N.E.3d 848 (Massachusetts Supreme Judicial Court, 2016)
A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)
Berman v. Linnane
434 Mass. 301 (Massachusetts Supreme Judicial Court, 2001)
Sharon v. City of Newton
769 N.E.2d 738 (Massachusetts Supreme Judicial Court, 2002)
Berish v. Bornstein
437 Mass. 252 (Massachusetts Supreme Judicial Court, 2002)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
Hodas v. Morin
442 Mass. 544 (Massachusetts Supreme Judicial Court, 2004)
Klairmont v. Gainsboro Restaurant, Inc.
465 Mass. 165 (Massachusetts Supreme Judicial Court, 2013)
M. DeMatteo Construction Co. v. A. C. Dellovade, Inc.
652 N.E.2d 635 (Massachusetts Appeals Court, 1995)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Castricone v. Mical
909 N.E.2d 29 (Massachusetts Appeals Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
IRENE TABACHNIK & Another v. CT INSTALL AMERICA, LLC FRANCIS M. PANACHELLI & Another, Third-Party, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irene-tabachnik-another-v-ct-install-america-llc-francis-m-panachelli-massappct-2024.