IPSCO Tubulars, Inc. v. Ajax TOCCO Magnathermic Corp.

779 F.3d 744, 2015 WL 898043
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 4, 2015
Docket13-3354, 13-3466
StatusPublished
Cited by7 cases

This text of 779 F.3d 744 (IPSCO Tubulars, Inc. v. Ajax TOCCO Magnathermic Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IPSCO Tubulars, Inc. v. Ajax TOCCO Magnathermic Corp., 779 F.3d 744, 2015 WL 898043 (8th Cir. 2015).

Opinion

BENTON, Circuit Judge.

IPSCO Tubulars, Inc. contracted for Ajax TOCCO Magnathermic Corp. to provide equipment to heat-treat steel pipe. IPSCO sued for breach of contract, gross negligence, and punitive damages. The district court found Ajax liable for breach of contract, awarding $5,162,298.55 in damages to IPSCO. Ajax appeals. IPSCO cross-appeals the dismissal of its gross negligence and punitive damages claims. Having jurisdiction under 28 U.S.C. § 1291, this court reverses and remands the breach-of-contract damages, and affirms in all other respects.

I.

IPSCO produces heat-treated steel pipe for use in the oil and gas industry. It manufactures larger-diameter casing and smaller-diameter tubing at grades defined by American Petroleum Institute (API) 5CT standards. In 2006, IPSCO took bids for induction heating (“austenitizing”), quenching, and pre-tempering equipment for its facility in Blytheville, Arkansas. IPSCO contracted for Ajax’s equipment despite concern about the design of Ajax’s quench.

IPSCO heat-treats electric resistance welded (ERW) casing and tubing formed according to IPSCO’s chemical recipe. Ajax’s equipment alters the structural properties of the pipe by heating it to a specified temperature range to form aus-tenite; cooling it to a specified range to form martensite (which has a high degree of strength and hardness); and reheating it to a specified range (adding ductility without compromising hardness). Exiting the Ajax equipment, the pipe is tempered, straightened, and inspected with other equipment. The contract requires Ajax’s equipment to convey pipe at certain speeds; for example, smaller tubing at 96 feet per minute (fpm). Ajax Quotation, “General Specifications.” See also Technical Specifications § 6.2 (“[The equipment] shall be capable of operating continuously to meet the throughput requirements .... ”).

*747 After installation in July 2007, Ajax’s quench did not perform properly. When IPSCO tried to process tubing at 96 fpm, the pipe had severe distortions, cracks, and inconsistency in as-quenched hardness. Pipe sometimes distorted so badly it wrecked in the quench and had to be removed manually. The pipe could not meet API specifications. To produce tubing without distortion, cracks, or inconsistency, IPSCO had to run the Ajax equipment at slower speeds, 35 to 50 fpm. Operating at reduced capacity, IPSCO began producing pipe for sale on September 27, 2007.

That fall, an Ajax expert began to troubleshoot. The quench was designed with two barrels pointing in the direction of product flow, using water to rapidly cool the pipe. Ajax’s expert identified several design flaws with the equipment and told IPSCO that the flume, which drains water from the quench, was not designed correctly by IPSCO’s contractor. Because of the small flume, IPSCO operated the quench at reduced water flows and pressures. On Ajax’s advice, IPSCO modified the flume by June 26, 2008, allowing operation at the recommended water flow.

Even after enlarging the flume, IPSCO had problems with severe distortion, quench cracks, and inconsistency (when processing at 96 fpm). In August 2008, IPSCO modified the quench itself by pointing the second barrel opposite the direction of product flow and changing the angle of the spray holes. This permitted IPSCO to produce pipe with minimal defects at a higher line speed, but still less than 96 fpm. Although Ajax’s expert continued to work with IPSCO to improve line speeds, Ajax never informed IPSCO of the suspected design flaws.

Still dissatisfied, IPSCO held a series of performance tests. Trials on casing in October 2008 were successful. Trials on tubing throughout 2009 were not successful due to distortion, cracks, and inconsistency at 96 fpm, even after IPSCO used the quench as designed and performed all Ajax-requested maintenance. In 2011, IP-SCO further modified the quench without Ajax’s advice. The modified equipment can process tubing at about 80 fpm with minimal defects.

IPSCO sued Ajax in February 2010, alleging breach of contract and gross negligence and seeking punitive damages. The district court granted judgment on partial findings for Ajax on gross negligence and punitive damages. After a bench trial, it found for IPSCO on the breach of contract claim, awarding $5,162,298.55 in damages. Ajax appeals liability and the damages calculations. IPSCO cross-appeals the dismissal of the gross negligence claim and punitive damages.

II.

Ajax contests the court’s interpretation of the contract, as well as the determination of breach and causation. After a bench trial, this court reviews a district court’s factual findings for clear error and its legal conclusions de novo. Speer v. City of Wynne, Ark., 276 F.3d 980, 984-85 (8th Cir.2002). See also Fed.R.Civ.P. 52(a)(6) (“Findings of fact ... must not be set aside unless clearly erroneous.... ”). A factual finding is clearly erroneous “only if it is not supported by substantial evidence in the record, if the finding is based on an erroneous view of the law, or if we are left with the definite and firm conviction that an error has been made.” Tadlock v. Powell, 291 F.3d 541, 546 (8th Cir.2002). “ "Where there are two permissible views of the evidence, the factfinder’s choice between them cannot be clearly erroneous.’ ” Lesch v. United States, 612 F.3d 975, 980 (8th Cir.2010), quoting Anderson v. City of Bessemer City, N.C., *748 470 U.S. 564, 574, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985).

A.

Ajax disputes the district court’s construction of the contract, asserting the contract makes no guarantees on defects, including cracking and distortion. IPSCO argues that the contract obligates Ajax to provide equipment capable of heat-treating pipe to API 5CT specifications. The court held that “Ajax breached its contractual obligations by failing to provide IPSCO with equipment that performed at the contractual rates and specifications.” It found, “Ajax knew that IPSCO required equipment that provided a uniform heating and cooling process” and “Ajax knew that IPSCO’s intended purpose was to create higher grades of pipe, instilled with certain qualities required for use in the oil and gas industry.”

Arkansas law governs the interpretation of the contract. See Murray v. Greenwich Ins. Co., 533 F.3d 644, 648 (8th Cir.2008), citing Erie R.R. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 82 L.Ed. 1188 (1938).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
779 F.3d 744, 2015 WL 898043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ipsco-tubulars-inc-v-ajax-tocco-magnathermic-corp-ca8-2015.