International Telephone & Telegraph Corp. v. Envirco Services, Inc.

364 A.2d 549, 144 N.J. Super. 31, 1976 N.J. Super. LEXIS 651
CourtNew Jersey Superior Court Appellate Division
DecidedSeptember 28, 1976
StatusPublished
Cited by2 cases

This text of 364 A.2d 549 (International Telephone & Telegraph Corp. v. Envirco Services, Inc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Telephone & Telegraph Corp. v. Envirco Services, Inc., 364 A.2d 549, 144 N.J. Super. 31, 1976 N.J. Super. LEXIS 651 (N.J. Ct. App. 1976).

Opinion

The opinion of the court was delivered by

Larner, J. A. D.

This appeal relates to the claim of a subcontractor, Atlas Steel Products Company (Atlas), against a property owner, Central Parkway Associates (CPA), based upon stop notices for work and materials furnished in the construction of a professional office building. In the latter part of 1971 CPA engaged Kolker Construction Corp. (Kolker) as general contractor to construct the building pursuant to a written contract at a total cost of $1,050,000. In December 1971 the owner filed the contract and specifications with the Essex County Clerk in accordance with the provisions of N. J. S. A. 2A:44-75.

Kolker engaged several subcontractors, including Atlas, and commenced performance of the contract. The trial [34]*34judge found as a fact that as of Novemeber 1972 Kolker defaulted on his contract in several respects, so that by early December 1972 he either abandoned or was justifiably removed from the job.

Between November 2, 1972 and January 1973 Atlas filed and served several stop notices for moneys due from Kolker in the total sum of $78,300, pursuant to N. J. S. A. 2A: 44-77 to 79.

' Upon default by Kolker the principals of CPA undertook the completion of the building through the formation of a new corporation1 as the general contractor and the services of a group of contractors under the supervision of a consulting engineer. Among the contractors retained by the newly formed corporation were Atlas and other firms that had formerly worked on the project under contract with Kolker.

The project continued to near completion as of the time of trial, at a greatly increased cost to CPA. The judge found that the overall cost of construction to the owner was approximately $1,500,000 instead of the Kolker contract price of $1,050,000. Kolker had been paid approximately $700,000 prior to the default and prior to the filing of the stop notices, so that CPA incurred an additional cash payout subsequent thereto to other contractors and materialmen in a sum approximating $800,000.

The filed contract provided for progress payments to Kol-ker which accounted for the $700,000 paid prior to default. In addition there was a provision for retainages by the owner amounting to 10% of the progress payments, which were withheld from Kolker by CPA. The contract further provided that when the architect issued certificates of payment aggregating $750,000, the owner was obligated to release 5% of the retainage to Kolker, “providing that the [35]*35Contractor is otherwise in full compliance with its obligations under this Agreement and that there are no unsettled claims then pending.” The architect’s certificates totalled $750,000, but CPA withheld payment of any portion of the retainage because of Kolker’s default.

It is implicit in the trial judge’s findings that Kolker had not complied with its obligations under the contract and that there were many substantial unsettled claims pending against Kolker, all of which constituted the factual underpinning of the finding that Kolker defaulted under its contract. In fact, subsequent litigation between CPA and Kolker resulted in a consent judgment for $45,000 in favor of CPA against Kolker for the breach of contract.

As a consequence of the foregoing, the trial judge concluded that CPA was legally justified in withholding the total 10% retain#ge and that as of the time of the filing of the stop notices there were no moneys rightfully due from CPA to Kolker which should have been withheld for the benefit of the stop notice claimant. Not only did the judge find that plaintiff had failed to carry its burden of proving that defendant owed contract moneys to Kolker as of the time of filing the stop notices, but he found affirmatively that there was nothing due to Kolker.

Our review of the record reveals that there is an abundance of credible evidence to support this finding and we therefore accept the same as controlling on appeal. State v. Johnson, 42 N. J. 146, 162 (1964).

In view of that finding, it follows, as the trial judge acknowledged, that plaintiff is not entitled to recovery under its stop notice claim. Nevertheless, the judge proceeded to impose liability on the theory that CPA made payments to other subcontractors in violation of the priority right of Atlas under N. J. S. A. 2A:44-80.

The trial judge found that after Kolker’s default and the stoppage of work, CPA or its newly formed corporation engaged three subcontractors, who had performed partially under contract with Kolker, to complete their particular eon-[36]*36struction functions. As part of the new and direct contracts with these firms, CPA paid to them certain moneys by way of settlement of their claims against Kolker in order to induce them to complete their respective jobs expeditiously. The judge found that CPA paid or agreed to pay the following amounts to subcontractors, $3,200 to Lupton, $5,000 to C. J. Halpin and $5,300 to Daidone Electric. In return for these payments, these subcontractors discharged the stop notices that had been filed subsequent to that of Atlas. Significantly, the judge found that these payments to other subcontractors were made in good faith as a proper business judgment in order to salvage the project after the dilemma caused by Kolker’s default.

The judge thus concluded that these payments violated the right of Atlas to the priority to which it was entitled by the earlier filing of its stop' notice, and entered judgment in favor of Atlas for $13,500 as damages for the violation of its priority right.

In our view, the judge erred in basing his judgment against CPA upon an alleged violation of stop notice priorities. While N. J. S. A. 2A:44-80 does require an owner to pay stop notice claimants in the order in which notices have been filed, this duty does not and cannot arise unless other elements of the statutory scheme are fulfilled. A basic prerequisite to the recovery on stop notice claims against an owner is that the subcontractor establish that moneys were due and owing from the owner to the general contractor as of the time of the filing of the stop notice or subsequent thereto. N. J. S. A. 2A:44-78, dealing with the retention of moneys by the owner pursuant to a stop> notice, specifically provides that the retention shall be made “out of the amount owing by him on the contract or that may thereafter become due from him on such contract.”

In the absence of evidence of advance pajnnents to the general contractor which are contrary to the filed contract provisions, or other collusive conduct designed to frus[37]*37trate the rights of the stop notice claimant,2 an owner cannot be held liable for the debts of his general contractor if there is no fund which is due and owing to that contractor. Grunt v. Zapeikov, 107 N. J. L. 143, 144 (E. & A. 1930); Stone Post Co. v. Corcoran, 80 N. J. L. 549, 551 (Sup. Ct. 1910); Reeve v. Elmendorf, 38 N. J. L. 125, 130 (Sup. Ct. 1875); Brunetti v. Grandi and Criscitelli, 89 N. J. Eq. 116, 119 (Ch. 1918). Since a stop notice operates as an assignment pro tanto of the money due the contractor, any defense available to defeat the claim of the general contractor is equally available to defeat the claim of the subcontractor. See Union Bldg. & Inv. Co. v. Forest Hill Apartments, Inc., 30 N. J. Super.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Labov Mechanical, Inc. v. East Coast Power, L.L.C.
872 A.2d 142 (New Jersey Superior Court App Division, 2005)
Legge Ind. v. Kushner Hebrew Acad.
756 A.2d 608 (New Jersey Superior Court App Division, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
364 A.2d 549, 144 N.J. Super. 31, 1976 N.J. Super. LEXIS 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-telephone-telegraph-corp-v-envirco-services-inc-njsuperctappdiv-1976.