Ingram Barge Co. v. West Lake Quarry & Material Co.

357 F. Supp. 624, 1973 U.S. Dist. LEXIS 14610
CourtDistrict Court, E.D. Missouri
DecidedMarch 8, 1973
DocketNo. 71 A 369(1)
StatusPublished
Cited by2 cases

This text of 357 F. Supp. 624 (Ingram Barge Co. v. West Lake Quarry & Material Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingram Barge Co. v. West Lake Quarry & Material Co., 357 F. Supp. 624, 1973 U.S. Dist. LEXIS 14610 (E.D. Mo. 1973).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

MEREDITH, Chief Judge.

Findings of Fact

1. Ingram Barge Co., a corporation, was at all times material hereto the owner of deck barges Joe Barrett, Elmo Barrett, WT-1200, BL-102, BL-104, BL-108 and BL-112.

2. West Lake Quarry and Material Co., Inc., a corporation, was at all times material hereto, the owner and operator of a rock quarry with barge-loading facilities at or about limo, Missouri.

[625]*6253. The WT series barges, the Joe Barrett, Elmo Barrett and WT-1200, are steel barges built by Nashville Bridge Company; the WT-1200 was built in 1958 and the Joe Barrett and Elmo Barrett were built in 1961. All barges of that series measure 40 feet wide, 195 feet long, and 9% feet deep. They have twelve main bouyancy compartments and two rake compartments.

4. The BL series barges, the BL-102, BL-104, BL-108 and BL-112, were built by Jeffboat, Inc., in the latter part of 1966, and measure 35 feet wide, 200 feet long, and 10 feet deep. They have eight bouyancy compartments and two rake compartments.

5. The internal supporting structures of both series of barges are basically the same, being a deck of y2 inch steel, welded on top of deck stringers, which are U-shaped steel beams, laid on their sides, intermittently spaced and placed parallel to each other. These stringers are in turn welded on top of 9 inch channel irons, or top chords. Supporting these chords are vertical beams welded perpendicularly to the chords and diagonals. Giving added support are beams running diagonally between the verticals, thus forming a webbing. This entire structure is called a truss 'and there are three trusses per compartment in the WT series, and six trusses per compartment in the BL series of barges.

6. The external features of both series of barges are the same, being a flat deck surface with the loading area above the compartments. There are occasional timberheads and kevels placed throughout the deck, and access hatches to each compartment. On one side or the other of the deck, running the length of the compartments, is a 30 inch high sideboard, which serves the purpose of keeping stone off the river side of the deck on one side of the barge, thus permitting a walkway down the side of the barge when the barge is loaded, and of being a backstop for unloading purposes.

7. From the time these barges were put into service until the present day, they had been engaged in the rock-hauling trade and had been loaded at Reed’s Quarry in Gilbertsville, Kentucky, except for the instant loading. The method of loading at Reed’s Quarry was by dumping onto the deck of the barge, rock which consisted of rip rap (weighing from 15 to 125 to 200 pounds), and quarry run (weighing of a fine dust to 3,000 pounds). The distance the rock fell would be anywhere from 6 to 14 feet.

8. The method of unloading this rip rap and quarry run stone is by means of a dragline bucket which is pulled across the deck from the side coaming, thus filling the bucket with stone. In the course of unloading a barge, the bucket will travel the full width of the barge and by successive trips will travel the full length of the barge. On at least one occurrence, during the time in question, the barges were unloaded by means of a tracked front end loader known as a hi-lift.

9. Rock barges will sustain severe wear and tear because of the nature of the trade. Decks will be washboarded, indentations will be made on the decks of the barge and over a period of time, a set down of the deck up to 2% inches is not uncommon.

10. Ingram Barge Co. inspected each of the barges during the off season in the spring of 1968 at the Ingram repair facility. Any damage which was found on any barge was noted on an inspection report. The inspection was a general visual inspection and was made by John Fischer, who by his own admission is not an expert in barge construction and repair. The Elmo Barrett, the WT-1200, and the Joe Barrett, three of the four more heavily damaged barges, were inspected respectively on March 13-14, 1968, March 12, 1968, and February 20, 1968. At that time the Elmo Barrett was found to have 70-75 verticals which needed rewelding and were repaired; the inspection report for the WT-1200 showed that loose verticals (of an unspecified number and location) were [626]*626welded back and the inspection report for the Joe Barrett showed that loose braces (of an unspecified number and location) in three compartments were welded. Loose verticals will cause the deck to be weakened and subject to damage by loading. The inspection report on the other barges was unexceptional.

11. Subsequent to the inspection of the barges in the spring of 1968 and prior to loading at West Lake, the barges were in constant service and loaded at various times, all by Ingram Barge at Reed’s Quarry with rip rap and/or quarry run each as follows: the Elmo Barrett was loaded twice, the WT-1200 was loaded four times, the Joe Barrett was loaded twice, the BL-102 was loaded three times, the BL-108 was loaded four times, the BL-104 was loaded twice and the BL-112 was loaded once. Subsequent to each loading at Reed’s Quarry, the barges were, of course, unloaded at destination. At no time after any loading or unloading, and prior to the time that they were delivered to West Lake, was any inspection made of any of the barges to determine its condition and particularly the condition of the internal structures. Ingram Barge has failed to prove that the barges when delivered to West Lake for loading were “staunch, tight and in all respects seaworthy” and in good condition.

12. The barges were delivered to West Lake for loading in the summer of 1968 because Ingram Barge (Reed’s Quarry) could not supply the heavier stone of 3-6 tons and 11-15 tons required by its contract.

13. West Lake used four pieces of equipment to load the barges: a Euclid 27-ton truck; a Michigan 375 front-end loader, with a lifting capacity of 29,000 lbs.; and an experimental model of a front-end loader with a maximum weight of 83,530 lbs.

14. West Lake loaded the barges by first constructing a ramp of small chat rock up to the barge being loaded and then a front-end loader would drive over this ramp onto the barge and deposit the load of stone on the far end of the barge. Thereafter, the Euclid truck would back out the length of the barge and dump the stone against the pile of stone laid there on the prior load.

15. Each barge was loaded once by West Lake with the exception of the Joe Barrett, which was loaded twice. The barges were loaded with coverstone, weighing 3-6 tons, except for the WT-1200, which carried a split load of 3-6 ton coverstone, together with 20 pieces of 11-15 ton coverstone. No inspection was made after the West Lake loading or within a reasonable time thereafter of the internal structures of the barges to determine their condition at that time, even though Fischer was worried about the possibility of damage being done to the barges. After the loading at West Lake, the Joe Barrett was again loaded at Reed’s and unloaded at its destination and no inspection of the barge was made prior to the time that it was delivered to West Lake in late summer of 1968 for another loading. No inspection was made of the barge Joe Barrett after the second loading at West Lake.

16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
357 F. Supp. 624, 1973 U.S. Dist. LEXIS 14610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingram-barge-co-v-west-lake-quarry-material-co-moed-1973.