Iowa Gateway, Inc. v. Interstate Power Co.

350 N.W.2d 141, 1984 Iowa Sup. LEXIS 1134
CourtSupreme Court of Iowa
DecidedMay 16, 1984
Docket83-138
StatusPublished
Cited by1 cases

This text of 350 N.W.2d 141 (Iowa Gateway, Inc. v. Interstate Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Gateway, Inc. v. Interstate Power Co., 350 N.W.2d 141, 1984 Iowa Sup. LEXIS 1134 (iowa 1984).

Opinion

LARSON, Justice.

This is an interlocutory appeal from equity rulings in a bifurcated trial involving ownership rights in a transloading facility on the Mississippi River. The district court reserved the law issues for later disposition. The critical issue on appeal is the effect of Iowa Gateway, Inc.’s attempted exercise of an option to repurchase the facility. We conclude the attempted exercise was invalid and therefore reverse on that issue. Other rulings, controlled by our ruling on the exercise of the option, are affirmed. The remaining issues are remanded for trial.

The events leading up to this litigation began in 1973, when Interstate Power Company entered into a long-term contract for a large supply of western coal for electric generation. Interstate is an electric utility furnishing power for portions of Iowa, Minnesota, and Wisconsin, operating a generating plant at Lansing, Iowa, where this coal was to be used.

In 1975, Interstate began to look for a rail/barge transloading site or facility on the Mississippi River to unload coal from railroad cars and load onto barges for shipment upstream to Lansing. At that time, Gateway owned and operated a small transloading and storage facility at mile marker 371, in Lee County. It had the *143 necessary permits, apparently, to construct such facility as Interstate envisioned and had begun investigation on its own of the possibilities’of enlarging its transloading facility. Gateway’s location on the river and its possession of these permits were valuable to this project. There was some evidence that Gateway, in fact, had the only viable location for such a facility between mile marker 371 and the Lansing plant upstream in Allamakee County. As it later developed, Gateway’s site and permits were virtually its only assets. At the suggestion of Burlington Northern Railroad, which was shipping the coal to Interstate, the two parties got together.

In 1975, Interstate and Gateway executed a “nonbinding” letter of intent concerning the construction of this facility. Then, in November 1976, a “binding,” letter of intent was executed between the parties.

Gateway began searching for financing, using Interstate’s letter of intent as collateral. Financing for the project was no small matter, however, as the estimated cost of the project was in excess of $30 million.

In December 1976, a potential financing meeting was held by Interstate, Gateway, Manufacturer’s Hanover Trust, and the First National Bank of Chicago. The lenders wanted Interstate to guarantee any loan to Gateway. Interstate refused. (Interstate’s refusal to guarantee any such loan continued to be a major obstacle to Gateway’s loan arrangements. The reason for Interstate’s refusal was that a guarantee might be required by federal regulatory rules to be shown on its balance sheet as a liability, which could result in a downgrading of its bond rating thereby raising the cost of its own financing.)

When the prospects for Gateway’s financing appeared dim, a meeting was held by Gateway, Interstate, Orba Corporation and Johnson Brothers Corporation to discuss a “turnkey” construction plan. Under such a plan, the construction contractor would provide the financing during construction and, on completion, would turn the property over to the permanent owner, who would “take out” the construction lender by arranging its own financing. (Johnson Bros, is a construction contractor which had had previous experience in building transloading facilities and Orba is an engineering firm which had had previous experience in their design. Orba and Johnson later formed separate entities known as Orba-Johnson Transshipment Company, Orba Transshipment of Iowa, Inc., and Johnson Bros. Transshipment Corporation of Iowa, Inc., for purposes of owning and operating the facility. These entities are named as separate defendants in this action, but for our purposes, we will collectively refer to them in most instances as “Orba-Johnson.”) A turnkey approach was agreed upon, and Orba-Johnson was selected to design and build the facility.

In February, 1977, Gateway, Interstate, and Orba-Johnson drafted a “coal contract,” a document which figures prominently in this litigation. This contract provided that a transloading facility would be built by Gateway, that Gateway would transload coal for Interstate and other customers, and that Interstate would pay a fee to Gateway calculated to pay the construction and operation costs of the facility. At about this time, Interstate learned of Gateway’s precarious financial position, and it delayed the signing of the coal contract.

Gateway and Interstate, in the meantime, met to discuss bankruptcy and insolvency concerns. Interstate offered to purchase Gateway’s assets; Gateway refused. The parties agreed that further negotiations would follow.

In June 1977, Gateway and Interstate executed an offer to purchase and first addendum. Gateway agreed to sell its property for $3,400,000. A release of all claims by both parties was incorporated in the agreement. The first addendum provided the February draft of the coal contract would be executed “as of the date hereof” and that Interstate would give Gateway an option to repurchase for $3,400,000 plus costs of construction.

*144 Finally, in July 1977, Gateway and Interstate executed the coal contract which had been drafted in February, and a first addendum to it. They also executed a lease allowing Gateway to lease back its existing transloading and storage operation during construction of the coal facility. Other agreements, not bearing directly on the litigation, were also executed at about the same time.

On October 28, 1977, a closing was held on a purchase and sale agreement between Interstate and Gateway which superseded the prior offer to purchase and its addenda. Under the new agreement, (1) Gateway’s assets were sold to Interstate or its nominee; (2) Gateway was to be given an option to repurchase; (3) Gateway released all prior claims against Interstate; and (4) the coal contract of February, 1977, under which Interstate was to pay Gateway for transloading the coal, was rendered inoperative unless Gateway exercised its option to repurchase.

Interstate and Orba-Johnson entered into a construction contract on December 13, 1977. Under this agreement, the estimated completion date for the transloading facility was June 30, 1979.

In February, 1978, Gateway and Interstate executed an option to repurchase pursuant to the purchase and sale agreement. It provided in relevant part:

Such Option of Iowa Gateway shall be exercised, if at all, by written notice of Iowa Gateway’s election to exercise such Option, accompanied by letters of credit or firm commitments from financial institutions reasonably satisfactory to OJS and Interstate that funds for such repurchase will be available at closing, conditioned only upon OJS’s [Orba-Johnson System’s] full performance hereunder, being delivered to or served upon OJS on or before [60 days] prior to the estimated date of final completion (whether or not such final completion is accomplished when estimated).

(Under the December 13 construction contract, the “estimated date of final completion” as referred to in the option to repurchase, was June 30, 1979. Exercise of the option would thus have to be made on or prior to May 1, 1979.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Junkins v. Branstad
421 N.W.2d 130 (Supreme Court of Iowa, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
350 N.W.2d 141, 1984 Iowa Sup. LEXIS 1134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-gateway-inc-v-interstate-power-co-iowa-1984.