INFINITY DESIGN BUILDERS v. Hutchinson
This text of 964 So. 2d 752 (INFINITY DESIGN BUILDERS v. Hutchinson) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
INFINITY DESIGN BUILDERS, INC., Appellant,
v.
M.F. HUTCHINSON, Appellee.
District Court of Appeal of Florida, Fifth District.
*754 Penny W. Schmidt and R. Gregg Jerald, of Schutt, Schmidt, Burnett & Noey, Jacksonville, for Appellant.
P. Campbell Ford and Ali A. Tedrick, of Ford, Miller & Wainer, P.A., Jacksonville, for Appellee.
MONACO, J.
Infinity Design Builders, Inc., appeals an order of the trial court denying its motion to stay arbitration proceedings. Because there was no agreement between the parties to arbitrate, and because Infinity did not knowingly waive its constitutional right to litigate its dispute with the appellee, M.F. Hutchinson, in court, we reverse.
The relevant facts of this case begin in 2001, when the parties executed a contract in which Infinity agreed to construct an oceanfront custom residence on Mr. Hutchinson's real property. Infinity thereafter and in due time constructed the house. In 2005, Mr. Hutchinson notified Infinity and the American Arbitration Association ("AAA"), that he was demanding arbitration with respect to his claim that during the hurricanes of the previous year, significant leaking occurred around the windows of the home. As a result, according to Mr. Hutchinson, the windows were damaged and mold and mildew infiltrated the house. Mr. Hutchinson attached to his demand for arbitration a copy of an AIA construction contract that required disputes over the construction of the residence to be resolved by arbitration and mediation. The contract, which was purported to be the one entered into by the parties, bore no signatures. An addendum also submitted by Mr. Hutchinson was signed by the parties, but contained no reference to arbitration.
During the four-month period between the filing of the demand for arbitration and the objection to arbitration, the parties had exchanged letters concerning the arbitration proceeding, and Infinity filed a motion with the AAA to abate the arbitration until Mr. Hutchinson complied with the notice requirements of Chapter 558, Florida Statutes (2006), which deals with construction defects. In addition, Infinity denied liability and reserved the right to assert affirmative defenses. The parties further agreed that the arbitration would be held in Jacksonville, and that certain AAA procedures would not apply. Finally, the parties sent a checklist for conflicts to the AAA, agreed on the selection process and the criteria for the arbitrator, and took a number of other steps consistent with their participation in arbitration.
At that point Infinity filed an objection to arbitration with the AAA asserting that in fact no arbitration agreement existed between Infinity and Mr. Hutchinson, because the contract attached to the demand *755 for arbitration was not an accurate copy of the contract actually executed by the parties. The correct contract, according to Infinity, was actually signed by the parties, but had the entire section on mediation and arbitration crossed out. The crossed out section was, moreover, initialed by each of the parties.
A month later Infinity filed a complaint in circuit court seeking a stay of the arbitration proceeding in accordance with section 682.03(4), Florida Statutes (2006). The trial court granted a temporary stay of the arbitration and set a hearing date to consider Infinity's motion to stay arbitration.
At the conclusion of the hearing, which was non-testimonial in nature, the trial court entered an order on Infinity's motion to stay arbitration in which it related that the contract attached to the demand for arbitration "was not the correct, signed contract." It also confirmed that the correct contract was the one offered by Infinity in which the arbitration provision had been struck by the parties. Nevertheless the trial court, considering only the documents submitted by the parties and legal argument, denied the motion to stay arbitration on the theory that Infinity's participation in the arbitration process waived its right to have its disputes with Mr. Hutchinson decided in a trial forum. Infinity appeals. Our jurisdiction is based on rule 9.130(a)(3)(C)(iv), Florida Rules of Appellate Procedure. As the only evidence before the court was in the form of the same documents that are now before us, we review the order de novo.
Article I, section 21 of the Florida Constitution requires the courts of this state to be "open to every person for redress of any injury." As with any other constitutional right, the right of access to the courts may be relinquished. See Kaplan v. Kimball Hill Homes Fla., Inc., 915 So.2d 755, 761 (Fla. 2d DCA 2005), review denied, 929 So.2d 1053 (Fla.2006).
Arbitration stands on a different foundation because it is a matter of contract. Accordingly, a party cannot be compelled to arbitrate any dispute that he or she did not agree to submit to arbitration. Kemiron Atl., Inc. v. Aguakem Int'l, Inc., 290 F.3d 1287, 1290 (11th Cir.2002); Technical Aid Corp. v. Tomaso, 814 So.2d 1259, 1261 (Fla. 5th DCA 2002). In deciding whether arbitration is required, therefore, one must necessarily begin by asking whether the parties contractually agreed to arbitrate. If they did not, then unless there is a waiver of the right, Article I, section 21 requires submission of the legal dispute to the courts.
In the present case it is abundantly clear that the parties did not agree to arbitrate any dispute, including any that might arise out of the construction contract. The trial court nevertheless ruled that the matter of the water leakage around the windows would remain in arbitration because it found that Infinity had waived its right to have its dispute with Mr. Hutchinson litigated in the courts. We think the trial court erred.
Waiver is "the voluntary and intentional relinquishment of a known right or conduct which implies the voluntary and intentional relinquishment of a known right." See Raymond James Fin. Servs., Inc. v. Saldukas, 896 So.2d 707 (Fla.2005); see also LeNeve v. Via South Florida, L.L.C., 908 So.2d 530, 535 (Fla. 4th DCA 2005).
When a party moves to compel arbitration of an issue, a trial court must consider the following three elements: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived. See Raymond *756 James, 896 So.2d at 711; Seifert v. U.S. Home Corp., 750 So.2d 633, 636 (Fla.1999). Here, of course, there is no valid written agreement to arbitrate, and there are, accordingly, no arbitrable issues under the contract. Thus, unless Infinity has waived its right to seek a resolution of the dispute in the courts, as the trial court indeed found, the conclusion that Infinity may not be forced to arbitrate is compelled.
Whether a party has waived its right to arbitrate or presumably to litigate depends on the trial court finding: (1) the existence of a right which may be waived; (2) actual or constructive knowledge of the right; and (3) an intent to relinquish the right. See LeNeve, 908 So.2d at 535. Proof of waiver may either be express or implied from "conduct or acts that lead a party to believe that the right has been waived." Id.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
964 So. 2d 752, 2007 Fla. App. LEXIS 13250, 2007 WL 2403169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/infinity-design-builders-v-hutchinson-fladistctapp-2007.