Information Communication Corp. v. Unisys Corp.

181 F.3d 629, 1999 WL 499559
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 16, 1999
Docket97-20826, 97-20827
StatusPublished
Cited by15 cases

This text of 181 F.3d 629 (Information Communication Corp. v. Unisys Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Information Communication Corp. v. Unisys Corp., 181 F.3d 629, 1999 WL 499559 (5th Cir. 1999).

Opinion

BENAVIDES, Circuit Judge:

These two appeals arise from a cross-filed suit between Information Communication Corporation (“ICC”) and Unisys Corporation (“Unisys”) over a bilateral contract between the two companies. At *631 trial, the jury found through a special verdict that both companies had ' materially breached the contract, that Unisys had breached first, and that Unisys’s and ICC’s respective damages from the breaches were $192,000 and $2.7 million. After the trial, but before the district court rendered judgment, Abbott, Simses, Album & Knister (“Abbott Simses”), which represented ICC during part of the case, sought to intervene to protect its right to recover its attorneys’ fees from any award to ICC. As to the suit between the companies, the district court ruled that neither ICC nor Unisys was entitled to an award and entered a take-nothing judgment. The district court also denied Abbott Sims-es motion to intervene. All three parties appealed the district court’s rulings which we now affirm as to the take-nothing judgment.

I. BACKGROUND

At the heart of this case is a contract that ICC and Unisys entered into in April 1988. Titled the Software Development Subcontract (the “Master Contract”), it governed the relationship of ICC and Uni-sys as joint creators of public-safety computer systems that could be used by police departments in small-to-medium-size cities to facilitate 911 dispatch, to manage records, and to write reports. ICC created and supplied the software applications, and Unisys supplied the computer hardware. Both parties agree that the Master Contract, with addenda, should be construed as one agreement and that performance by each party was intended to be measured by performance to each of the eight cities that purchased one of the Unisys/ICC systems. Both parties also agree that ICC’s and Unisys’s covenants under the Master Contract were mutually dependent, such that if either party materially breached the contract, the other was excused from performing its contractual obligations.

Each city that installed a Unisys/ICC system encountered various and significant start-up problems. Although ICC’s software had run on computers used to demonstrate the systems, it did not function on the hardware ultimately supplied by Uni-sys for installation. The problems cost each -oí the companies greatly; The substantial amount. of time and money that ICC spent rewriting the software for use on the Unisys machines exacerbated the company’s cash flow problems and forced ICC to close its doors in January 1991. Although Unisys was ultimately able to supply the cities with working systems after ICC closed, it paid more than $2 million to settle claims made by the cities under the terms of their contracts.

After ceasing its operations, ICC filed suit against Unisys, and Unisys counterclaimed. Each asserted that the start-up problems had been caused by the other having breached the Master Contract. During a nine-day trial in August 1996, the parties introduced twenty-two witnesses and volumes of exhibits to show whether ICC and Unisys had fulfilled their contractual obligations. ICC contended that Uni-sys had supplied inadequate hardware with inadequate central processing units as well as insufficient memory and disk space. ICC argued that its software had run adequately on earlier Unisys hardware and hardware from other manufacturers. While admitting that its delivery of some software was late under the terms of the Master Contract, ICC attributed the delays to its need to rewrite its software to work on Unisys’s inadequate machines. Unisys, on the other hand, claimed that its hardware had functioned properly and that the problems had arisen due to ICC’s software. Unisys contended that ICC’s software did not function as promised and that it was delivered late at numerous sites. Unisys also contended that the inadequacies in its hardware, if any, were due to ICC having underestimated the technical requirements of its own software.

At the end of the trial, the jury was instructed to answer six questions. In the answers to those questions, the jury found that both Unisys and ICC had failed, with *632 out excuse, to perform material obligations under the Master Contract; that Unisys had been the first to breach materially; that $2.7 million dollars would fairly compensate ICC for Unisys’s breach; and that $192,000 would fairly compensate Unisys for ICC’s breach. After trial, ICC moved for judgment on the verdict and Unisys moved for a Rule 50 judgment n.o.v. or, in the alternative, a remittitur of ICC’s damage award.

In April 1997, the district court produced a forty-five page memorandum and order granting Unisys’s motion, and entered a take-nothing judgment for both parties. The district court held that neither ICC nor Unisys could recover damages under the Master Contract because each had materially breached it. The court ruled in the alternative that, as a matter of law, the evidence presented to the jury concerning ICC’s damages was too speculative to support any recovery. Finally, the court stated that even if ICC was permitted some recovery as a matter of law, the damages awarded by the jury exceeded the bounds of reasonable recovery, and that they should be reduced from $2.7 million to $132,280.

In the same memorandum and order, the district court ruled on several motions pending before it, including the Abbott Simses motion to intervene. Abbott Sims-es represented ICC in its litigation against Unisys from March 1991 to October 1994. In October 1994, the attorney at Abbott Simses that had led the team representing ICC moved to a different firm, taking the ICC account with’ him. Having not received any payments for the legal services provided to ICC, Abbott Simses argued that it was entitled to intervene 'in order to recover by preference and priority out of the first monies received by ICC from the judgment. The district court denied Abbot Simses motion, ruling: “Given the Court’s primary decision herein that ICC may not recover as a matter of law, these motions are moot. In any event, the Motion for Leave is denied. The matters in issue are not sufficiently related to the operative facts in this six year old case to justify joinder of the proposed new claims.”

II. DISCUSSION

A. Take-Nothing Judgment

ICC argues on appeal that the district court erred both in interpreting Texas law as requiring a take-nothing judgment, and in concluding that ICC offered insufficient evidence at trial to support the jury’s finding that it had $2.7 million in lost profits damages. Unisys does not contest the district court’s take-nothing judgment. It does argue, however, that if ICC’s award is reinstated, Unisys’s award should also be reinstated to setoff any recovery by ICC. We review de novo the district court’s judgment as a matter of law, whether based upon an interpretation of Texas law or based upon the sufficiency of the evidence. See, e.g., Cobb v. Natural Gas Pipeline Co., 897 F.2d 1307, 1309 (5th Cir.1990) (reviewing conclusions of state law de novo); Conkling v. Turner, 18 F.3d 1285

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes v. Dresser L L C
W.D. Louisiana, 2025
Wellogix, Inc. v. Accenture, LLP
823 F. Supp. 2d 555 (S.D. Texas, 2011)
Meaux Surface Protection, Inc. v. Fogleman
607 F.3d 161 (Fifth Circuit, 2010)
Gomez v. St. Jude Medical Daig Division Inc.
442 F.3d 919 (Fifth Circuit, 2006)
Bowman v. Orleans Parish School Board
141 F. App'x 291 (Fifth Circuit, 2005)
Piotrowski v. City of Houston
237 F.3d 567 (Fifth Circuit, 2001)
Aguillard v. McGowen
207 F.3d 226 (Fifth Circuit, 2000)
McGruder v. Will
204 F.3d 220 (Fifth Circuit, 2000)
Spring v. Beverly Ent Ms
Fifth Circuit, 2000
Rutherford v. Harris County Texas
197 F.3d 173 (Fifth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
181 F.3d 629, 1999 WL 499559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/information-communication-corp-v-unisys-corp-ca5-1999.