Irelan v. Smoot

1928 OK 451, 270 P. 29, 132 Okla. 270, 1928 Okla. LEXIS 759
CourtSupreme Court of Oklahoma
DecidedJuly 3, 1928
Docket18447
StatusPublished
Cited by10 cases

This text of 1928 OK 451 (Irelan v. Smoot) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irelan v. Smoot, 1928 OK 451, 270 P. 29, 132 Okla. 270, 1928 Okla. LEXIS 759 (Okla. 1928).

Opinion

HEFNER, J.

A. M. Smoot, the defendant in error, plaintiff below, commenced this action in the district court of Creek county against O. M. Irelan, plaintiff in error, defendant below, to foreclosure a mechanic’s lien against a certain oil and gas leasehold estate.

The defendants O. M. Irelan and E. R. Minshall owned an undivided one-half interest in an oil and gas lease covering 35 acres of land. They entered into a written contract with P. J. King to drill a test well on the 35 acres, which provided:

First. That King would drill an oil and gas well on the 35 acres described in the contract to the Wilcox sand, unless oil or gas was found in paying quantities at a less depth.

Second. That King would furnish well rig, casing, tools, and all material at his own expense for drilling and completing the well.

Third. The consideration to be received by King for drilling the well and furnishing the casing, well rig, and tools, was the written assignment of an undivided one-fourth interest in the leasehold estate from Irelan and Minshall. The written assignment was to be placed in escrow and delivered to King when he had completed the well according to the contract.

Fourth. If the well proved to be dry, King was given the option to move all material from the well and lease, which he might place on the location for use in the performance of the contract.

Fifth. If the well produced oil or gas in paying quantities, the expense of further development and operation of the lease was to be borne proportionately among the parties according to their interest in the leasehold estate.

There is no controversy as to the facts. The plaintiff, Smoot, owned an interest in the land on which the well was drilling and P. J. King, the contractor, employed Smoot to haul the casing and well rig to the location on the leasehold estate. The plaintiff hauled the material pursuant to the contract with King between the dates of November 20, 1924, and March 21, 1925. He was not paid for the work.

Smoot filed a verified lien claim in the office of the court clerk on June 1, 1925. The statement was not filed within 60 days after the last date service was performed by Smoot under the contract with King for which the lien statement was filed. Notice of the filing of the lien was not served on the defendant Irelan.

Maxwell was the lessor of the defendantt *271 Irelan and the plaintiff, Smoot, acquired an interest in the land after the lease was executed and before the well was drilled. The lease expired by its own terms after the well was drilled, and the defendant Irelan executed and delivered a release of the same to Maxwell and Smoot at the request of Smoot. The casing had been removed from the lease by the plaintiff for the defendant Irelan and delivered to the owner before the plaintiff filed his mechanic’s lien; the well rig was moved off the premises after the suit was commenced against the defendant Irelan by the plaintiff, and the plaintiff was paid the sum of $152 by the defendant Irelan for moving the casing and well rig off the premises. At the time of the trial the easing and well rig were being used to drill another well about. 12 miles distant from the land described in the mechanic’s lien.

The plaintiff pleaded that he entered into an oral contract with the defendant F. J. King and W. A. Foyle, as trustees for the Mounds Frilling Syndicate, and with the Mounds Frilling Syndicate, a common-law trust, by virtue of which the plaintiff was to furnish necessary tools, wagons, trucks, and labor and haul certain lumber, etc. He alleged that the defendants O. M. Irelan and E. R. Minshall claimed some right in and to the oil and gas lease and in and to* the derrick, tools, casing, lines, and other equipment. He prayed for a judgment against the defendants P. J. King and W. A. Foyle, trustees for the Mounds Frilling Syndicate, and the Mounls Frilling Syndicate, a common-law trust. He does not allege he ever had any contract with the defendant Irelan; neither does he pray for a personal judgment against Irelan, and it was admitted in the trial of the case that he was not seeking a personal judgment against him.

Upon these pleadings and the facts here-inbefore stated, the trial court found that the sum of $192 for the service done by plaintiff and the sum of $50 for attorney’s fees were due from W. A. Foyle and P. J. King, contractor, as trustees for the Mounds Frilling Syndicate, and the Mounds Frilling Syndicate, to the plaintiff. The court also rendered judgment foreclosing the lien as to all defendants. There was no personal judgment rendered against the defendant Irelan. The only judgment affecting Irelan was the court ordered him to deliver possession of th'e casing and well rig to the sheriff of Creek county. Okla., for the purpose of sale to satisfy the indebtedness found due and owing to the plaintiff from W. A. Foyle and P. J. King, trustees. Prom this order, the defendant Irelan has appealed.

It is first necessary for us to determine whether or not the plaintiff was an original contractor or a subcontractor. If he was a subcontractor, it is admitted that he had no lien, because the claim was not filed within the time prescribed by law. If he was an original contractor, then the lien claim was filed within the time prescribed by law.

The plaintiff does not claim that he entered into any contract with the defendant Irelan. The contract was made with P. J. King, the contractor mentioned in the contract hereinbefore set out. It will be remembered, too, that the plaintiff on the trial of the case admitted that he was not seeking a money judgment against the defendant Irelan. He was, therefore, not proceeding on the theory that he was an original contractor with the defendant Irelan, because, if this had been true, he would have sought a personal judgment against him.

The plaintiff insists that he is an original contractor because the relationship existing between defendant and the co-owners of the lease was that of a mining partnership. In other words, his claim is that the contract under which King, the contractor, drilled the well constituted him a mining partner with the defendants Irelan and Minshall, If this contention be true, the plaintiff would be an original contractor. If it be not true, then, since his contract was only with King, the person who contracted to drill the well, he would necessarily be a subcontractor.

An undivided one-half interest in the lease was owned by the defendant Irelan and Minshall. King had no interest whatever in the lease at the time he was employed by Irelan and Minshall to drill the well. Under the contract King agreed to drill the well and also to furnish the well rig, casing, tools, and all material at his own expense for drilling and completing the same. The consideration King was to receive for his services was a written assignment of an undivided one-fourth interest in the leasehold estate from Irelan and Minshall. The assignment was placed in escrow. It was not to be delivered to him unless he did complete the well according to the contract. If the well was dry, King had the option to move all material from the well and lease *272 which he might: have placed thereupon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Hardwick
1960 OK 38 (Supreme Court of Oklahoma, 1960)
Cameron v. Speer
1937 OK 303 (Supreme Court of Oklahoma, 1937)
Elm Oil Co. v. Clark Lumber Co.
1937 OK 104 (Supreme Court of Oklahoma, 1937)
White v. A. C. Houston Lbr. Co.
1937 OK 58 (Supreme Court of Oklahoma, 1937)
Kissinger v. G. E. Burgher Oil & Gas Co.
1935 OK 897 (Supreme Court of Oklahoma, 1935)
McAnally v. Cochran
1935 OK 81 (Supreme Court of Oklahoma, 1935)
Josey Oil Co. v. Ledden
1933 OK 185 (Supreme Court of Oklahoma, 1933)
Crawford v. Tramonte
36 S.W.2d 269 (Court of Appeals of Texas, 1931)
Tidal Oil Co. v. Fullerton-Stuart Lbr. Co.
1929 OK 234 (Supreme Court of Oklahoma, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
1928 OK 451, 270 P. 29, 132 Okla. 270, 1928 Okla. LEXIS 759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irelan-v-smoot-okla-1928.