Intertherm, Inc. v. Structural Systems, Inc.

504 S.W.2d 64, 1974 Mo. LEXIS 562
Supreme Court of Missouri·Decided January 14, 1974·No. 56803·Published·Cited by 6 cases

Opinion

MORGAN, Judge.

Plaintiff instituted suit against defendant to recover $52,500 for alleged breach of a certain contract wherein defendant agreed to construct a warehouse by July 16, 1965, and thereafter lease the same to plaintiff. Defendant counterclaimed for a forfeiture of the contract (lease) and restitution of the premises. Judgment was entered on the petition for plaintiff in the sum of $10,500 plus interest (a total of $13,220) from which both plaintiff and defendant appealed. Defendant appealed from the judgment in favor of plaintiff on the counterclaim. Jurisdiction is in this court by virtue of the amount involved since the appeals were filed prior to January 1, 1972, to-wit: April 20, 1971. We affirm.

Although not requested, the trial court made findings of fact and conclusions of law as follows :

“1. The parties entered into a lease agreement on June 21, 1965. Said lease provided in part that: Defendant was to construct a warehouse to be occupied by plaintiff. The warehouse was to be completed and ready for occupancy by July 16, 1965. Defendant agreed to pay plaintiff the sum of $500.00 per day for each working day after July 16, 1965 that the warehouse structure was not ready for occupancy.
2. The warehouse structure was not ready for occupancy by plaintiff until December 15, 1965. A total of 105 working days elapsed between July 16, 1965 and December 15, 1965.
3. The lease between the parties provided for extensions of time to defendant for delays occasioned by reason of strikes, acts of God, unavailability of materials, acts of Lessee or Lessee’s failure to act when otherwise required to act or other causes beyond Lessor’s control.
4. Defendant was delayed in the construction of the warehouse structure by weather conditions, by a strike, by unavailability of materials, through change of plans by plaintiff and by other causes beyond the control of defendant. The delay resulting therefrom totaled 84 days as more fully set out, to-wit:
5 days — due to grade differences,
14 days — due to change of plans,
12 days — due to delay in obtaining permits,
25 days — due to delay in getting materials,
4 days — due to workers strike,
8 days — due to refusal of workers to work because of weather,
16 days — due to weather conditions.

The Court finds as to defendant’s counterclaim that:

1. Plaintiff executed the lease under the name of International Oil Burner Co. Thereafter plaintiff’s name was changed to International Industries, Inc. and then to Intertherm, Inc.
2. Plaintiff’s occupancy of the warehouse structure was in accordance with the terms of the lease.
*66 3. Plaintiff kept in force all insurance policies as required in the lease.
CONCLUSIONS OF LAW
The lease entered into by the parties on June 21, 1965 was a valid and subsisting agreement. The $500.00 per day for each working day as damages provided in the lease was not disproportionate to actual damages established by plaintiff and therefore was not a penalty provision.
Plaintiff is entitled to recover from defendant the sum of $500.00 for 21 days, the difference between the 105 days delay in the occupancy of the building by plaintiff and the 84 days extension to which defendant is entitled.
The defendant is not entitled to recover under its counterclaim.
FINDING AND JUDGMENT in favor of plaintiff and against defendant on plaintiff’s cause of action in the amount of $10,500.00 with interest thereon of $2,520.00 from December 28, 1966 at 6% per annum, a total of $13,220.00 and in favor of plaintiff and against defendant’s counterclaim. Costs against defendant.”

We do observe, initially, that the record confirms that this is not a case involving an unusual set of facts nor any novel question of law. The trial revolved around the efforts of skilled counsel for both parties to persuade the trial court what the true facts actually were.

Free access — add to your briefcase to read the full text and ask questions with AI

Intertherm, Inc. v. Structural Systems, Inc., 504 S.W.2d 64, 1974 Mo. LEXIS 562 (Mo. 1974).

504 S.W.2d 64 (Intertherm, Inc. v. Structural Systems, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kahawaiolaa v. Hawaiian Sun Investments, Inc.
463 P.3d 1081 (Hawaii Supreme Court, 2020)
Purcell Tire & Rubber Co. v. Executive Beechcraft, Inc.
59 S.W.3d 505 (Supreme Court of Missouri, 2001)
Atlas Corp. v. Mardi Gras Corp.
962 S.W.2d 927 (Missouri Court of Appeals, 1998)
Foundation Development Corp. v. Loehmann's, Inc.
788 P.2d 1189 (Arizona Supreme Court, 1990)
Sherwood Medical Industries, Inc. v. Building Leasing Corp.
527 S.W.2d 407 (Missouri Court of Appeals, 1975)