Insurance Company of North America and Fidelity and Casualty Company of New York, as Subrogees of Aes Placerita, Inc. v. Abb Power Generation Inc.

112 F.3d 70, 1997 U.S. App. LEXIS 8077
CourtCourt of Appeals for the Second Circuit
DecidedApril 23, 1997
Docket686, Docket 96-7691
StatusPublished
Cited by4 cases

This text of 112 F.3d 70 (Insurance Company of North America and Fidelity and Casualty Company of New York, as Subrogees of Aes Placerita, Inc. v. Abb Power Generation Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Insurance Company of North America and Fidelity and Casualty Company of New York, as Subrogees of Aes Placerita, Inc. v. Abb Power Generation Inc., 112 F.3d 70, 1997 U.S. App. LEXIS 8077 (2d Cir. 1997).

Opinion

LEVAL, Circuit Judge:

Defendant ABB Power Generation Inc. appeals from the judgment of the United States District Court for the Southern District of New York, Lewis A. Kaplan, Judge, finding that plaintiffs’ claims are not barred by applicable statutes of limitations, holding that plaintiffs’ tort claims are arbitrable, and ordering arbitration. The question whether plaintiffs’ demand for arbitration of the contract claims is timely turns on the interpretation of New York statutory law on which there is no authoritative guidance from the *71 courts of New York. We have decided to certify this question to the New York Court of Appeals. We respectfully request the Court’s guidance on this issue governed by the law of New York.

As to the arbitrability of the tort claims, we defer ruling until we receive the answer of the New York Court of Appeals.

Background

This action was precipitated by an equipment failure at a California power plant. The plant was built for AES Placerita, Inc. (“AES” or the “Owner”) by a predecessor of defendant ABB Power Generation Inc. (“ABB” or the “Builder”). The Owner was insured by plaintiffs Insurance Company of North America and Fidelity and Casualty Company of New York (“INA/FCC” or the “Insurers”). The Owner and the Builder entered into a contract for the design and construction of the plant. Construction under the contract was completed in due course, and the plant was accepted by the Owner in September 1988. Some two years later, in January 1991, one of the plant’s steam turbines malfunctioned and was so badly damaged that the entire facility was shut down until June of that year. The Owner filed a claim with the Insurers, which paid the Owner more than $5.5 million, covering repairs and business interruption. Acting as the Owner’s subrogees, the Insurers then served a demand on the Builder that it submit to arbitration under the terms of its contract with the Owner to answer tort and contract claims.

After unsuccessful attempts to settle with the Builder, the Insurers filed suit in New York Supreme Court for New York County to compel arbitration and obtain a declaratory judgment that their claims were not time barred. The Builder removed the case to the United States District Court for the Southern District of New York, and answered to the effect that the contract claims were untimely and that it had no obligation to arbitrate tort claims. After trial on a stipulated record, Judge Kaplan rejected the Builder’s defenses and ordered the parties to proceed to arbitration. Insurance Co. of N. Am. v. ABB Power Generation, Inc., 925 F.Supp. 1053 (S.D.N.Y.1996). The Builder brought this appeal from those rulings.

On appeal, the Builder contends that the tort claims were not subject to arbitration and that the contract claims were barred by California’s 4-year limitation period for claims on written contracts, Cal.Civ.Proc. Code § 337(l)(West 1997), made applicable under New York’s “borrowing statute.” N.Y. C.P.L.R. § 202 (McKinney 1990).

We defer ruling on Judge Kaplan’s finding that the Insurers’ tort claims are arbitrable. The question whether the demand for arbitration of the contract claims was timely under New York law we respectfully certify to the New York Court of Appeals.

Discussion

The parties agree that New York law governs the determination whether the demand for arbitration was timely. The contract’s arbitration article specifies, “All Disputes between the parties hereto shall be resolved ... by an arbitration panel ... except that the Panel shall have no authority to act upon a claim if the party claimed against could successfully assert the statute of limitations as a bar to such claim if a law suit were brought on it.” This commitment to arbitrate “shall be specifically enforceable under the prevailing arbitration laws of the State of New York.” The contract thus applies the limitation period governing litigation of a claim under New York law to a demand for arbitration of that claim. 1

The question remains whether New York’s choice of law principles call for use of New *72 York’s limitation period. In particular, the parties dispute whether New York’s borrowing statute, N.Y. C.P.L.R. § 202 (McKinney 1990), makes California’s limitation period applicable. Under § 202, “[a]n action based upon a cause of action accruing without [New York] state cannot be commenced after the expiration of the time limited by the laws of either the state [of New York] or the place without the state where the cause of action accrued,” unless plaintiff is a New York resident. Id.

The parties are not New York companies, and the plant breakdown occurred in California. The Builder asserts that because the claims “accrued” in California, § 202 directs the borrowing of California’s statute of limitations, which is stricter than New York’s and allegedly bars the claims. Judge Kaplan rejected this argument. He ruled that § 202 is inapplicable because the contract’s selection of a New York arbitration venue precludes arbitration outside New York. In his view, § 202 was designed to protect New York defendants from time-barred foreign claims. Foreign claimants who were barred from bringing the claims where they arose might be tempted to resuscitate them by taking advantage of more generous New York limitation periods. Section 202 was designed to foreclose such forum shopping by requiring the New York courts to apply the shorter foreign statutes in these circumstances. Here, because the forum selection clause designates New York as the exclusive venue for arbitration, there is no issue of forum shopping. In Judge Kaplan’s view, because the Insurers never had the option to bring the Owner’s claims in California, the anti-forum-shopping policies underlying § 202 would have no application to their action. New York would simply treat this as an arbitration appropriately sought in New York, rather than as an improper effort to resuscitate a lapsed California claim.

In refusing to apply § 202, Judge Kaplan relied primarily on the analysis set forth in Stafford v. International Harvester Co., 668 F.2d 142 (2d Cir.1981). In Stafford, the plaintiff, a New Jersey resident, had been injured in an accident in Pennsylvania when the steering mechanism on his tractor truck failed. Plaintiff brought suit in New York against a mechanic shop which had performed repairs on the steering mechanism; the relevant Pennsylvania statute of limitations provided a shorter period than New York’s and would have barred the claims. Applying § 202, the district court borrowed the Pennsylvania limitation period and dismissed the suit as untimely.

This court reversed on appeal. The mechanic shop had no ties to Pennsylvania that could subject it to personal jurisdiction there.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
112 F.3d 70, 1997 U.S. App. LEXIS 8077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/insurance-company-of-north-america-and-fidelity-and-casualty-company-of-new-ca2-1997.