IPL Industrial Group v. Indianapolis Power and Light Company

CourtIndiana Court of Appeals
DecidedNovember 4, 2020
Docket20A-EX-800
StatusPublished

This text of IPL Industrial Group v. Indianapolis Power and Light Company (IPL Industrial Group v. Indianapolis Power and Light Company) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IPL Industrial Group v. Indianapolis Power and Light Company, (Ind. Ct. App. 2020).

Opinion

FILED Nov 04 2020, 8:48 am

CLERK Indiana Supreme Court Court of Appeals and Tax Court

ATTORNEYS FOR APPELLANTS ATTORNEYS FOR APPELLEES Citizens Action Coalition of Indiana, Inc. Indiana Utility Regulatory Commission Jennifer A. Washburn Indianapolis, Indiana Aaron T. Craft City of Indianapolis Jeremy R. Comeau Steven L. Davies Anne E. Becker Beth E. Heline Bette Jean Dodd Indianapolis, Indiana Indianapolis, Indiana Indianapolis Power and Light Indiana Office of Utility Consumer Company Counselor Peter J. Rusthoven Abby R. Gray Teresa E. Morton William I. Fine Jeffrey M. Peabody Randall C. Helmen Indianapolis, Indiana Jeffrey M. Reed Indianapolis, Indiana IPL Industrial Group Todd A. Richardson Joseph P. Rompala Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 1 of 22 IPL Industrial Group, Citizens November 4, 2020 Action Coalition of Indiana, Court of Appeals Case No. Inc., City of Indianapolis, and 20A-EX-800 Indiana Office of Utility Appeal from the Indiana Utility Consumer Counselor, Regulatory Commission Appellants-Intervenors, The Honorable Jennifer L. Schuster, Administrative Law v. Judge The Honorable James F. Huston, Indianapolis Power and Light Chairman Company and Indiana Utility IURC Cause No. 45264 Regulatory Commission, Appellees-Petitioners.

Riley, Judge.

STATEMENT OF THE CASE [1] Appellants-Intervenors and Statutory Party, IPL Industrial Group, Indiana

Office of Utility Consumer Counselor, City of Indianapolis, and Citizens

Action Coalition of Indiana, Inc. (Collectively, Consumer Parties), appeal the

Indiana Utility Regulatory Commission’s (Commission) Order approving

Appellee-Petitioner’s, Indianapolis Power & Light Company (IPL), Proposed

Plan involving $1.2 billion in system investments over a seven-year period.

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 2 of 22 [2] We affirm.

ISSUES [3] The Consumer Parties raise three issues on appeal, which we restate as follows:

1. Whether the Commission’s decision to admit into evidence IPL’s

workpapers was an abuse of discretion, when the admission occurred at

the end of the evidentiary hearing and without a sponsoring witness or

foundation;

2. Whether the Commission erroneously interpreted the statutory

requirement that the incremental benefits yielded by the Proposed Plan

must justify its estimated costs when IPL’s evidence established that its

Proposed Plan was geared towards risk reduction of an already highly

reliable system; and

3. Whether the Commission failed to make specific findings on material

issues and only formulated a conclusory finding in summary fashion on

the statutory cost-justification requirement and the disputed

monetization analysis offered by IPL.

FACTS AND PROCEDURAL HISTORY [4] The case before us arises under the Transmission, Distribution, and Storage

System Improvement Charge (TDSIC) statute, as enacted in Indiana Code Ch.

8-1-39. Unlike a traditional rate case which involves a comprehensive review of

a utility’s operations and financial status, the TDSIC mechanism allows utilities

to request increases in their rates—outside of a rate case—to fund certain

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 3 of 22 upgrades and improvements to an energy utility’s transmission, distribution, or

storage system in Indiana. The TDSIC statute institutes two distinct types of

proceedings. First, pursuant to Section 10, the utility must secure the

Commission’s preapproval of a plan to complete identified improvement

projects at a defined budget over a specified time period. See I.C. § 8-1-39-10.

To gain approval, the plan must satisfy certain enumerated statutory criteria,

including the best estimate of costs, a finding of public convenience and

necessity, a showing of reasonableness, and a determination that “the estimated

costs of the eligible improvements included in the plan are justified by

incremental benefits attributable to the plan.” See I.C. § 8-1-39-10(b). Once a

plan is approved, the utility may then, pursuant to Section 9, seek periodic rate

increases at six-month intervals to recover 80% of the approved costs as the

planned work is completed. See I.C. § 8-1-39-9(a). Up to these authorized

expenditures, rate recovery is automatic. The remaining 20% of the costs is

accumulated in a deferred account for recovery, with carrying charges, in the

utility’s next rate case. See I.C. § 8-1-39-9(c).

[5] On July 24, 2019, IPL filed its petition with the Commission under Section 10

of the TDSIC statute, seeking approval of proposed expenditures of $1.2 billion

over a seven-year period to replace, rebuild, upgrade, redesign, and modernize a

wide range of IPL’s transmission- and distribution-system assets (Proposed

Plan). The Proposed Plan was intended to address grid resiliency, so that the

system could be restored more easily when outages occur. The investments

under the Proposed Plan were prioritized through a Risk Model, which

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 4 of 22 identified assets based on the amount of risk—in terms of likelihood of failure

and consequence of failure—and the cost to buy down risk in order to achieve

the highest risk reduction per dollar invested. IPL projected that the planned

projects would result in a system risk reduction of about 36.6% over the seven-

year period. To justify the enormous cost of the Proposed Plan, IPL relied on a

monetization analysis. Using a Department of Energy calculation tool, IPL

monetized the impact of projected outages over a twenty-year period, which

IPL asserted could be avoided through the planned projects enumerated in the

Proposed Plan. According to IPL, the monetization analysis reflects a net

benefit of $939 million to IPL customers by the end of the twenty-year period.

[6] At the same time IPL filed its petition, it also prefiled, pursuant to Commission

procedure, its case-in-chief evidence consisting of the written testimony and

related exhibits of six witnesses. IPL also submitted voluminous workpapers

consisting of underlying supporting material associated with the witnesses’

testimony.

[7] By statute, the ratepaying public is represented in all utility proceedings by the

Office of Utility Consumer Counselor (OUCC), an independent state agency.

In addition, three other Consumer Parties intervened in this proceeding. The

IPL Industrial Group (Industrial Group) is an ad hoc group comprised of

several large volume consumers served by IPL; the City of Indianapolis

intervened in its capacity as an IPL ratepayer with an interest in the impact of

IPL rates on the local economy and its citizenry; and Citizens Action Coalition

and Environmental Law & Policy Center are advocacy organizations for

Court of Appeals of Indiana | Opinion 20A-EX-800 | November 4, 2020 Page 5 of 22 consumer and environmental interests that were jointly represented below. All

of the Consumer Parties opposed IPL’s petition for approval of the Proposed

Plan and prefiled their written testimony and exhibits in response. On October

23, 2019, IPL filed its rebuttal evidence but did not file any additional

workpapers in connection with the rebuttal evidence.

[8] Over the course of three days—November 14, 21, and 22, 2019—the

Commission conducted a publicly noticed evidentiary hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
IPL Industrial Group v. Indianapolis Power and Light Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ipl-industrial-group-v-indianapolis-power-and-light-company-indctapp-2020.