IPSCO Steel (Alabama), Inc. v. Blaine Construction Corp.

371 F.3d 141
Court of Appeals for the Third Circuit·Decided June 10, 2004·No. 03-2929, 03-2966·Published·Cited by 1 cases

Opinion

OPINION

GARTH, Circuit Judge.

The question which we must answer on this appeal is whether the District Court properly approved two settlement agreements among the litigants over the objection of one of the parties, Kvaerner U.S. Inc. (“Kvaerner”).. Because we hold that the District Court did not err, we affirm.

I.

A. Kvaerner

This litigation arose from a $550 million project involving the construction of a steel plant in Alabama. The project owner, IP-SCO Steel, Inc. (“IPSCO”) hired Kvaerner as its Project Manager. Under the Project Management Agreement (“PMA”), Kvaerner was responsible for recommending the contracts that IPSCO awarded to various subcontractors and suppliers. The PMA also specified that Kvaerner was “IPSCO’s agent for the purpose of administering Supplier Contracts and managing and coordinating Suppliers’ Work” and that, in connection with liens and disputes, Kvaerner was “to protect IPSCO’s interests at all times.”

*144 The PMA prescribed certain penalties and incentives. Kvaerner expressly warranted that the “Aggregate Cost” of the project would not exceed a “Guaranteed Maximum Price” of $182 million and that it would reimburse IPSCO for any costs in excess of $182 million. If, however, the Aggregate Cost came in below the Guaranteed Maximum Price, IPSCO promised to share 50% of the savings with Kvaerner.

The PMA anticipated that certain disputes would arise with the suppliers and it authorized Kvaerner to serve as IPSCO’s litigation manager. The relevant provision, which is Section 4.04(x) in the PMA, reads:

The Project Manager [Kvaerner] shall be primarily responsible for the management and resolution, either with its own resources or through legal counsel or other consultants, of claims and disputes between Suppliers and with Suppliers within the Guaranteed Portion of the Project ... provided that [Kvaerner] shall promptly inform and keep IPSCO fully informed of such claims and disputes and any negotiations or legal proceedings with such Suppliers ... [and] that any final resolution or settlement of such dispute shall be subject to IPSCO’s approval ... [and] IPSCO’s interests are otherwise at all times protected ....

(Appendix at 220.)

The PMA also included an insurance component. Specifically, the PMA required IPSCO to procure at least $20 million of professional liability insurance covering Kvaerner, the subconsultants, and the design professionals. To satisfy this obligation, IPSCO hired Marsh USA, Inc. (“Marsh”), an insurance broker, who in turn procured a $20 million policy from Liberty Mutual Insurance Company (“Liberty Mutual”). The policy was a so-called “wasting policy,” whereby costs of defending legal actions would be deducted from the total amount of available coverage.

B. Blaine

On Kvaerner’s recommendation, IPSCO awarded the contract to complete the design and construction of the primary buildings to Blaine Construction Corporation (“Blaine”). Less than one year into the project, Blaine discovered design errors in its work and abandoned the project, which caused significant disruptions and delays.

In response to Blaine’s unexpected abandonment, IPSCO and Kvaerner entered into a written agreement reinforcing their (IPSCO’s and Kvaerner’s) agency relationship and amending certain aspects of the PMA. The “Amending Agreement,” which estimated the losses resulting from Blaine’s abandonment to be in the range of $14 million to $18 million, provided that any proceeds ultimately recovered from Blaine or its insurers, if any, would be paid solely to IPSCO, but that such recovered funds would be applied as a credit against the “Aggregate Cost” under the PMA.

Under the terms of the Amending Agreement, IPSCO and Kvaerner agreed Kvaerner would pursue recovery from Blaine, Liberty Mutual and Marsh for damages resulting from Blaine’s conduct. More important, IPSCO and Kvaerner agreed their respective roles in that dispute would be governed by Section 4.04(x) of the PMA. See Amending Agreement ¶ 5.01 (“The rights and responsibilities of [Kvaerner] and IPSCO in respect of the Blaine Action will be governed by section 4.04(x) [of the PMA].”) (App.278.).

C. Construction Action; Coverage Action

At about the same time, IPSCO and Kvaerner filed suit against Blaine in the District Court for the Western District of Pennsylvania, where Kvaerner has its *145 principal place of business. The complaint sought to recover the damages caused by Blaine’s abandonment and design errors. For ease of reference, we will refer to this lawsuit as the “Construction Action.”

Blaine then turned to Liberty Mutual and demanded both defense and coverage under the $20 million wasting policy that Liberty Mutual had issued. When Liberty Mutual denied coverage on the ground that it had allegedly never received proper notice that Blaine was an insured under the policy, Blaine filed suit against Liberty Mutual in the Western District of Pennsylvania seeking a declaration from the court that it was covered under the policy. Blaine also asserted claims against Marsh, the insurance broker, because Marsh had issued an “advice of insurance” three years earlier assuring Blaine that it was covered by the Liberty Mutual policy. We refer to this lawsuit as the “Coverage Action.”

The following year, IPSCO and Kvaer-ner entered into a confidential settlement agreement with Blaine (the “Construction Action Settlement”). Under that agreement, the parties agreed to submit the issue of Blaine’s liability to an arbitration panel and, in the event the arbitration panel found Blaine liable, the parties agreed to enter a $26 million stipulated judgment against Blaine in favor of IP-SCO. Blaine, however, had “empty pockets,” so IPSCO and Kvaerner further agreed that they would satisfy the $26 million judgment, if any, by looking solely to Blaine’s insurers..

To that end, the Construction Action Settlement required Blaine to continue prosecuting the Coverage Action against Liberty Mutual and against Marsh. Blaine was prohibited from settling any of its claims without prior written approval from IPSCO and Kvaerner. Upon learning of the Construction Action Settlement, the District Court stayed both the Construction Action and Coverage Action, presumably because a finding of “no liability” in the arbitration proceeding would put an end to both lawsuits.

D. Alabama Action Against Kvaerner

Meanwhile, IPSCO filed a lawsuit against Kvaerner in federal court in Alabama seeking more than $60 million in various cost overruns on the project. These cost overruns included damages resulting from Blaine’s abandonment of construction. Because Kvaerner is insured under the $20 million policy issued by Liberty Mutual, almost all of the defense costs that it incurred in the Alabama lawsuit have been paid by Liberty Mutual. Accordingly, each dollar spent on Kvaerner’s defense reduced Liberty Mutual’s coverage under its wasting policy. It was estimated at oral argument that $5 million had been expended to that time.

E.

Free access — add to your briefcase to read the full text and ask questions with AI

IPSCO Steel (Alabama), Inc. v. Blaine Construction Corp., 371 F.3d 141 (3d Cir. 2004).

371 F.3d 141 (IPSCO Steel (Alabama), Inc. v. Blaine Construction Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related