International Contracting Co. v. United States

47 Ct. Cl. 158, 1911 U.S. Ct. Cl. LEXIS 1, 1911 WL 1341
CourtUnited States Court of Claims
DecidedDecember 18, 1911
DocketNo. 30803
StatusPublished
Cited by1 cases

This text of 47 Ct. Cl. 158 (International Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Contracting Co. v. United States, 47 Ct. Cl. 158, 1911 U.S. Ct. Cl. LEXIS 1, 1911 WL 1341 (cc 1911).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court:

■ The question for decision arises on the defendants’ demurrer to the petition on the ground that the facts averred do not constitute a cause of action. The question presented by the demurrer is, Did the parties by the contract sued on intend it to be an entire or a separable one?

The work authorized by the act of March 2,1907 (34 Stat. L., 1073, 1075), was the improvement of Newport Harbor, B. I. In response to the advertisement therefor the claimant’s bid was received and accepted, and on December 9, 1907, it entered into the contract annexed to and made part of the petition, Whereby it obligated itself to excavate, as estimated in the specifications, 582,000 cubic yards of material, scow measurement, at 22 cents per cubic yard. Ten percent of the amount earned was to be deducted from the monthly payments until the same should equal $10,000. Of the material to be excavated it was estimated that about 222,000 cubic yards were to be in making the channel leading [160]*160through the harbor 18 feet deep at mean low tide and 150 feet wide, to be completed on or before June 80, 1908, and the remainder, estimated to consist of about 860,000 cubic yards, in extending the 13-foot anchorage area to the harbor line along the south side of the channel, to be completed on or before December 31, 1909.

Upon notice of the approval of the contract and within the time therein fixed the claimant commenced work and, as averred, completed the two areas within the time agreed upon respectively, no final inspection being made or demanded until the completion of the entire work, when the Government made final inspection of both areas and settled with the claimant upon'the basis thereof, deducting, as averred, the sum of $10,919.04 for 49,632 cubic yards over-depth dredging in said two areas, of which sum so deducted $7,741.58 claimed in this action was for 35,189 cubic yards overdepth dredging in the 18-foot channel way, against which deduction the claimant, as averred, then and there protested in writing. Hence this action.

The quantity of overdepth dredging in the two areas at the time the final inspection was made is not controverted by the averments of the petition, nor is any claim made for overdepth dredging the 13-foot anchorage area.

The claimant contends that the two areas to be dredged were separate and distinct pieces of work, done at different times, the unit price for which was apportionable to each, and that, therefore, the contract was a separable one, entitling the claimant to a final inspection of the 18-foot channel way within a reasonable time after its completion and before the completion of the 13-foot anchorage area.

In support of its contention the claimant, among other things, avers that the dredging of the 13-foot anchorage area was. not contemplated until after the 18-foot channel way had been completed, inspected, and accepted, for the purpose of determining the amount of overdepth dredging, as well as the amount due for the work done; that though the officers of the Government accepted the 18-foot channel way the work was not finally inspected until after the inspection and acceptance of the 13-foot anchorage area, when final inspection of the entire work was made, and the overdepth [161]*161dredging in the two areas was thereby disclosed; that though no demand was made therefor the failure of the Government to make final inspection of the 18-foot channel way within a reasonable time after its completion and before the completion of the 18-foot anchorage area was unreasonable and in violation of the claimant’s rights under the contract, by reason of which, it is averred, the Government is estopped from making the deduction for overdepth dredging in the 18-foot channel way.

The averments of the petition so far as material and not in conflict with the contract and specifications must, for the purposes of the demurrer, be taken as true.

Paragraphs 2 and 9 of the contract provide:

“2. All materials furnished and work done under this contract shall, before being accepted, be subject to a rigid inspection by an inspector appointed on the part of the Government, and such as do not conform to the specifications set forth in this contract shall be rejected. The decision of the engineer oflicer in charge as to quality and quantity shall be final.
“ 9. It is further agreed by and between the parties hereto that until final inspection and acceptance of, and payment for, all of the material and work herein provided for, no prior inspection, payment, or act is to be construed as a waiver of the right of the party of the first part to reject any defective work or material or to require the fulfillment of any of the terms of the contract.”

Paragraph 22 of the specifications provides:

“ The depth of cutting in the channel will be from 0 to 3 feet; in the anchorage area from 2 to 10 feet. The finished work must be of the full prescribed depth, and no allowance for overdepth exceeding 1 foot will be made. If over-depths greater than allowed are dredged, the excess will be measured in place and increased by oné-fourth and deducted from the scow measurement.”

How the officers of the Government could have accepted the 18-foot channel way as averred before final inspection in the face of paragraph 9 of the contract set out above is not shown other than by the averment, which is clearly in [162]*162conflict therewith. This brings us to the legal question involved.

In the construction of contracts the intention of the parties thereto must be inquired into, and such intention effectuated if not contrary to law or public policy; and “ if the language is clear and unambiguous it must be taken according to its plain meaning as expressive of the intention of the parties, and under settled principles of judicial decision should not be controlled by the supposed inconvenience or hardship that may follow from such construction.” (Loud v. Romono Land and Water Company, 153 U. S., 564, 576.) Nor is the court limited to any particular provision, but must embrace within its construction the entire contract.

As the parties competent to contract are tile best judges of their motives their contract should be construed not only in the light of the circumstances under which the same was signed but in harmony with their conduct in performance. (Bell v. Bruen, 1 How., 169, 186; Chicago, R. I. & P. R. R. Co. v. Denver & R. G. R. R. Co., 143 U. S., 596, 609.) In other words, the court in the case of ambiguous language should endeavor to ascertain the situation of the parties and their interpretation, if añy, of the contract for the purpose of determining their intention. (Topliff v. Topliff, 122 U. S., 121, 131.) This, however, does not mean that where there is no ambiguity in provisions standing alone they are not subject to interpretation in connection with doubtful provisions to ascertain the meaning of the entire contract. (O'Brien v. Miller, 186 U. S., 287, 297.) And while contracts requiring construction should be construed most strongly against the party preparing the same, the other party is not thereby relieved from performance on his part, though he may not have read the contract. (Upton v. Tribilcock, 91 U. S., 45, 50.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 158, 1911 U.S. Ct. Cl. LEXIS 1, 1911 WL 1341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-contracting-co-v-united-states-cc-1911.