Intercon Manufacturing, Inc. v. Centrifugal Casting MacHine Co.

1993 OK CIV APP 143, 875 P.2d 1149, 65 O.B.A.J. 1992, 1993 Okla. Civ. App. LEXIS 193
CourtCourt of Civil Appeals of Oklahoma
DecidedAugust 17, 1993
Docket78777, 79866 and 80134
StatusPublished
Cited by2 cases

This text of 1993 OK CIV APP 143 (Intercon Manufacturing, Inc. v. Centrifugal Casting MacHine Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intercon Manufacturing, Inc. v. Centrifugal Casting MacHine Co., 1993 OK CIV APP 143, 875 P.2d 1149, 65 O.B.A.J. 1992, 1993 Okla. Civ. App. LEXIS 193 (Okla. Ct. App. 1993).

Opinion

MEMORANDUM OPINION

HANSEN, Chief Judge:

Appellant, Centrifugal Casting Machine Company, Inc., (CCM), seeks review of three orders of the trial court in this contract action. Appellee, Intercon Manufacturing, Inc., (Intercon), brought this action against CCM to recover the balance due on a construction contract which required Intercon to manufacture and supply a cement lining system to CCM. The trial court rendered partial summary judgment in favor of Intercon for the balance due on the contract. After a non-jury trial, the trial court rendered judgment in favor of Intercon on its action to recover certain interest from CCM, but denied Intercon’s claim of fraud. In the third order appealed from, CCM seeks review of the trial court’s order which granted Inter-con’s request for attorney fees and prejudgment and postjudgment interest.

Sometime prior to June 14, 1989, the date of the contract between the parties, CCM entered into a contract with representatives from China for the sale of equipment used to manufacture water pipe. This equipment consisted of various components which were subcontracted by CCM to various subcontractors. One component was the lining system which is the subject of the contract between the parties. It is undisputed that the requirements of the contract between the parties and the contract between CCM and the Chinese are independent of each other.

The schedule incorporated into the contract between CCM and Intercon provided February 15, 1990, as the date the system would be delivered for export. However, the entire project between CCM and the Chinese was put on hold after political events in China threatened financing of the deal. On July 17, 1990, CCM sent a letter to Intercon requesting it to issue a “Stop Work Order” and to stop all work on the system until CCM’s financing with the Chinese was worked out. Intercon complied by shutting down production and laying off employees. By July 31, 1990, the equipment Intercon was to supply to CCM was 96% complete. In November, 1990, CCM had successfully renegotiated a letter of credit with the Chinese and the project was resumed. The *1151 water pipe system was exported to China March 9, 1991.

The contract between the parties provided for the manufacture, testing, and training of personnel for a complete cement lining system. The contract details technical specifications of the system and requires Intereon to supply certain training and testing. Paragraph 3 of the contract provides:

Intereon will provide facilities, equipment, staff and instruction for up to twenty people in the use and maintenance of this equipment. It will be the responsibility of the buyer to provide translation to and from English, and the pace of instruction will be constructed to permit translation and questions. The nature and tone of the school will be especially suited to the Chinese, and will assume some technical background on the part of the students. Inter-con will provide basic refreshments and supply tea making equipment for the convenience and comfort of the participants.

The contract further sets forth the requirements of classroom instruction and specific areas in which hands-on training should be provided. The contract also contains a provision which requires Intereon to provide on-site technical advisors in China. That provision is as follows:

Intereon will provide technical advisors on-site, when required, to assist in the set up, tuning and operation of this equipment. Air and surface transportation, western-style hotel accommodations and food, and other direct expenses will be the responsibility of CCMCO. Fees for this service are $300 per man per day and will be assessed for each full day out of Tulsa.

Finally, the contract provides:

8.1 Equipment and facilities will be available for testing and training within the schedule provided by the Buyer. The schedule provided becomes a part of this purchase order contract.
8.1.1 Inspection will take place within 15 days of sellers notification of readiness. 8.2 Training will take place approximately 15 days after notification of buyers readiness. Training will be available for 30 days.

The contract price was $344,636.26 and was payable 75% “upon completion and inspection of the equipment” by CCM and 25% “upon completion of personnel training”. CCM admits it has not paid Intereon $43,-080.00 under the contract. It maintains this balance is not due under the contract because Intereon has not yet completed the training requirements of the contract. Specifically, CCM argues Intereon failed to supply the “hands-on” training, required by paragraph 3, to a second group of Chinese representatives and that such failure authorizes it to withhold the balance.

The schedule attached to the contract slated January 15, 1990 for testing and training. Two groups of Chinese came to the United States for training in February, 1991, and May, 1991. The parties agree the first group received all the required training from Inter-con at the Intereon facility under the terms of the contract. However, CCM maintains the second group did not receive the hands-on training portion as required by the contract and that Intereon should be required to travel to China to complete the hands-on training. Hands-on training was impossible in the U.S. when the second group came in May of 1991 because the system had been shipped to China in March, 1991.

The depositions and affidavits attached to the summary judgment pleadings clearly show the target dates in the initial schedule were not met.. The evidence suggests the parties had reached an alternate agreement regarding the training requirements of the contract. It is the substance of this alternate agreement that is in dispute. Because of the delays caused by the upheaval in China and CCM’s requirement the lining system be shipped on a particular boat before their letter of credit expired, Intereon submits it agreed to fully train the first group from China even though some evidence suggests that group was not the group intended to receive the training. When the second group arrived, Intereon conducted training which did not include some of the hands-on training required by the contract. 1 Whether the par *1152 ties had agreed Intercon was required to give this second group hands-on training, either in the U.S. or in China, or whether the parties had agreed to waive hands-on training for the second group, is a question of fact which must be determined by the trier of fact. 2

Summary judgment is a procedural device used to reach a final judgment where there is no dispute as to any material facts. Hargrave v. Canadian Valley Electric Cooperative, Inc., 792 P.2d 50, 55 (Okla.1990). All inferences in the evidence must be taken in favor of the party opposing the motion. Id. Summary judgment is improper if under the evidence, reasonable people could reach different conclusions from the facts. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Manchester Gas Storage, Inc.
309 B.R. 354 (N.D. Oklahoma, 2004)
Lovekamp-Serrato v. Lovekamp
2001 OK CIV APP 71 (Court of Civil Appeals of Oklahoma, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
1993 OK CIV APP 143, 875 P.2d 1149, 65 O.B.A.J. 1992, 1993 Okla. Civ. App. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intercon-manufacturing-inc-v-centrifugal-casting-machine-co-oklacivapp-1993.