IPS Avon Park Corporation v. Kinder Morgan, Inc.

CourtDistrict Court, M.D. Florida
DecidedJanuary 19, 2022
Docket8:20-cv-01643
StatusUnknown

This text of IPS Avon Park Corporation v. Kinder Morgan, Inc. (IPS Avon Park Corporation v. Kinder Morgan, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IPS Avon Park Corporation v. Kinder Morgan, Inc., (M.D. Fla. 2022).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF FLORIDA TAMPA DIVISION

IPS AVON PARK CORPORATION AND D E JONES CONSULTING, INC.,

Plaintiffs,

v. Case No. 8:20-cv-1643-TPB-CPT

KINDER MORGAN, INC., EL PASO LLC, SHADY HILLS POWER COMPANY LLC, AND MESQUITE INVESTORS, LLC,

Defendants. ________________________________/

ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT AND DENYING PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT

This matter is before the Court on Defendants’ “Motion for Summary Judgment and Incorporated Memorandum of Law” and “Plaintiffs IPS Avon Park Corporation and D E Jones Consulting, Inc.’s Motion for Summary Judgment,” both filed on October 29, 2021. (Docs. 38; 40). Each party filed a response in opposition. (Docs. 45; 50). Defendant filed a reply. (Doc. 50). Upon review of the motions, responses, court file, and record, the Court finds as follows: Background IPS Avon Park Corporation (“Avon Park”) and D E Jones Consulting, Inc. (“Jones Consulting”) (collectively “Plaintiffs”) are developers and consultants for energy projects. Kinder Morgan, Inc. (“Kinder Morgan”), El Paso LLC (“El Paso”), and Mesquite Investors, LLC (“Mesquite”) (collectively “Defendants”) are entities involved in the ownership and development of energy projects. In 1999, Plaintiffs entered a contract to evaluate and develop electric

generation projects, including one in Pasco County, Florida. Shady Hills Power Company, LLC (“Shady Hills Power”) was formed to continue this development and own the Pasco County project (the “Project”). Plaintiffs were each granted a 2.5% equity interest in Shady Hills Power while Shady Hills Holding Company, LLC (“Shady Hills Holding”), an affiliate of El Paso, held the remaining 95% ownership interest in Shady Hills Power. In 2000, Plaintiffs entered into an Agreement with

El Paso, Shady Hills Power, and Shady Hills Holding to sell Plaintiffs’ minority interests in Shady Hills Power. As consideration for Plaintiff’s minority interests, Plaintiffs each received payments totaling $4.25 million ($8.5 million in total). The Agreement also provides that in the event of an Expansion of the Project, defined in the Agreement as “the addition of one or more combustion turbines to the site of the Project,” Plaintiffs are entitled to an additional payment of $2.5 million. Specifically, the payment is due upon the issuance of a notice to proceed with the

construction of the Expansion of the Project under any engineering, procurement, and construction contract (“EPC contract”). Section 2(b) of the Agreement (the “Payment Provision”) states: The payment for the Expansion of the Project shall be due and payable upon the issuance of notice to proceed with construction of the Expansion of the Project under any engineering, procurement and construction contract related thereto. (Doc. 1-3). El Paso also executed a Guaranty of Shady Hills’ payment obligations arising from the Agreement. Kinder Morgan has since assumed El Paso’s liability. The Existing Facility and Proposed New Facility

A simple-cycle power plant was constructed at the Pasco County site (the “Existing Facility”). In 2016, Seminole Electric Cooperative (“Seminole Electric”) requested proposals to meet its power supply needs, and Shady Hills Energy, LLC (“Shady Hills Energy”), an entity formed to develop an expansion of the Existing Facility, submitted a proposal which was selected by Seminole Electric. In 2017, Shady Hills Energy and Seminole Electric entered into a Tolling Agreement (the

“Tolling Agreement”) pursuant to which Shady Hills Energy would develop, design, operate, and own a new combined cycle generating facility (the “Proposed New Facility”). The Proposed New Facility would include the addition of a gas turbine and a steam turbine system. The Contracts and Notices to Proceed Shady Hills Energy entered into four agreements with varying degrees of connection to the expansion of the power plant. First, Shady Hills Energy entered a

contract for the sale of power generation equipment and related services (the “GE Agreement”) with General Electric Company (“GE”). The agreement requires GE to manufacture and ship certain equipment to be used at the Proposed New Facility and to provide project management services. Second, Shady Hills Energy entered a contract with Duke Energy to connect the Proposed New Facility to the existing Duke Energy power grid to deliver power to customers (the “Duke Agreement”). The Duke Agreement has a 30-year term with an automatic renewal provision. Third, Shady Hills Energy entered a contract with Aquatech International,

LLC (“Aquatech”) for the construction of a turnkey water treatment facility (the “Aquatech Agreement”). The Aquatech Agreement is an EPC contract. Fourth, Shady Hills Energy entered a contract with The Industrial Company (“TIC”) for the construction of a combined cycle electric power generation facility. The TIC Agreement is an EPC contract. In connection with this contract, six notices to proceed were issued. The first notice was for front-end engineering work.

The second authorized the design and construction of a concrete foundation pad about the size of a dining room for the fire pump enclosure that would service the Proposed New Facility. The third authorized a silt fence around a cement slab on the property. The fourth, fifth, and sixth authorized the mowing of the job site and the clearing of trees. Due to a lack of financing and a dispute with Seminole Electric, the “Proposed New Facility” was never built. Plaintiffs have each submitted invoices to

Defendants requesting payment of the $1,250,000 that they allege is due pursuant to Section 2(b) of the Agreement. On June 18, 2020, Plaintiffs filed a complaint against Defendants in state court, raising claims for breach of contract (Count I) and a breach of guaranty (Count II). On July 17, 2020, Defendants removed the action to this Court based on diversity jurisdiction. Plaintiffs and Defendants now move for summary judgment. Legal Standard Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a

matter of law.” Fed. R. Civ. P. 56(a). A properly supported motion for summary judgment is only defeated by the existence of a genuine issue of material fact. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986). The moving party bears the initial burden of showing that there are no genuine issues of material fact. Hickson Corp. v. N. Crossarm Co., 357 F.3d 1256, 1260 (11th Cir. 2004). When the moving party has discharged its burden, the

nonmoving party must then designate specific facts showing the existence of genuine issues of material fact. Jeffery v. Sarasota White Sox, Inc., 64 F.3d 590, 593-94 (11th Cir. 1995). If there is a conflict between the parties’ allegations or evidence, the nonmoving party’s evidence is presumed to be true and all reasonable inferences must be drawn in the nonmoving party’s favor. Shotz v. City of Plantation, 344 F.3d 1161, 1164 (11th Cir. 2003). The standard for cross-motions for summary judgment is not different from

the standard applied when only one party moves for summary judgment. Am. Bankers Ins. Grp. v. United States, 408 F.3d 1328, 1331 (11th Cir. 2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeffery v. Sarasota White Sox, Inc.
64 F.3d 590 (Eleventh Circuit, 1995)
Beck v. Lazard Freres & Co., LLC
175 F.3d 913 (Eleventh Circuit, 1999)
Shotz v. City of Plantation, FL
344 F.3d 1161 (Eleventh Circuit, 2003)
Hickson Corp. v. Northern Crossarm Co.
357 F.3d 1256 (Eleventh Circuit, 2004)
American Bankers Insurance Group v. United States
408 F.3d 1328 (Eleventh Circuit, 2005)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Saregama India Ltd. v. Mosley
635 F.3d 1284 (Eleventh Circuit, 2011)
United States v. Frank M. Oakley
744 F.2d 1553 (Eleventh Circuit, 1984)
Strama v. Union Fidelity Life Ins. Co.
793 So. 2d 1129 (District Court of Appeal of Florida, 2001)
J & S Coin Operated MacHines, Inc. v. Gottlieb
362 So. 2d 38 (District Court of Appeal of Florida, 1978)
BKD Twenty-One Management Co. v. Delsordo
127 So. 3d 527 (District Court of Appeal of Florida, 2012)
Vyfvinkel v. Vyfvinkel
135 So. 3d 384 (District Court of Appeal of Florida, 2014)
Gulliver Schools, Inc. v. Snay
137 So. 3d 1045 (District Court of Appeal of Florida, 2014)
Ciklin Lubitz Martens & O'Connell v. Patrick J. Casey, P.A.
199 So. 3d 309 (District Court of Appeal of Florida, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
IPS Avon Park Corporation v. Kinder Morgan, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ips-avon-park-corporation-v-kinder-morgan-inc-flmd-2022.