Inland Wetland Watercourses v. Scarveles, No. 30 57 82 (Apr. 3, 1991)

1991 Conn. Super. Ct. 3262
CourtConnecticut Superior Court
DecidedApril 3, 1991
DocketNo. 30 57 82
StatusUnpublished

This text of 1991 Conn. Super. Ct. 3262 (Inland Wetland Watercourses v. Scarveles, No. 30 57 82 (Apr. 3, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inland Wetland Watercourses v. Scarveles, No. 30 57 82 (Apr. 3, 1991), 1991 Conn. Super. Ct. 3262 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION ON MOTION TO DISSOLVE TEMPORARY INJUNCTION This motion was brought by the defendants to dissolve an ex parte temporary injunction issued on October 4, 1990. That injunction commanded and enjoined defendants "to wholly and absolutely desist and refrain from continuing to conduct a regulated activity at the subject property in violation of the Connecticut General Statutes, the Bethany Inland Wetlands Watercourses Regulations, and the Plaintiff's Cease Restore Order. . . ." Based on the credible evidence presented at the hearing on this motion, the court finds the following material facts established:

On November 1, 1989, in Application #360, the defendant Scarveles, applied for a permit from the Bethany Inland Wetlands Watercourses Commission to conduct regulated activities as CT Page 3263 follows: Regrade, restore east end of pond — Phase III .79 acres (3/4 acre) Map — Final Grading Plan Bethany West Lake."

On January 25, 1990, that permit was denied by the Commission, which required the defendant to do as follows:

"[R]estore all areas east of the line established under permit #358 (which is 600' (six hundred feet) easterly of the spillway), as nearly as possible to the original countours in that area allowed under permit #199. This does not require reconstruction of the small former ponds in said area. Prior to the commencement of the required restoration work, sediment and erosion controls shall be installed where necessary and inspected and approved by the Commission."

The denial of Application # 360 and the accompanying restoration order were not appealed.

Based on a site inspection conducted on July 28, 1990, the Commission determined that the defendants had excavated in and filled portions of the east end of the pond — the area specifically addressed in the restoration order. That activity involved work for which permission had been sought by defendant Scarveles in Application #360. As of July 28, 1990, all of the Bethany permits held by Scarveles had expired or were the subject of pending litigation.

On July 31, 1990, the Commission issued a Cease and Restore Order to the defendants directed at their filling, grading and disturbing of wetlands on the premises as observed by the Commission members during the July 28, 1990 inspection.

The order stated the following:

The work proposed in application #360 has been performed in spite of the application having been denied. The stipulations noted in the notice of denial have been ignored.

Other violations include non maintenance of sediment and erosion controls, pumping silt laden water into a wetland, creating stockpiles in an area to be cleared and seeded, resulting in additional runoff of pollutants into a wetland.

Defendants were ordered as follows:

"[Y]ou are hereby ordered to CT Page 3264

1.) Cease any and all activity within the perimeter of the pond except for that work necessary to restore the grades and wetlands in the area stipulated in the denial of your application #360 and:

2.) Cease the removal of any materials stockpiled on the site until the restoration work has been completed and so certified in writing by the Commission;

3.) Submit an application to the Commission for a permit to do the additional grading, etc, necessary to complete the project and have a permit issued for said work."

A show cause hearing concerning the Cease and Restore Order was held before the Commission on August 7, 1990. At the hearing, the defendant Scarveles disputed the Cease and Restore Order claiming that he had already complied with parts 1 and 2 of the Order. He requested, and the Commission agreed, to re-inspect the property. The hearing was continued to August 20, 1990.

The Commission inspected the property on August 10, 1990 The following members of the Commission were present in addition to Mr. Scarveles: Dorothy Parker, John Garcia, Chairman Eric Stone, and Andrew Levetin, a proposed but not official member of the Commission. The Commission members concluded from that inspection that no work had been undertaken to comply with the order. Based on independent site viewings, Commissioner members Civitello and Evans concurred with that conclusion.

On August 20, 1990, the Commission, after reconvening the hearing, ordered the Cease and Restore Order to continue and ordered defendant to submit a new application explaining the work to be done to comply with the order. On September 11, 1990, the Bethany Town Clerk was served with a copy of an administrative appeal of the Commission's action in continuing the Cease and Restore Order. That appeal is pending in this court as Scarveles, Trustee v. Inland Wetlands Commission of the Town of Bethany, No. CV 90 0304925S.

On October 1, 1990, Commission Chairman Eric Stone received a complaint that, despite the existence of the Cease and Restore Order, defendants were conducting grading activities at the site and were hauling material off site. On October 2, 1990, Mr. Stone, on a site visit, observed a bulldozer and backhoe removing material from the southwestern slope of the pond. The material was being placed in dump trucks which left the site and headed CT Page 3265 west toward Beacon Falls. The excavation was occurring approximately ten feet from the water of the pond.

When Commissioner Stone reminded Mr. Scarveles that he did not have a local wetlands permit authorizing that work, Mr. Scarveles stated his intention to continue working because a State Department of Environmental Protection (DEP) Water Diversion Permit authorized his activities there. On or about September 14, 1990, defendant Scarveles had obtained a DEP Divers permit on which allowed grading and filling at the property. However, Mr. Scarveles had been informed, by letter of the DEP Inland Water Resources Division, that the Diversion Permit did not obviate the need to obtain local wetlands permits prior to conducting regulated activities at the site.

The continuing violations and unauthorized work at the site have adversely affected the fragile wetlands and watercourses in that area and downstream. The work has also threatened to exacerbate the erosion and sedimentation which have already occurred in the pond and downstream.

Prior to July 31, 1990, the defendant, Scarveles, had applied for and obtained various other permits for excavation work at the Simpsons Pond site from both the DEP and the Town of Bethany. All prior Bethany permits had expired, however, by November 1, 1989. Scarveles had obtained a DEP permit on July 23, 1990 for dam construction and a DEP permit, on September 14, 1990, for diversion of water.

STANDARD FOR ISSUANCE: OF A TEMPORARY INJUNCTION

Section 22a-44 (b) of Conn. Gen. Stat. provides as follows:

"The superior court, in an action brought by the commissioner, municipality, district or any person shall have jurisdiction to restrain a continuing violation of said sections, to issue orders directing that the violation be corrected or removed and to assess civil penalties pursuant to this section."

In order to obtain a temporary injunction, the Commission must establish that the defendants' activities at the site violated the wetlands statutes, local regulations, or a condition of an order by the Commission. Conservation Commission v. Price,193 Conn. 414, 428-430 (1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crabtree v. Van Hise
464 A.2d 865 (Connecticut Superior Court, 1983)
Zoning Commission v. Leninski
376 A.2d 771 (Connecticut Superior Court, 1976)
Gerdis v. Bloethe
467 A.2d 689 (Connecticut Superior Court, 1983)
Water Resources Commission v. Connecticut Sand & Stone Corp.
364 A.2d 208 (Supreme Court of Connecticut, 1975)
Conservation Commission v. Price
479 A.2d 187 (Supreme Court of Connecticut, 1984)
Mario v. Town of Fairfield
585 A.2d 87 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 3262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inland-wetland-watercourses-v-scarveles-no-30-57-82-apr-3-1991-connsuperct-1991.