Ingle Manufacturing Co. v. San Diego Oil Products Corp.

227 P. 627, 67 Cal. App. 458, 1924 Cal. App. LEXIS 446
CourtCalifornia Court of Appeal
DecidedMay 24, 1924
DocketCiv. No. 4191.
StatusPublished
Cited by1 cases

This text of 227 P. 627 (Ingle Manufacturing Co. v. San Diego Oil Products Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingle Manufacturing Co. v. San Diego Oil Products Corp., 227 P. 627, 67 Cal. App. 458, 1924 Cal. App. LEXIS 446 (Cal. Ct. App. 1924).

Opinion

HOUSER, J.

The defendant appeals from a judgment rendered in favor of the plaintiff in an action brought to recover the agreed purchase price of $2,396 for twelve galvanized iron tanks, each of the capacity of 8,189 gallons.

The contract was evidenced by certain letters passing between the parties. Of such letters those which are considered of material consequence in determining tins controversy specified that the tanks be guaranteed against leaks before leaving plaintiff’s factory, and that the tanks be placed on platforms not exceeding twelve inches in height. The construction of the tanks was commenced at the plaintiff’s factory, but was completed on the property of the defendant. The platforms on which the tanks were to rest were furnished and constructed by the defendant, and while used for the purpose for which they were intended, the trial court found that they were not “accepted by the plaintiff,” and “that the plaintiff assumed no obligations in regard to the foundations furnished by the defendant.” The court further found: “That said tanks did comply with plain*tiff’s written guarantee and did comply with the express warranty found in Civil Code section 1770, and were reasonably fit for the purpose for which they were manufactured ; that four of said tanks leaked to the extent of 295¾ gallons, but that the plaintiff was not responsible for the leaks for the reason that the foundation upon which said tanks were placed and which foundation was furnished by the defendant, was not substantial and presented an uneven and *460 yielding surface, and that the leakages were caused by the defective platform furnished by the defendant, and that the plaintiff is not responsible therefor; that the said tanks were not defective in workmanship.”

If it be determined with reference to the tanks which leaked that all the warranties, express as well as implied, were fulfilled by the plaintiff, or that such tanks leaked because of the fault of the defendant, the plaintiff was entitled to judgment; on the other hand, if the leaks were caused by the fault of the plaintiff, the judgment should be reversed. That part of the contract which provided that the tanks should be guaranteed against leaks before leaving the factory of the plaintiff, was modified by implied consent of the parties in that the tanks were only partially constructed at the factory of the plaintiff and the tanks were completed at the plant of the defendant. It must therefore have been within the contemplation of the parties as a part of such modification that, whether constructed at the plaintiff’s factory or at the defendant’s plant (without 'reference to the foundation on which the tanks rested), the tanks would be free from leaks on their completion. The warranty contained in section 1770 of the Civil Code, covering the manufacture of articles in the class in which the subject matter of this action falls, is to the effect that these tanks were guaranteed by the manufacturer to be reasonably fit for the purpose for which they were made. As shown by the findings, considering the fact that the tanks leaked only to the extent of 295¾ gallons, which was less than one-tenth of one per cent of the aggregate of 342,627 gallons of oil contained in the tanks during their use of about four months; or, to put the matter more concretely, about one drop out of 16,000 drops in a one week’s storage of oil—the conclusion by the lower court that the tanks did comply with the terms of the contract between the parties, as well as with the warranty as contained in and required by the provisions of section 1770 of the Civil Code, does not seem entirely unreasonable. But assuming that the aggregate capacity of the tanks was about 98,000 gallons, the week’s leakage, instead of being represented by one drop out of 16,000 drops, would be shown by a loss of three drops out of 16,000, or slightly less than one-half a drop per day. The contract was uncertain in its terms as to who was obligated to construct the foundation; but in view of the *461 construction placed upon the language of the contract by the parties thereto, and the consequent assumption by the defendant of that part of the contract, it must be presumed that the intention was that such duty was to devolve upon the defendant. The testimony of the plaintiff’s superintendent, as taken from the transcript on appeal, is as follows : “When I first went out to the defendant’s plant, I wanted to know where the tanks were going to be placed. Mr. Peacock showed me where the tanks were to be located and asked me about the foundation. He asked me if a base of scrap lumber he had there, of various lengths, breadths and thicknesses, would do. I said ‘No.’ He asked if the tanks could be set right on the ground—I said they could but the chemical action that would result would cause holes and leaks. Then he asked me if a base made of some three inch by eight inch planks about ten feet long would do. I replied if they were placed on the ground, properly leveled, they would in my judgment serve the purpose all right. The defendant’s men then leveled off the ground and placed boards for us to put the tanks on. I should say these planks were laid from two to three inches apart. The first supply of planks were of uniform length, of about sixteen feet long, but they were exhausted before they had enough foundation. After that, defendant got some other planks which were mostly two by twelve, and of various lengths to complete the foundations. I should judge five or six tanks were placed on the planks of uniform length and thickness. Some of the planks were so placed that the ends of the planks were beneath tanks. I should judge every other tank had plank ends beneath it. The tanks were eleven feet in diameter and were set from a foot to eighteen inches apart. ... We had heavy rain fall after the first day or two we were on the job, which prevented our completing the tanks right away. . . . The eaves of the shed covering the tanks containing the crude oil emptied just about on the edge of the platforms which were beneath the tanks we built. . . . The water that flowed off this roof flowed right on the ground in and around these tanks. . . . The ground around and about the platform upon which the tanks were placed was soaked with water.”

With reference to the effect upon the tanks produced by the manner of construction of the platforms and their surroundings, the same witness stated: “The tanks were leak *462 ing because the seams had cracked in one or two places causing leaks. ... I concluded these cracks were caused by the settling of the foundation. I found some planks had settled more than others and that the planks were not even on a level. In some places planks had settled so much that they no longer touched or supported the tank. I found a leak at one such place where one plank was high and the planks on either side had settled so they were three-fourths of an inch below the bottom of the tank. Such an unevenness of the foundation would cause the bottom of the tank to bulge and put an unnecessary strain on the seams. This would tend to crack open the solder and cause a leak. A full tank of oil would weigh approximately 56,000 pounds; that would make a weight of about 580 pounds per square foot all over the surface of the bottom of the tank. That weight would be sufficient to draw and open the seams at the bottom of the tank if it was resting upon an uneven surface.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Fish & Game Commission v. District Court
84 P.2d 798 (Montana Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
227 P. 627, 67 Cal. App. 458, 1924 Cal. App. LEXIS 446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingle-manufacturing-co-v-san-diego-oil-products-corp-calctapp-1924.