International Fuel & Iron Corp. v. Donner Steel Co.

221 A.D. 253, 223 N.Y.S. 110, 1927 N.Y. App. Div. LEXIS 6420
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 28, 1927
StatusPublished
Cited by2 cases

This text of 221 A.D. 253 (International Fuel & Iron Corp. v. Donner Steel Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Fuel & Iron Corp. v. Donner Steel Co., 221 A.D. 253, 223 N.Y.S. 110, 1927 N.Y. App. Div. LEXIS 6420 (N.Y. Ct. App. 1927).

Opinion

Taylor, J.

The complaint allegauthat on or about July 1, 1920, a written contract was entered into; which stated that the plaintiff agreed to sell and deliver to the defendant and the defendant agreed to purchase from the plaintiff betwen July 1 and November 1, 1920, 15,000 tons of steel scrap; that deliveries were made; that on September 30, 1920, defendant requested plaintiff to suspend further shipments until defendant should be in a position to accept them; that plaintiff did not accept the named condition, but on October fourth stated different conditions under which it would be willing to suspend shipments for the time being, one of the conditions being that plaintiff should be allowed to make shipments afterward “ to complete its contract; ” that on April 18, 1921, plaintiff notified defendant that unless the latter would accept the balance of the scrap due under the contract within thirty days from April 19, 1921, plaintiff would consider that defendant had refused to take it; that on April 20, 1921, defendant replied insisting that shipments were not temporarily suspended but were suspended until such time as defendant was in a position to accept the material. Defendant did not accept and this action was brought for damages.

The amended answer admitted the making of the contract set forth in the complaint, but alleged that plaintiff and defendant also executed” another written agreement which, among other things, stated that each month’s delivery should be treated as under a separate contract independent of deliveries in other months, and that deliveries should be at the rate of 2,000 tons of heavy melting and 1,000 tons of hydraulically compressed sheet steel each month, July to November, 1920, inclusive.

The fact was established on the trial that when the Donner Steel Company’s plant was in operation its process was continuous. Open-hearth furnaces, which are used in the production of steel, require their supply of scrap, limestone and iron regularly and continuously. This was a circumstance known to both parties at the time the contract in suit was made.

The answer also set up two counterclaims based upon the failure of the plaintiff to deliver scrap and coke as agreed, and alleged damages in the sum of $107,620. The first counterclaim was withdrawn, and as to the second the jury found no cause of action. Proof under the allegations in the counterclaims was offered in defense, without objection on that ground.

The verdict of the jury was in favor of plaintiff in the sum of $117,830.41. This is an appeal from the judgment, from an order of the court denying a new trial on its minutes, and from an order granting plaintiff $2,000 additional allowance of costs.

[256]*256The plaintiff, respondent, claims that all, or nearly all, of the law of this case was settled at Special Term upon the argument of a demurrer to the complaint; respondent urging that the demurrer decision left but two questions of fact (outside of damages) for the jury to decide, viz.: (1) Whether the defendant broke its contract; and (2) whether the plaintiff waited a reasonable time before instituting suit. The decision of the Special Term was unanimously affirmed by this court, without opinion, in May, 1922 (202 App. Div. 781).

It becomes necessary to ascertain just what was decided in re the demurrer. Under the general rule, all legitimate inferences deducible from the allegations of the complaint were admitted for the purposes of the demurrer. In addition to what has been stated, the complaint alleged that the promise of the plaintiff in its letter dated October 4, 1920, was that it would suspend shipments, not until the defendant was in position to accept the material, but until further advised ” (meaning, as plaintiff claims, “ until plaintiff further advised the defendant ”). The defendant, in support of the demurrer, claimed and now claims that the action was prematurely brought; that until further advised ” meant “ until defendant further advised the plaintiff; ” and that the plaintiff could not tender the balance of the scrap until the defendant was “ in a position to accept it.” The phrase until further advised ” was construed by the Special Term to mean that the defendant might postpone the receipt of the material, but only for a reasonable time, taking all the circumstances into consideration. “ The facts alleged in the complaint are sufficient to warrant the inference that the reasonable time for the suspension expired before the action was begun.” (From the Special Term opinion.) The demurrer was accordingly overruled, and the answer of the defendant interposed. It is apparent that the Special Term decision did not settle the law of this case, for the single reason that that decision dealt with the complaint only. After the amended answer, with its affirmative allegations, was interposed, the controversy between the parties assumed a much broader aspect.

Of the two contract writings involved, the first in point of time was the one made out on the contract form of the Donner Steel Company. The latter one was on the form of the International Fuel and Iron Corporation. The former contract is known and designated as No. 1909, the latter as No. 2000. They will be referred to hereafter as the “ Donner contract ” and the International contract.” These two separate instruments were both duly signed by the parties in interest. Each one, considered separately and alone, is unambiguous. But read together they [257]*257are inconsistent in several material respects: (1) The International form calls for the delivery of 15,000 tons of scrap at any time between July 1 and November 1, 1920, while the Donner form calls for the delivery of the scrap at a fixed scheduled rate, to wit, 2,000 tons of heavy melting and 1,000 tons of hydraulically compressed sheet steel each month July 1 to November 1,1920; (2) the stated terms of payment differ; (3) the Donner contract contains a proviso that each month’s delivery is to be treated as a separate contract, independent of the provisions for deliveries in other months; and (4) specifications are annexed to the Donner contract and none to the International contract.

The Donner contract was signed in Buffalo by Mr. Hendrickson, representing the defendant, and by Mr. Enck, representing the plaintiff, on June 18, 1920. Sometime between June thirtieth and July thirteenth, the date of this contract was changed to July 1, 1920, to conform with the date when the plaintiff could legally do business in New York State.

On July 8, 1920, Enck mailed to Hendrickson duplicates of the International contract dated July 1, 1920, requesting that Hendrickson sign both and return one, and stating that the plaintiff wanted the contracts signed “ as a matter of record.” Hendrickson signed and returned one copy of the contract on or about July 13, 1920. Hendrickson testified that at about this time he had a talk with Enck in Buffalo, during which absolutely nothing was said with reference to a cancellation of the Donner contract or as to its being superseded by the International contract. This testimony was not disputed.

On the very day (July eighth) on which Enck wrote the letter to Hendrickson inclosing the International contract for execution he wrote another letter to Hendrickson in which he said: “Beg to confirm verbal arrangement made with you June 30th, in connection with your contract 1909, covering steel scrap, permitting us to begin shipments July first instead of August first as originally specified.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silver Syndicate, Inc. v. Sunshine Mining Co.
611 P.2d 1011 (Idaho Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
221 A.D. 253, 223 N.Y.S. 110, 1927 N.Y. App. Div. LEXIS 6420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-fuel-iron-corp-v-donner-steel-co-nyappdiv-1927.