International Fidelity Insurance v. China Construction America (SC) Inc.

650 S.E.2d 677, 375 S.C. 175, 2007 S.C. App. LEXIS 165
CourtCourt of Appeals of South Carolina
DecidedAugust 21, 2007
Docket4288
StatusPublished

This text of 650 S.E.2d 677 (International Fidelity Insurance v. China Construction America (SC) Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Fidelity Insurance v. China Construction America (SC) Inc., 650 S.E.2d 677, 375 S.C. 175, 2007 S.C. App. LEXIS 165 (S.C. Ct. App. 2007).

Opinion

*177 HEARN, C.J.

International Fidelity Insurance Company (Surety) appeals the circuit court’s order granting summary judgment to China Construction America (SC), Inc. (Contractor) on Surety’s action seeking payment of contract funds. We affirm.

FACTS

On May 26, 1999, Contractor entered into a general construction contract with Haier Corporation to build a large manufacturing facility in Camden, South Carolina. Contractor subcontracted the electrical work to Electrical Maintenance Technicians (Subcontractor). As a precondition of the subcontract, Contractor required Subcontractor to post performance and payment bonds in the sum of the full subcontract, $1,831,167.22. On October 19, 1999, Surety issued the bonds on behalf of Subcontractor, which named Contractor as the third party beneficiary.

During the project, Subcontractor became insolvent, and several of Subcontractor’s suppliers and subcontractors filed mechanic’s liens. Subcontractor failed to complete the subcontract on time, delaying the project for eighty-three days. Contractor demanded that Subcontractor and Surety discharge the liens pursuant to their obligations. When the liens were not immediately bonded off, Contractor brought a civil action against Subcontractor, Surety, and the three lien creditors. Contractor sought breach of contract damages against Subcontractor and Surety; a declaration of Surety’s obligation to discharge the liens; and a determination of the relative rights of the lien creditors to the subcontract retainage. Ultimately, Surety bonded off the liens and paid Subcontractor’s lien creditors such that Contractor’s only remaining claim was a breach of contract claim against Subcontractor.

On the day of trial, Subcontractor failed to appear, and Surety moved to be dismissed from the case without prejudice. Contractor consented to Surety’s request and proceeded to try its breach of contract claim against Subcontractor. The circuit court found in favor of Contractor, holding Subcontractor liable for delay in completion of the project and for Subcontractor’s failure to perform pursuant to the terms of the subcontract. At the circuit court’s request, counsel for Con *178 tractor prepared a draft order. Counsel for Surety requested a copy of the order after it was executed and suggested non-substantive changes concerning the involvement of Surety in the proceeding. Contractor consented to the proposed changes, and the circuit court issued an amended order granting judgment for Contractor against Subcontractor in the amount of $660,250.51. This judgment was not appealed.

Sometime after Contractor filed its action, Surety filed a separate action against Contractor seeking the balance of the subcontract as Subcontractor’s subrogated surety. Contractor counterclaimed averring the judgment against Subcontractor was binding and conclusive on its surety, and as a matter of law, Contractor was entitled to judgment against Surety for the full amount of the judgment against Subcontractor. In response, Surety argued the prior judgment was not binding because it was beyond the scope and coverage of the bond and that there were issues of fact as to whether the judgment in the previous case was obtained by fraud or collusion. Additionally, Surety claimed three theories of estoppel, collateral, judicial, and equitable, applied to prevent Contractor from asserting its counterclaims. Both parties moved for summary judgment. The circuit court granted Contractor’s motion for summary judgment finding the prior judgment against Subcontractor was binding on Surety as a matter of law. Further, the court found no merit to Surety’s allegations of fraud and collusion. Lastly, the court held Surety’s estoppel arguments were without merit. This appeal followed.

STANDARD OF REVIEW

When reviewing the grant of a summary judgment motion, this court applies the same standard of review as the trial court under Rule 56, SCRCP. Cowburn v. Leventis, 366 S.C. 20, 30, 619 S.E.2d 437, 443 (Ct.App.2005). Summary judgment is proper when there is no issue as to any material fact and the moving party is entitled to a judgment as a matter of law. Rule 56(c), SCRCP; Helms Realty, Inc. v. Gibson-Wall Co., 363 S.C. 334, 340, 611 S.E.2d 485, 488 (2005). To determine whether any triable issues of fact exist, the reviewing court must consider the evidence and all reasonable inferences in the light most favorable to the non-moving party. Law v. S.C. Dep’t of Corr., 368 S.C. 424, 434, 629 S.E.2d 642, 648 *179 (2006). When plain, palpable, and indisputable facts exist on which reasonable minds cannot differ, summary judgment should be granted. Ellis v. Davidson, 358 S.C. 509, 518, 595 S.E.2d 817, 822 (Ct.App.2004).

LAW/ANALYSIS

I. Conclusiveness of the Bond

Surety argues the trial court erred in its determination that the judgment against Subcontractor was conclusive and covered within the scope of the bond. Surety attacks the conclusiveness of the prior judgment on its obligations under the bond, arguing the amount of damages awarded was beyond the scope of the bond. 1 We disagree.

In South Carolina, a judgment against a principal is binding and conclusive on a surety. Ward v. Fed. Ins. Co., 233 S.C. 561, 106 S.E.2d 169 (1958). In Ward, the supreme court addressed the effect of a prior judgment against a principal on subsequent litigation against the surety. Id. The court stated:

As a general rule, in all cases where the liability of a surety is dependent on the outcome of litigation in which his principal is or may be involved, a judgment against a principal is binding and conclusive on the surety, and the surety may not impose defenses which should or might have been set up in the action in which the judgment was recovered, or require proof of the facts on which the judgment rests, or attack the validity of the judgment, except for fraud or collusion or want of jurisdiction. The rule is applicable even though the surety had no notice of the suit or opportunity to defend.

Ward, 233 S.C. at 564, 106 S.E.2d at 170 (citing 72 C.J.S. Principal and Surety § 261).

This issue was most recently addressed in this court’s opinion in Cooper v. Beauliau, 310 S.C. 392, 426 S.E.2d 819 *180 (Ct.App.1992). In that case, Cooper obtained a judgment against an auto dealer and sought to recover against dealer’s surety. Id. at 393-94, 426 S.E.2d at 820.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B & a Development, Inc. v. Georgetown County
641 S.E.2d 888 (Supreme Court of South Carolina, 2007)
Ellis v. Davidson
595 S.E.2d 817 (Court of Appeals of South Carolina, 2004)
Cowburn v. Leventis
619 S.E.2d 437 (Court of Appeals of South Carolina, 2005)
Law v. South Carolina Department of Corrections
629 S.E.2d 642 (Supreme Court of South Carolina, 2006)
Cooper v. Beauliau
426 S.E.2d 819 (Court of Appeals of South Carolina, 1992)
Ward v. Federal Insurance Co.
106 S.E.2d 169 (Supreme Court of South Carolina, 1958)
Helms Realty, Inc. v. Gibson-Wall Co.
611 S.E.2d 485 (Supreme Court of South Carolina, 2005)
McEachern v. Black
496 S.E.2d 659 (Court of Appeals of South Carolina, 1998)
Staubes v. City of Folly Beach
529 S.E.2d 543 (Supreme Court of South Carolina, 2000)
L. B. Price Mercantile Co. v. Redd
99 S.E.2d 51 (Supreme Court of South Carolina, 1957)
Whiteside v. Cherokee County School District No. One
428 S.E.2d 886 (Supreme Court of South Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
650 S.E.2d 677, 375 S.C. 175, 2007 S.C. App. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-fidelity-insurance-v-china-construction-america-sc-inc-scctapp-2007.