Iola Capital v. Public Service Commission of Kentucky

CourtCourt of Appeals of Kentucky
DecidedJuly 15, 2022
Docket2020 CA 001394
StatusUnknown

This text of Iola Capital v. Public Service Commission of Kentucky (Iola Capital v. Public Service Commission of Kentucky) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iola Capital v. Public Service Commission of Kentucky, (Ky. Ct. App. 2022).

Opinion

RENDERED: JULY 15, 2022; 10:00 A.M. TO BE PUBLISHED

Commonwealth of Kentucky Court of Appeals

NO. 2020-CA-1394-MR

IOLA CAPITAL; DAVID BROWN; AND KIMBERLY BROWN APPELLANTS

APPEAL FROM FRANKLIN CIRCUIT COURT v. HONORABLE THOMAS D. WINGATE, JUDGE ACTION NO. 20-CI-00075

PUBLIC SERVICE COMMISSION OF KENTUCKY; ATTORNEY GENERAL OF KENTUCKY; AND LOUISVILLE GAS AND ELECTRIC COMPANY APPELLEES

AND

NO. 2020-CA-1395-MR

BERNHEIM ARBORETUM AND RESEARCH FOREST APPELLANT

APPEAL FROM FRANKLIN CIRCUIT COURT v. HONORABLE THOMAS D. WINGATE, JUDGE ACTION NO. 20-CI-00085 LOUISVILLE GAS AND ELECTRIC COMPANY; ATTORNEY GENERAL OF KENTUCKY; AND PUBLIC SERVICE COMMISSION OF KENTUCKY APPELLEES

OPINION AFFIRMING

** ** ** ** **

BEFORE: JONES, LAMBERT, AND K. THOMPSON, JUDGES.

THOMPSON, K., JUDGE: Bernheim Arboretum and Research Forest (Bernheim)

and Iola Capital, LLC, Kimberly Brown, and David Brown (collectively Iola)

appeal from the Franklin Circuit Court’s order which upheld the dismissal of their

complaints against the Public Service Commission of Kentucky (the Commission).

The appellants had sought to challenge the Commission’s prior grant of a

certificate of public convenience and necessity (CPCN) to Louisville Gas and

Electric Company (LG&E) for the construction of a section of natural gas pipeline

in Bullitt County, Kentucky, which would run through the appellants’ property.

We disagree with the circuit court that it lacked subject matter

jurisdiction of the appellants’ appeal of the dismissal of their complaint before the

Commission. Judicial review is required.

We agree with the circuit court that there was no due process violation

as there was no obligation to provide the appellants with notice, an opportunity to

-2- be heard, or an opportunity to intervene before the CPCN was granted. The

General Assembly chose not to give interested landowners any of these rights

when it comes to the application process for a CPCN for a natural gas pipeline and

we cannot grant the parties such rights through the judicial review process. We

note that at times there may be “some injustice” in a particular outcome, due to “a

hiatus in the law,” but our courts cannot provide a remedy; instead, the problem

can only be remedied by legislative action. Ernest Simpson Const. Co. v. Conn,

625 S.W.2d 850, 851 (Ky. 1981). At best, all we can do is bring attention to their

plight.

Accordingly, the properly granted CPCN could not be overturned

through a complaint brought before the Commission or through a declaratory

judgment and the Commission did not act arbitrarily in dismissing the appellants’

complaints. While the granting of the CPCN set the stage for the condemnation

process, affected landowners (through whose land a natural gas line route is

proposed to traverse) have no fixed rights prior to the condemnation proceedings.

Therefore, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

In November 2016, LG&E filed an application for approval of an

increase in its electric and gas rates with the Commission. Notice about the

proposed rate increase was published and listed on the Commission’s website.

-3- Within the rate action, LG&E disclosed its plans to put in a new ten to twelve-mile

section of natural gas pipeline in Bullitt County. Twelve intervenors participated

in the rate action.

LG&E did not file a separate application for a CPCN for the pipeline

pursuant to Kentucky Revised Statutes (KRS) 278.020(1)(a), believing it to be

unnecessary as an “extension” of existing facilities under KRS 278.020(1)(a)2.

While LG&E did disclose the route chosen for the pipeline to the Commission, it

did so subject to the route being treated as confidential by the Commission.

Concerns were raised by the Commission as to whether a CPCN was

in fact required for the pipeline due to the size of the proposed project. The

Commission then decided that pursuant to the statute a CPCN was required.

In June 2017, the Commission entered an order which made findings

that a CPCN should be granted for the pipeline. The Commission determined that

LG&E had satisfied all the requirements for a CPCN within the rate action and that

the proposed pipeline was necessary for LG&E to accommodate current and

expected system requirements. The granting of the CPCN was, however,

conditioned on LG&E providing statements of actual costs upon completion and

LG&E obtaining approval from the Commission prior to incurring long-term

financing for the project pursuant to KRS 278.300.

-4- In May 2019, counsel for Bernheim made an Open Records request of

the Commission for the route of the pipeline. After consultation with LG&E,

which advised that the route no longer needed to be protected as confidential, the

Commission disclosed the route. It was at this time that Bernheim first learned that

the proposed route was to extend through the Cedar Grove Wildlife Corridor which

is a section of conservation land which Bernheim alleges “the Commonwealth of

Kentucky is required to protect from development and gas pipelines pursuant to a

Conservation Easement held by the Commonwealth and under a deed restriction

giving the U.S. Fish and Wildlife Services authority on the disposition of the

property[.]”

After being granted the CPCN, LG&E began acquiring the easements

necessary for construction, but no agreement could be reached between LG&E and

either Iola or Bernheim. As a result, LG&E instituted condemnation actions in

July 2019, against Iola and Bernheim in Bullitt County Circuit Court pursuant to

KRS 416.570.1 Those proceedings are ongoing and are not the subject of this

appeal.

1 LG&E has broad authority to condemn as granted by both KRS 416.140 (producing or supplying gas) and KRS 278.502 (condemnation for gas pipelines). See Commonwealth, Dep’t of Highways v. Vandertoll, 388 S.W.2d 358, 360 (Ky. 1964), as modified on denial of reh’g (Mar. 26, 1965) (noting that courts will not interfere with such power to condemn unless “there has been such a clear and gross abuse of discretion as to violate Section 2 of the Constitution of Kentucky, which section is a guaranty against the exercise of arbitrary power”).

-5- In July and August 2019, Iola and Bernheim each respectively filed

formal complaints with the Commission seeking to void the CPCN in which they

named LG&E as the defendant. These complaints alleged that the issuance of the

CPCN without there being a CPCN application violated Kentucky law, the

Commission’s own regulations, and constituted a denial of due process. The

parties also claimed that they were entitled to receive notice of the CPCN

application, and had the right to intervene in that action, but were unreasonably

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesapeake & O. Ry. Co. v. Greenup County, Kentucky
175 F.2d 169 (Sixth Circuit, 1949)
Pritchett v. Marshall
375 S.W.2d 253 (Court of Appeals of Kentucky (pre-1976), 1963)
Kentucky Milk Marketing & Antimonopoly Commission v. Kroger Co.
691 S.W.2d 893 (Kentucky Supreme Court, 1985)
Pike County Board of Education v. Ford
279 S.W.2d 245 (Court of Appeals of Kentucky (pre-1976), 1955)
Kentucky Public Service Commission v. Commonwealth Ex Rel. Conway
324 S.W.3d 373 (Kentucky Supreme Court, 2010)
American Beauty Homes Corp. v. Louisville & Jefferson County Planning & Zoning Commission
379 S.W.2d 450 (Court of Appeals of Kentucky (pre-1976), 1964)
Kentucky Utilities Co. v. Public Service Commission
252 S.W.2d 885 (Court of Appeals of Kentucky (pre-1976), 1952)
Kentucky Central Life Insurance Co. v. Stephens
897 S.W.2d 583 (Kentucky Supreme Court, 1995)
Bee's Old Reliable Shows, Inc. v. Kentucky Power Co.
334 S.W.2d 765 (Court of Appeals of Kentucky, 1960)
Commonwealth, Department of Highways v. Vandertoll
388 S.W.2d 358 (Court of Appeals of Kentucky, 1964)
Inter-County Rural Electric Cooperative Corp. v. Public Service Commission
407 S.W.2d 127 (Court of Appeals of Kentucky, 1966)
Satterwhite v. Public Service Commission
474 S.W.2d 387 (Court of Appeals of Kentucky, 1971)
Ernest Simpson Construction Co. v. Conn
625 S.W.2d 850 (Kentucky Supreme Court, 1981)
Kelly v. Thompson
983 S.W.2d 457 (Kentucky Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Iola Capital v. Public Service Commission of Kentucky, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iola-capital-v-public-service-commission-of-kentucky-kyctapp-2022.