International Fidelity Insurance v. County of Rockland

51 F. Supp. 2d 285, 1999 U.S. Dist. LEXIS 8196, 1999 WL 360296
CourtDistrict Court, S.D. New York
DecidedMay 24, 1999
Docket97 Civ. 3711(CM)
StatusPublished
Cited by1 cases

This text of 51 F. Supp. 2d 285 (International Fidelity Insurance v. County of Rockland) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Fidelity Insurance v. County of Rockland, 51 F. Supp. 2d 285, 1999 U.S. Dist. LEXIS 8196, 1999 WL 360296 (S.D.N.Y. 1999).

Opinion

DECISION GRANTING SUMMARY JUDGMENT ON PLAINTIFF’S CLAIM FOR A DECLARATORY JUDGMENT AND ENJOINING DEFENDANT SWCF FROM ADJUDICATING THE DELAY DAMAGES DISPUTE

McMAHON, District Judge.

This matter comes before the Court in a somewhat unusual posture. Plaintiff In *286 ternational Fidelity Insurance Company (“IFIC”) has moved by order to show cause for a permanent (not preliminary) injunction preventing Defendant SWCF Architects Engineers Planners (“SWCF”) from determining a dispute submitted to it by defendant County of Rockland in its capacity as Project Architect under a construction contract for the build-out of the ninth floor of the Dr. Robert L. Yeager Health Center. IFIC, which started as the surety for one NANCO, the original construction contractor, and which eventually took over the construction contract after NANCO’s default, seeks to enjoin SWCF from adjudicating the parties’ dispute over delay damages on two grounds: first,-that the claims resolution clause pursuant to which the matter was submitted to the Project Architect does not encompass a. dispute over post-completion delay damages; and second, that even if it does, the County’s claim was not submitted to the Project Architect for decision within 21 days after it arose, as required by the claims resolution clause.

IFIC is correct on both counts, and has therefore shown that it can succeed on the merits of its claim that SWCF is not empowered to decide the County’s claim for delay damages (which the County has also asserted as a counterclaim in this action). It is therefore entitled to summary judgment on its Second Claim for Relief, in which it seeks a declaration that the Project Architect claims resolution procedure does not apply in this case, and a permanent stay (or injunction) of any proceeding before SWCF.

BACKGROUND

The parties háve submitted huge amounts of documentation to the Court in support of and in opposition to this motion. I make the following findings of fact, all of which are undisputed.

In February 1994, Rockland County issued a contract for the build-out of the ninth floor of the Dr. Robert L. Yeager Health Center, a County-owned nursing facility in Pomona, New York. NANCO was selected as construction contractor. Under the contract, construction was to be substantially completed within 180 days, or by August 8, 1994. The contract that NANCO and the County entered into contained, among other things, a claims resolution clause, which reads as follows:

4.4.2 Decision of Architect/Engineer. Claims, 1 including those alleging an error or omission by the Architect/Engineer, shall be referred initially to the Architect/Engineer for action as provided in Paragraph 4.5. A decision by the Architect/Engineer, as provided in Sub-paragraph 4.5.4, shall be required as a condition precedent to litigation of a Claim between the Contractor and Owner as to all such matters arising prior to the date final payment is due, regardless of (1) whether such matters relate to execution and progress of the Work or (2) the extent to which the Work has been completed. The decision by the Architect/Engineer in response to a Claim shall not be a condition precedent to litigation in the event (1) the position of Architect/Engineer is vacant, (2) the Architect/Engineer has failed to render a decision within agreed time limits, (3) the Architect/Engineer has failed to take action required under Subparagraph 4.5.4 within 60 days after the Claim is made, (4) 90 days have passed after the Claim has been referred to the Architect/Engineer or (5) the Claim relates to a mechanic’s lien.

*287 Construction Contract, attached as Ex. 5 to Aff. of Americo Tiso, at § 4.4.2.

Under the terms of the Contract, NAN-CO was required to post payment and performance bonds to secure the construction project. IFIC stood surety under those bonds. Pursuant to the performance bonds, IFIC had the right, in the event of default, to arrange for NANCO to complete the contract, obtain bids from qualified contractors acceptable to the County for completion of the contract, take over the contractor’s obligations under the Construction Contract and complete performance, or waive its right to perform and complete and tender the amount due to the County. See Performance Bond, attached as Ex. 6 to Aff. of Americo Tiso, at ¶ 4. As surety, IFIC was not a party to the underlying Construction Contract, and IFIC was granted the explicit right to bring suit on any matter involving its obligations as surety. See Performance Bond, attached as Ex. 6 to Aff. of Americo Tiso, at ¶ 9.

When it became clear that NANCO would be unable to complete the Project in a timely manner, IFIC exercised its option to step into the Construction Contractor’s shoes. Accordingly, it executed a Takeover Agreement, pursuant to which IFIC agreed to complete the contract in exchange for receipt of the payment of the remaining proceeds under the Construction Contract. The Takeover Agreement provided that all the terms of the underlying Construction Contract (including, necessarily, the claims resolution clause quoted above) were incorporated into the Takeover Agreement by reference. See Takeover Agreement, attached as Ex. E to the Complaint, at ¶ 1. It also provided that nothing in the Takeover Agreement affected any of IFIC’s rights as surety under its payment and performance bonds (including, necessarily, its right to have disputes arising under those bonds determined by a court of law).

IFIC engaged one Harani Contracting Corporation (“Harani”) to complete the Project. Unfortunately, Harani proved unable to get the work done within the Completion Contract period. The County did not default IFIC and continued to pay under the Construction Contract through the Spring of 1995. Even after the County ceased payment in May 1995, IFIC and Harani continued work, and the Project was accepted as substantially complete by SWCF, as the County’s representative, on October 5, 1995. Harani thereafter ceased work on the Project and filed for bankruptcy protection. The County defaulted IFIC on March 6, 1996, but ultimately permitted it to return to the Yeager Center and complete the Project with yet another contractor. The ninth floor was accepted as complete on January 24, 1997.

On September 14, 1995, shortly before substantial completion, Rockland County served IFIC with a “Notice of Claim” for alleged delay damages totaling $4,554,735. The Notice of Claim stated that the County “intended” to submit the matter to SWCF, but the County did not submit the matter for decision to the Project Architect at that time. By letter to counsel for the County, dated October 31, 1995, IFIC denied that the question of delay damages was one properly submissible to the Project Architect, and further contended that the County had failed to submit the claim within 21 days after it arose. Rockland County neither responded to these contentions nor sent the matter to SWCF until April 1, 1997, after final completion of the Project, when it served IFIC with a more detailed analysis of claim and forwarded the matter to the Project Architect for resolution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Huen New York, Inc. v. Board of Education Clinton Central School District
67 A.D.3d 1337 (Appellate Division of the Supreme Court of New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
51 F. Supp. 2d 285, 1999 U.S. Dist. LEXIS 8196, 1999 WL 360296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-fidelity-insurance-v-county-of-rockland-nysd-1999.