International Contractors Corp. v. Illinois Union Insurance

79 A.D.3d 1428, 913 N.Y.S.2d 800

Opinion

Stein, J.

Cross appeals from an order of the Supreme Court (Meddaugh, J.), entered April 9, 2010 in Sullivan County, which denied plaintiffs motion for summary judgment and denied a motion by defendant CLG Financial for, among other things, summary judgment dismissing the complaint against it.

Plaintiff is a corporation established by Johan Adriaans and his wife, Mary Adriaans, who are the sole corporate officers. The business conducted by the corporation is primarily the installation of roofs on commercial and residential buildings. In connection therewith, plaintiff contacted defendant CLG Financial, an insurance broker, to procure a policy of liability insurance and an umbrella policy. CLG secured such policies with defendant Illinois Union Insurance Company and its parent company, defendant ACE Westchester Specialty Group (hereinafter collectively referred to as defendants), for which CLG was paid a commission. In June 2005, during the period covered by the policies, plaintiff replaced a roof on a garage at the home of Laurence Spiro and Heather Spiro. Shortly thereafter, the Spiros and their guest, Judith Warren, were found dead in the Spiro home. The cause of their deaths was ultimately determined to be carbon monoxide poisoning, which apparently emanated from the home’s furnace.

Approximately one year later, wrongful death actions were commenced against plaintiff on behalf of the Spiros and Warren, alleging that plaintiff negligently permitted or allowed obstruction of a rooftop vent for the furnace, thereby contributing to the deaths. Upon receiving notice of such actions from plaintiff, CLG notified defendants thereof. After defendants disclaimed coverage, plaintiff commenced this declaratory judgment action against defendants and CLG alleging, among other things, negligence, breach of contract and breach of fiduciary duty on the part of CLG. Plaintiff thereafter moved for summary judgment, seeking a declaration that CLG is obligated to defend and indemnify it and to reimburse plaintiff for all defense costs incurred prior to the date of judgment or settlement of the underlying actions. CLG opposed the motion and cross-moved for summary judgment dismissing the complaint. Plaintiff opposed the cross motion with regard to the first (breach of contract), second (negligence and misrepresentation), tenth (detrimental reliance) and eleventh (breach of fiduciary [1430] duty) causes of action.1 Supreme Court denied both motions and these appeals by plaintiff and CLG ensued.

We affirm. Plaintiffs action is premised on its contention that it gave reasonable notice to CLG of the occurrence at the Spiro residence in accordance with directions given by CLG to plaintiff for reporting potential or actual claims, and that CLG breached its obligations to plaintiff by failing and neglecting to timely report the occurrence to defendants and/or to monitor a potential claim. CLG primarily asserts that it breached no duty to plaintiff. CLG further asserts that, inasmuch as plaintiff failed to provide it with timely notice of the occurrence, even if it did breach a duty to plaintiff by failing to promptly report the occurrence to defendants, such failure would have been irrelevant, as defendants would have disclaimed coverage in any event. Therefore, CLG argues that its acts or omissions cannot be the proximate cause of plaintiffs damages.

According to the uncontroverted testimony of Mary Adriaans, she met with Donald Scott Leibert, CLG’s representative, in 2004 to discuss plaintiffs insurance needs. Subsequent to that meeting, CLG presented plaintiff with an insurance package that included a document entitled “Business Insurance Summary for International Contractors Corp.” That document described, among other things, the duties and responsibilities of CLG’s “service team,” which listed Barbara Walker as an account manager responsible for the coordination of all client services and Nancy Calvario as the claims coordinator. Calvario’s duties included “[cjontact person for claims reporting/involved in initial submission of claims/follow up with insurance company claims personnel. Monitors claim status/investigation and management.” Leibert also testified that he advised the Adriaanses to call Calvario “[i]f you have a claim or possible occurrence that you think may be a claim . . . [and] she will report it on your behalf to the insurance carrier so they have knowledge of the claim and coordinate contact with the carrier thereafter during the claim process.”

The insurance policy ultimately procured by CLG on plaintiffs behalf included both general liability and umbrella coverage. Under the general liability policy, the insured was required to notify the carrier of an occurrence, claim or suit “as soon as practicable.” The umbrella portion of the policy contained a similar provision, but required notice to the carrier “as soon as [1431] possible.” It is well settled that, when notice of an occurrence is required to be given as soon as practicable pursuant to a policy of liability insurance, such notice must be given within a reasonable period of time (see Great Canal Realty Corp. v Seneca Ins. Co., Inc., 5 NY3d 742, 743 [2005]; Klersy Bldg. Corp. v Harleysville Worcester Ins. Co., 36 AD3d 1117, 1118 [2007]). However, failure to provide notice may be excused when the insured has a reasonable good faith belief of nonliability (see Klersy Bldg. Corp. v Harleysville Worcester Ins. Co., 36 AD3d at 1118). The question of reasonableness is generally a question of fact for a jury (see id. at 1119).

Free access — add to your briefcase to read the full text and ask questions with AI

International Contractors Corp. v. Illinois Union Insurance, 79 A.D.3d 1428, 913 N.Y.S.2d 800 (N.Y. Ct. App. 2010).

79 A.D.3d 1428 (International Contractors Corp. v. Illinois Union Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Great Canal Realty Corp. v. Seneca Insurance
833 N.E.2d 1196 (New York Court of Appeals, 2005)
Hoffend & Sons, Inc. v. Rose & Kiernan, Inc.
851 N.E.2d 1149 (New York Court of Appeals, 2006)
Alvarez v. Prospect Hospital
501 N.E.2d 572 (New York Court of Appeals, 1986)
Wojcik v. Empire Forklift, Inc.
14 A.D.3d 63 (Appellate Division of the Supreme Court of New York, 2004)
Klersy Building Corp. v. Harleysville Worcester Insurance
36 A.D.3d 1117 (Appellate Division of the Supreme Court of New York, 2007)
Bruckmann, Rosser, Sherrill & Co.
65 A.D.3d 865 (Appellate Division of the Supreme Court of New York, 2009)
Sutton Park Development Corp. Trading Co. v. Guerin & Guerin Agency Inc.
297 A.D.2d 430 (Appellate Division of the Supreme Court of New York, 2002)