Intek Construction Corp. v. Tegrity Contractors, Inc.

CourtDistrict Court, W.D. Arkansas
DecidedFebruary 18, 2026
Docket5:25-cv-05211
StatusUnknown

This text of Intek Construction Corp. v. Tegrity Contractors, Inc. (Intek Construction Corp. v. Tegrity Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intek Construction Corp. v. Tegrity Contractors, Inc., (W.D. Ark. 2026).

Opinion

IN THE UNITED STATES DISTRICT COURT WESTERN DISTRICT OF ARKANSAS FAYETTEVILLE DIVISION

INTEK CONSTRUCTION CORP. PLAINTIFF

V. CASE NO. 5:25-CV-5211

TEGRITY CONTRACTORS, INC. DEFENDANT

OPINION AND ORDER

Before the Court is Defendant Tegrity Contractors, Inc.’s Motion to Compel Arbitration (Doc. 7) and Brief in Support (Doc. 8), to which Plaintiff Intek Construction Corp. filed a Response in Opposition (Doc. 9) and Tegrity filed a Reply (Doc. 12). On February 10, 2026, the Court held a hearing on the Motion. The sole question before the Court is whether the parties’ dispute should be sent to arbitration. The Court evaluates Tegrity’s Motion under Federal Rule of Civil Procedure 12(b)(6), as the Court has not considered any facts outside the record in evaluating the parties’ arguments and arriving at its decision. See Seldin v. Seldin, 879 F.3d 269, 272 (8th Cir. 2018). To survive a motion to dismiss for failure to state a claim, “a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). When analyzing a motion to dismiss, “a court must accept the allegations contained in the complaint as true and make all reasonable inferences in favor of the nonmoving party.” Martin v. Iowa, 752 F.3d 725, 727 (8th Cir. 2014). I. BACKGROUND In mid-2024 Tegrity, a Texas contractor, hired Intek, an Arkansas subcontractor, to perform renovation work at certain hospital buildings operated by the Veterans Administration in Little Rock, Arkansas, and in Fayetteville, Arkansas. See Doc. 3, ¶¶ 7–

8. The parties executed a Master Subcontract Agreement (“MSA”) setting forth Intek’s scope of work. Included in the MSA was the following arbitration clause: Any dispute, controversy, or claim arising out of or related to this Agreement or any Purchase Order, or any breach or termination of this Agreement or any Purchase Order, and any alleged violation of any federal, state, or local statute, regulation, common law, or public policy, whether sounding in contract, tort, or statute, shall be submitted to and decided by binding arbitration.

(Doc. 3-1, ¶ 12.05). Critically, the arbitration clause specified that “[a]rbitration shall be administered by the American Arbitration Association and held in Collin County, Texas before a single arbitrator . . . .” Id. (emphasis added). Representatives from Intek and Tegrity manifested their agreement to all terms in the MSA by signing the face sheet of the document and initialing every page, including the page with the arbitration clause. The parties’ business relationship quickly soured, and on March 18, 2025, Tegrity terminated the MSA. See Doc. 3, ¶¶ 17–18. Intek claims that it substantially performed a majority of its contract work at both the Little Rock and Fayetteville construction sites before it was terminated, but Tegrity failed to reimburse Intek for its labor and materials, which combined exceeds $1.5 million. See id. Rather than bring these claims before an arbitrator, as agreed, Intek filed a lawsuit against Tegrity in Arkansas state court on September 11, 2025, claiming breach of contract and tortious interference with business expectancy, as well as alternative claims for equitable relief. Intek anticipated the parties’ current dispute over arbitration: Count I of the Amended Complaint is a claim for declaratory judgment, which asks the Court to find that the arbitration clause in the MSA is void under Arkansas law. See id. ¶¶ 41–51. According to Arkansas Code § 4-56-104(c), an arbitration clause in a construction contract is void if the arbitration venue is somewhere other than Arkansas.

Tegrity removed the case to federal court, citing diversity as the basis for federal subject matter jurisdiction. See Doc. 2 (citing 28 U.S.C. § 1441). In Tegrity’s view, the Federal Arbitration Act (“FAA”), 9 U.S.C. §§1–16, preempts Arkansas Code § 4-56-104(c) and renders the MSA’s arbitration clause valid and enforceable. II. DISCUSSION Before getting into the specifics of Arkansas Code § 4-56-104(c), it is clear from the outset that the FAA applies to the MSA’s arbitration clause, which the parties executed by mutual consent. See Volt Info. Scis., Inc. v. Bd. of Trs. of Leland Stanford Junior Univ., 489 U.S. 468, 479 (1989) (“Arbitration under the [FAA] i[s] a matter of consent, not coercion.”). Section 2 of the FAA is a congressional “declaration [of] a national policy

favoring arbitration”; it broadly governs “contracts evidencing a transaction involving commerce.” Southland Corp. v. Keating, 465 U.S. 1, 10 (1984) (citing 9 U.S.C. § 2). The MSA falls under § 2 of the FAA because the contract involved parties from different states and a construction project that utilized materials flowing through interstate commerce. Since the FAA governs the arbitration clause, the Court’s role is “limited to determining (1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement encompasses the dispute.” Pro Tech Indus., Inc. v. URS Corp., 377 F.3d 868, 871 (8th Cir. 2004). Arkansas is one of thirty-two states to have enacted a “home-court” statute to govern the litigation and arbitration of construction contracts. See Daniel D. McMillan, et al., Construction Home-Court Statutes: Scope, Enforcement, and Preemption Under the Federal Arbitration Act, 43 Construction Law. 9, 2 (Fall 2024). A home-court construction

statute prohibits parties to a construction contract from agreeing to litigate or arbitrate outside the state where the construction work took place. Arkansas Code § 4-56-104(c) is a typical home-court construction statute in that it renders “void and unenforceable” any “provision, covenant, clause, or understanding written in a construction agreement or construction contract . . . that requires any litigation, arbitration, or other alternative dispute resolution proceeding arising from the construction agreement or construction contract to be conducted in another state.” If a construction contract’s arbitration clause specifies an out-of-state venue, that clause will be severed “and shall not cause the entire . . . contract to become unenforceable.” Ark. Code Ann. § 4-56-104(d). Returning to the two-step process for analyzing arbitration clauses under the FAA,

step one asks whether the clause is valid and enforceable. Setting aside for a moment the issue of whether Arkansas Code § 4-56-104(c) (hereafter, “Home-Court Statute”) voids the MSA’s arbitration clause, the Court finds that the clause is otherwise enforceable because it manifests mutual agreement and mutual assent, legal consideration, and a meeting of the minds. See Alltel Corp. v. Sumner, 360 Ark. 573, 576 (2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Doctor's Associates, Inc. v. Casarotto
517 U.S. 681 (Supreme Court, 1996)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Cd Partners, LLC v. Grizzle
424 F.3d 795 (Eighth Circuit, 2005)
R.A. Bright Construction, Inc. v. Weis Builders, Inc.
930 N.E.2d 565 (Appellate Court of Illinois, 2010)
Jordan v. Diamond Equipment & Supply Co.
207 S.W.3d 525 (Supreme Court of Arkansas, 2005)
M.C. Construction Corp. v. Gray Co.
17 F. Supp. 2d 541 (W.D. Virginia, 1998)
William Martin v. State of Iowa
752 F.3d 725 (Eighth Circuit, 2014)
Scott Seldin v. Theodore Seldin
879 F.3d 269 (Eighth Circuit, 2018)
Alltel Corp. v. Sumner
203 S.W.3d 77 (Supreme Court of Arkansas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Intek Construction Corp. v. Tegrity Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/intek-construction-corp-v-tegrity-contractors-inc-arwd-2026.