Iowa Bonding & Casualty Co. v. Frank Cram & Sons

228 N.W. 24, 209 Iowa 424
CourtSupreme Court of Iowa
DecidedDecember 13, 1929
DocketNo. 38687.
StatusPublished
Cited by2 cases

This text of 228 N.W. 24 (Iowa Bonding & Casualty Co. v. Frank Cram & Sons) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Bonding & Casualty Co. v. Frank Cram & Sons, 228 N.W. 24, 209 Iowa 424 (iowa 1929).

Opinion

Morling, J.

Tbe basis of tbe suit is a stipulation in tbe accepted application by defendants to plaintiff for contractor’s bond, whereby defendants agree .“to pay to the company upon the execution of the said bond, if it be a final contract bond * * * $1,066.26 in advance for two years and $1,066.26 annually in advance thereafter” until company’s receipt of evidence of discharge, and “to pay to the company upon the completion of the contract an additional premium at the same rate, computed upon any increase of the original contract price as shown by the architect in charge of the contract.” Defendant asks to have the application reformed by eliminating the stipulation for additional premium. The court, though not in terms deny *425 ing, did not grant this relief. Defendants have not appealed, and though there is evidence in support of the claim for reformation, we give no further attention to it. Plaintiff’s pleaded cause of action is merely one at law ,(though we infer the whole case was tried in equity, because of the cross-petition), to recover because the total contract price for the work amounted to $271,731.12, instead of $106,625.68, as stated in the application. Defendants’ contention is that the correct interpretation of the application requires the payment only of $1,066.26, which has been made.

Defendants had procured a street-grading contract, which recites that the amount of the work was estimated at 115,271 cubic yards of excavation, “more or less.” The contract required the dirt removed to be placed on such streets or other property as the city official might designate. Defendants agreed to do the work “at the price of $0.925 per cubic yard for excavation of all material except rock * * * $2 per cubic yard for rock, the haul to be two thousand (2,000) feet or less from the center of gravity of each block. All greater distance than two thousand (2,000) feet * * * shall be overhaul and shall be paid for at the rate of two cents (2c) per cubic yard per one hundred (100) feet of overhaul which shall be in full compensation for the cost of the entire work, and the city of Des Moines shall not be liable to said party of the first part for extras of any kind, or for any damages which he may sustain by coming in contact with sand, water, or any other unforeseen obstacles or material, except rock, or by reason of unfavorable weather, it being expressly understood that the contract price above specified shall be in full for all work done under this contract.” Butters, who was the representative of P. J. Clancy & Company, plaintiff’s general agents, and who was “licensed” by plaintiff as its agent, solicited defendants for the bond. Other companies were also seeking the business. Defendants told Butters that the contract had an overhaul clause in it. Butters investigated at the city hall. “He just came back and submitted me [one of defendants] his price.” (As we are not considering defendants’ claim for reformation, we do not take into account the testimony in behalf of defendants relating to the alleged oral agreement between Butters and defendants.) Butters went out of defendants’ office, and later returned, with the application *426 sued upon. This was on a printed form. Much of the data called for by the printed form was not filled in. The application as presented and signed contained data and blanks as follows:

“5. Penalty of bond: $53,400 * ® *

"6. Contract price: $106,625.68. If the contract price is per unit of measure, state here the probable total amount of the contract: $..

“7. Name and address of the architect or engineer in charge:.....

“8. The architect’s or engineer’s estimate of the cost of the work: $.. * * *

“15. Amount of contract price retained until work is completed: $106,375. ® * *

“32. * * * In consideration of the execution by The Iowa Bonding and Casualty Company, * * * of the bond herein and hereby applied for the undersigned.agrees as follows: 1. ”

Here follows the stipulation of the application sued upon, as above set out. The contract is dated February 9, 1920; the bond, February 12, 1920. Butters, on September 17, 1920, collected of defendants the $1,066.26.

Butters told defendants, during the negotiations for the bond, that he had examined the contract with the city. Defendants “did not give information with regard to the bond” to Butters. More than two years after the work was completed, plaintiff asked for additional premium. The bond is in the penalty of $53,400. The bond recites, in the language of the contract (which Butters evidently got from the city hall) : “The amount of work is estimated at 115,271 cubic yards of excavation more or less. ’ ’

Final estimates were ordered paid February 11, 1921. By them the total amount for excavation was $114,813.78, and for overhaul $156,917.44, a total of $271,731.22. There were long overhauls, and the difference between the amount of the estimated contract price and the amount finally allowed was due to the overhauls. Plaintiff introduced evidence “that premiums on bonds of this kind are computed upon the amount of the contract price. The rate upon city contracts for grading was $10 a thousand. That was the customary premium in force * * * *427 and one per cent of the contract price * * *” It is not shown that any price except $1,066.26 was made to defendants, or that defendants were in any wise apprised (unless it be by the stipulation of the application sued on, which defendants say, without contradiction, they did not read) that any price or premium was in contemplation or called for other than the $1,066.26. Plaintiff does not claim fraud or mistake. It does not appear that defendants knew of the customary premium alleged. The plaintiff says that the estimated yardage of 115,271, in connection with the price of $.925 for excavation, as stated in the contract, and the estimated total contract price of $106,625.68, as stated in the application in connection with the premium, $1,066.26, show that the premium was merely provisionally computed on the basis of the estimated yardage and the agreed price for excavation. The computation, however, on that basis only approximates the stated contract price, and the application, while it states the contract price to be $106,625.68, says that the amount to be retained is $106,375. The printed form for the application appears to have been designed for contract bonds generally. It gives the contract price as $106,625.68. Defendants did not represent that sum as the contract price. The grading contract did not set out those figures or any other figures except the estimated yardage and the unit prices for the work. The computation of premium must have been made by plaintiff’s agent Butters, who was not a witness. In connection with the statement in the application of the contract price, which plaintiff, through defendants’ own agent, inserted on his own information, is the inquiry, “If the contract price is per unit of measure state here the probable total amount of the contract.” No answer to this inquiry is inserted. Tet the contract, as plaintiff knew, was entirely on the basis of unit of measure both for the excavation and the overhaul (though the length of the overhaul, as the evidence shows, could not have been estimated).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vorthmann v. Great Lakes Pipe Line Co.
289 N.W. 746 (Supreme Court of Iowa, 1940)
Umbarger v. State Farm Mutual Automobile Insurance
254 N.W. 87 (Supreme Court of Iowa, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
228 N.W. 24, 209 Iowa 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-bonding-casualty-co-v-frank-cram-sons-iowa-1929.