International Union, United Automobile, Aerospace And Agricultural Implement Workers Of America, Uaw And Its Local 647, Uaw v. General Electric Company, Inc.

474 F.2d 1172, 82 L.R.R.M. (BNA) 2945, 1973 U.S. App. LEXIS 11296
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 6, 1973
Docket72-1619
StatusPublished
Cited by1 cases

This text of 474 F.2d 1172 (International Union, United Automobile, Aerospace And Agricultural Implement Workers Of America, Uaw And Its Local 647, Uaw v. General Electric Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Union, United Automobile, Aerospace And Agricultural Implement Workers Of America, Uaw And Its Local 647, Uaw v. General Electric Company, Inc., 474 F.2d 1172, 82 L.R.R.M. (BNA) 2945, 1973 U.S. App. LEXIS 11296 (6th Cir. 1973).

Opinion

474 F.2d 1172

82 L.R.R.M. (BNA) 2945, 70 Lab.Cas. P 13,480

INTERNATIONAL UNION, UNITED AUTOMOBILE, AEROSPACE AND
AGRICULTURAL IMPLEMENT WORKERS OF AMERICA, UAW and
its Local 647, UAW, Plaintiffs-Appellants,
v.
GENERAL ELECTRIC COMPANY, INC., Defendant-Appellee.

Nos. 72-1619, 72-1620.

United States Court of Appeals,
Sixth Circuit.

Argued Dec. 12, 1972.
Decided March 6, 1973.

John A. Fillion, Detroit, Mich., for appellants-cross-appellees; Stephen I. Schlossberg, Detroit, Mich., Bernard C. Fox, Beckman, Lavercombe, Fox & Weil, Cincinnati, Ohio, on the brief.

J. Mack Swigert, Cincinnati, Ohio, for appellee-cross-appellant; Robert W. Maxwell II, Cincinnati, Ohio, on the brief; Taft, Stettinius & Hollister, L. S. Stek, Cincinnati, Ohio, of counsel.

Before EDWARDS, CELEBREZZE and PECK, Circuit Judges.

EDWARDS, Circuit Judge.

This case involves 3,600 grievances, a major labor dispute, the memorandum agreement by which that labor dispute was settled, and the laws of this country pertaining to arbitration. Nonetheless, the efforts of the parties themselves and those of the District Judge who heard this case at the trial level have resulted in an appellate record of manageable proportions.

As the International Union, United Automobile Aerospace and Agricultural Implement Workers of America and the General Electric Company, Inc., approached the termination date of their 1963-66 labor-management agreement for the General Electric plant at Evendale, Ohio, one of the major issues concerned how to dispose of a huge backlog of grievances which had not been resolved under two prior contracts, the then existing contract and its predecessor for the years 1960-63. Under the pressure of a possible strike, and with the mediation assistance of the United States Department of Labor's mediation service, the parties met in Washington, D. C., and ultimately on December 4, 1966, signed a memorandum agreement which in certain respects amended and in other major respects extended the 1963-66 agreement. Paragraph 4 of that memorandum agreement dealt specifically with the problem of the backlog of grievances:

4. With respect to the grievance backlog, the parties agree that active grievances at 2nd, 3rd, and 4th Steps on December 4, 1966, will be combined for the purpose of expediting processing.

The International Representative of the Union will review all unresolved grievances which were active at the 2nd, 3rd, and 4th Steps of the grievance procedure on October 17, 1966, for the purpose of eliminating and disposing from any further consideration, a substantial number of such grievances. The remaining active grievances will thereupon be referred to Step 3 of the grievance procedure set forth in Article XXII of the 1966-1969 Agreement for expedited consideration.

Should any of the grievances remain unsettled after such expedited consideration at Step 3, they will then be referred to a special committee for further efforts toward resolution. The Committee will be composed of the Manager of Union Relations, a Staff Representative, and a specialist from the Union's International Headquarters. Such grievances as may remain unsettled after consideration by the Committee will be categorized by the Committee into one of the following categories:

A. Grievances which are (1) arbitrable as a matter of right under the terms of the 1963-1966 collective bargaining agreement and as to which either party will determine whether it desires to proceed to arbitration and (2) arbitrable under the 1963-1966 agreement by mutual agreement.

B. Grievances which would constitute a contract violation but which are deemed to be non-arbitrable by the Company under the terms of the 1963-1966 Agreement. The Union will determine whether or not they wish to strike or proceed in court on such grievances under the terms of Section 301 of the Taft Hartley Act.

C. Non-contractual grievances. Should any of such grievances be issues upon which the Union elects to strike, it shall give ten days notice thereof to the Federal Mediation and Conciliation Service. The Company should be simultaneously notified. The grievance backlog program shall be conducted during the period January 3, 1967 through April 3, 1967, at the end of which period the Special Grievance Committee will be dissolved, and all matters connected with the issue of backlog of grievances shall be deemed settled for all purposes, excepting only such arbitration proceedings initiated or court actions which may have been filed, or any non-contractual grievances in mediation, or where notice of intent to strike has been given.

Between December 4, 1966, and April 3, 1967, the parties met and sought to resolve as many of the grievances as possible. It is clear from this record that during this period the total backlog of grievances from 1960 down to December 4, 1966, were under negotiation and that a number of grievances from the 1960-63 period were resolved along with numbers of grievances from the 1963-66 period.

Nonetheless, as of April 3, 1967, a formidable number of grievances still remained as to which there was no agreed-on solution and as to which the union claimed the absolute right to arbitration under the contract and the company asserted that, under the same contract, no such right existed. Thereupon the union filed suit in the United States District Court for the Eastern District of Michigan under Sec. 301 of the Labor-Management Relations Act, 29 U.S.C. Sec. 185(a) (1970) for a decree compelling arbitration. The case was transferred to the United States District Court for the Southern District of Ohio and there was heard by a District Judge in the Western Division.

The parties then filed a stipulation classifying the grievances into six classes (plus two individual grievances grouped generally with the B2 class) and agreeing upon a typical grievance as illustrative of the class concerned. The chart below is an attempt to present the stipulation in skeleton form:

Exhibit    Brief description of grievance                     Contract period
  No.                                                           during which
                                                              grievance arose
---------  ------------------------------------------------  ------------------
A1         Working in higher class                                1963-66
A2         Working in higher class                                1960-63
B1         Supervision or salaried personnel working on           1963-66
             bargaining unit.
           Company says not bargaining unit work.
B2         Supervision or salaried personnel working on           1960-63
             bargaining unit.
           Company says not bargaining unit work. (Also
             2AFN and 88E2 (past Step 4))
C1         Supervision working in bargaining unit.                1963-66
           Company admits bargaining unit work, but claims
             is justified under contract.
C2         Supervision working in bargaining unit.                1960-63
           Company admits bargaining unit work, but claims
             is justified under contract.

The complaint in this case was filed April 3, 1967.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
474 F.2d 1172, 82 L.R.R.M. (BNA) 2945, 1973 U.S. App. LEXIS 11296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-union-united-automobile-aerospace-and-agricultural-ca6-1973.