IPL Industrial Group v. Indianapolis Power and Light Company

Indiana Court of Appeals·Decided November 4, 2020·No. 20A-EX-800·Published

Opinion

FILED

Nov 04 2020, 8:48 am

CLERK

Indiana Supreme Court

Court of Appeals

and Tax Court

ATTORNEYS FOR APPELLANTS ATTORNEYS FOR APPELLEES Citizens Action Coalition of Indiana, Inc. Indiana Utility Regulatory Commission

Jennifer A. Washburn Indianapolis, Indiana Aaron T. Craft City of Indianapolis Jeremy R. Comeau Steven L. Davies

Anne E. Becker Beth E. Heline Bette Jean Dodd Indianapolis, Indiana Indianapolis, Indiana Indianapolis Power and Light Indiana Office of Utility Consumer Company Counselor Peter J. Rusthoven

Abby R. Gray Teresa E. Morton William I. Fine Jeffrey M. Peabody Randall C. Helmen Indianapolis, Indiana Jeffrey M. Reed Indianapolis, Indiana IPL Industrial Group Todd A. Richardson Joseph P. Rompala Indianapolis, Indiana

IN THE

COURT OF APPEALS OF INDIANA

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 1 of 22

IPL Industrial Group, Citizens November 4, 2020 Action Coalition of Indiana, Court of Appeals Case No. Inc., City of Indianapolis, and 20A-EX-800 Indiana Office of Utility Appeal from the Indiana Utility Consumer Counselor, Regulatory Commission Appellants-Intervenors, The Honorable Jennifer L.

Schuster, Administrative Law v. Judge The Honorable James F. Huston, Indianapolis Power and Light Chairman Company and Indiana Utility IURC Cause No. 45264 Regulatory Commission, Appellees-Petitioners.

Riley, Judge.

STATEMENT OF THE CASE

[1] Appellants-Intervenors and Statutory Party, IPL Industrial Group, Indiana

Office of Utility Consumer Counselor, City of Indianapolis, and Citizens Action Coalition of Indiana, Inc. (Collectively, Consumer Parties), appeal the Indiana Utility Regulatory Commission’s (Commission) Order approving Appellee-Petitioner’s, Indianapolis Power & Light Company (IPL), Proposed Plan involving $1.2 billion in system investments over a seven-year period.

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 2 of 22

[2] We affirm.

ISSUES

[3] The Consumer Parties raise three issues on appeal, which we restate as follows:

1. Whether the Commission’s decision to admit into evidence IPL’s workpapers was an abuse of discretion, when the admission occurred at the end of the evidentiary hearing and without a sponsoring witness or foundation;

2. Whether the Commission erroneously interpreted the statutory requirement that the incremental benefits yielded by the Proposed Plan must justify its estimated costs when IPL’s evidence established that its Proposed Plan was geared towards risk reduction of an already highly reliable system; and

3. Whether the Commission failed to make specific findings on material issues and only formulated a conclusory finding in summary fashion on the statutory cost-justification requirement and the disputed monetization analysis offered by IPL.

FACTS AND PROCEDURAL HISTORY [4] The case before us arises under the Transmission, Distribution, and Storage

System Improvement Charge (TDSIC) statute, as enacted in Indiana Code Ch. 8-1-39. Unlike a traditional rate case which involves a comprehensive review of a utility’s operations and financial status, the TDSIC mechanism allows utilities to request increases in their rates—outside of a rate case—to fund certain upgrades and improvements to an energy utility’s transmission, distribution, or storage system in Indiana. The TDSIC statute institutes two distinct types of proceedings. First, pursuant to Section 10, the utility must secure the Commission’s preapproval of a plan to complete identified improvement projects at a defined budget over a specified time period. See I.C. § 8-1-39-10. To gain approval, the plan must satisfy certain enumerated statutory criteria, including the best estimate of costs, a finding of public convenience and necessity, a showing of reasonableness, and a determination that “the estimated costs of the eligible improvements included in the plan are justified by incremental benefits attributable to the plan.” See I.C. § 8-1-39-10(b). Once a plan is approved, the utility may then, pursuant to Section 9, seek periodic rate increases at six-month intervals to recover 80% of the approved costs as the planned work is completed. See I.C. § 8-1-39-9(a). Up to these authorized expenditures, rate recovery is automatic. The remaining 20% of the costs is accumulated in a deferred account for recovery, with carrying charges, in the utility’s next rate case. See I.C. § 8-1-39-9(c).

[5] On July 24, 2019, IPL filed its petition with the Commission under Section 10 of the TDSIC statute, seeking approval of proposed expenditures of $1.2 billion over a seven-year period to replace, rebuild, upgrade, redesign, and modernize a wide range of IPL’s transmission- and distribution-system assets (Proposed Plan). The Proposed Plan was intended to address grid resiliency, so that the system could be restored more easily when outages occur. The investments under the Proposed Plan were prioritized through a Risk Model, which identified assets based on the amount of risk—in terms of likelihood of failure and consequence of failure—and the cost to buy down risk in order to achieve the highest risk reduction per dollar invested. IPL projected that the planned projects would result in a system risk reduction of about 36.6% over the seven- year period. To justify the enormous cost of the Proposed Plan, IPL relied on a monetization analysis. Using a Department of Energy calculation tool, IPL monetized the impact of projected outages over a twenty-year period, which IPL asserted could be avoided through the planned projects enumerated in the Proposed Plan. According to IPL, the monetization analysis reflects a net benefit of $939 million to IPL customers by the end of the twenty-year period.

[6] At the same time IPL filed its petition, it also prefiled, pursuant to Commission procedure, its case-in-chief evidence consisting of the written testimony and related exhibits of six witnesses. IPL also submitted voluminous workpapers consisting of underlying supporting material associated with the witnesses’ testimony.

[7] By statute, the ratepaying public is represented in all utility proceedings by the Office of Utility Consumer Counselor (OUCC), an independent state agency. In addition, three other Consumer Parties intervened in this proceeding. The IPL Industrial Group (Industrial Group) is an ad hoc group comprised of several large volume consumers served by IPL; the City of Indianapolis intervened in its capacity as an IPL ratepayer with an interest in the impact of IPL rates on the local economy and its citizenry; and Citizens Action Coalition and Environmental Law & Policy Center are advocacy organizations for consumer and environmental interests that were jointly represented below. All of the Consumer Parties opposed IPL’s petition for approval of the Proposed Plan and prefiled their written testimony and exhibits in response. On October 23, 2019, IPL filed its rebuttal evidence but did not file any additional workpapers in connection with the rebuttal evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

IPL Industrial Group v. Indianapolis Power and Light Company, (Ind. Ct. App. 2020).

IPL Industrial Group v. Indianapolis Power and Light Company (IPL Industrial Group v. Indianapolis Power and Light Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related