Industrial Pipe, Inc. v. Plaquemines Parish Council

139 So. 3d 1168, 2013 La.App. 4 Cir. 1345, 2014 WL 2134535, 2014 La. App. LEXIS 1345
CourtLouisiana Court of Appeal
DecidedMay 21, 2014
DocketNo. 2013-CA-1345
StatusPublished
Cited by1 cases

This text of 139 So. 3d 1168 (Industrial Pipe, Inc. v. Plaquemines Parish Council) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Pipe, Inc. v. Plaquemines Parish Council, 139 So. 3d 1168, 2013 La.App. 4 Cir. 1345, 2014 WL 2134535, 2014 La. App. LEXIS 1345 (La. Ct. App. 2014).

Opinion

ROLAND L. BELSOME, Judge.

| jThis appeal is taken from the trial court’s granting of a Coastal Use Permit (CUP) in favor of Industrial Pipe. For the following reasons, we affirm.

Industrial Pipe operates the Oakville Landfill in Plaquemines Parish. Industrial Pipe has 65.7 acres of land permitted by the Louisiana Department of Environmental Quality for the operation of a Type III C & D landfill. Within the 65.7 acres are 8.3 acres which are designated wetlands. A CUP is required in order for Industrial Pipe to operate in the 8.3 acres of wetlands.

Originally, Industrial Pipe submitted its application for a CUP in October of 2001. The Plaquemines Parish Council (Council) granted the CUP in November of 2003. In 2009, this Court determined that the granting of the CUP by the Council was proeedurally flawed, since the Statement of Justification for Recommendation of Coastal Zone Permit was not issued by the Parish Coastal Zone Administrator until April 21, 2006. That action by the Council violated the procedural guidelines. Thus, the CUP was vacated.1

|2In April of 2010, Industrial Pipe submitted a new CUP application. The Department of Natural Resources determined the issue was a local concern and did not review either CUP application. After Plaquemines Parish’s Coastal Program Manager and the Parish Coastal Zone Advisory Committee reviewed the new application, it was recommended that the Parish Council grant Industrial Pipe’s application. However, at its September 22, 2011 meeting, by a vote of eight to one, the Parish Council denied Industrial Pipe’s CUP application.

Industrial Pipe filed suit against the Parish alleging that the denial of the CUP application was unreasonable; arbitrary; and capricious, not consistent with the goals, policies and provisions of state law; and violated Plaquemines Parish’s local ordinances. Thereafter, Oakville Community Action Group, Louisiana Environmental Action Network and Gloria Mayfield intervened in the suit.

The trial court proceeded with a trial de novo.2 In a trial de novo, the trial court is the court of original jurisdiction.3 Following trial, the trial court rendered judgment granting Industrial Pipe a CUP. The Parish and the intervenors (collectively the appellants) appealed. The following assignments of error have been raised on appeal:4

1. The trial court erred in holding that allowing Industrial Pipe’s expansion into areas zoned Flood Plain, did not violate applicable Plaquemines Parish zoning ordinances;
2. The trial court erred in holding that the running of prescription under LSA-R.S. 9:5625 négated zoning ordinances;
ls3. The trial court erred in holding that the evidence at trial demonstrated Industrial Pipes’s satisfaction of applicable coastal use statutes and regulations, and the Louisiana Administrative Code;
4. The trial court erred when it determined that Industrial Pipe’s CUP application satisfied the criteria under LAC 43:I.701(H) without conducting the requisite analytical process required to demonstrate compliance with that section; and
[1170]*11705. The trial court erred when it failed to determine that Industrial Pipe’s CUP application violated La. R.S.49:214.30(C)(3).

In addition to the common assignments of error asserted by the appellants, the inter-venors assert that the trial court erred in admitting certain documentary evidence offered by Industrial Pipe.

On appeal, this Court reviews questions of fact under a manifest error standard.5 In applying the manifest error rule to the trial court’s interpretation, a court of appeal may not simply substitute its own view of the evidence for the trial court’s view, nor may it disturb the trial court’s finding of fact so long as it is reasonable.6 The appellate court reviews questions of law de novo to determine whether the trial court was legally correct.7

The 8.3 acres of land that the CUP pertains to is located in the Flood Plain Zoning District. In the first and second assignments of error, the appellants contend that the zoning ordinance in Plaque-mines Parish mandates that “[t]he use of property ... in the FP-Flood Plain District shall be limited” to one of fourteen | ¿listed uses, and landfill is not one of the permitted uses. Thus, using the 8.3 acres as landfill is a non-conforming use that violates the Parish’s zoning ordinances.

The evidence presented at trial established that there was a 1982 resolution by the Parish approving the use of Industrial Pipe’s Flood Plain property for landfill operations.8 Although the resolution was originally issued for Industrial Pipe’s predecessor, Oakville Landfill, it encompassed a portion of the same geographical location currently at issue.9 Furthermore, in 1990, when Industrial Pipe was operating the landfill, the Parish council again recognized that the landfill was being operated in a Flood Plain and issued a permit for Industrial Pipe to conduct landfill activities within that area. The trial court found the evidence supported the Parish’s approval of the landfill operations in the Flood Plain.

In addition to the trial court’s finding that Industrial Pipe proved the Parish had previously authorized the landfill operations to be conducted in the Flood Plain, it found that a non-conforming use had been obtained through prescription. La. R.S. 9:5625(A)(3) provides that:

With reference to violations of use regulations all such actions, civil or criminal, except those actions created for the purpose of amortization of nonconforming signs and billboards in conformity with the provisions of R.S. 33:4722, must be brought within five years from the date the parish, municipality, and the properly authorized instrumentality or agency thereof if such agency has been designated, first had been actually notified in writing of such violation.

Considering the 1982 and 1990 resolutions together with the previously granted |5CUP application in 2003,10 the trial court determined that the necessary agencies for the Parish had been on notice of the land[1171]*1171fill activities in the Flood Plain for more than five years. Thus, the time period to raise any zoning violations had prescribed. We find the documentation in the record adequately supports that conclusion and therefore find no error with the trial court’s determination.

Appellants’ assignments of error three, four, and five challenge the sufficiency of evidence presented by Industrial Pipe to establish that it met the guidelines and requirements set forth by applicable coastal use programs, the Louisiana Administrative Code and the Parish’s Costal Zoning Management Program. The appellants argue that the trial court erred in its analysis of applicable statutes, mainly, Louisiana Administrative Code 43.1.701(F) and 715(C)-(D).

The guidelines and requirements that Industrial Pipe needed to meet in order to be granted a CUP are found in La. Admin. Code 43:1.701 et seq. The statutes are constructed to give the issuing authority direction and oversight in the permitting process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Parish of St. Bernard
206 So. 3d 259 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
139 So. 3d 1168, 2013 La.App. 4 Cir. 1345, 2014 WL 2134535, 2014 La. App. LEXIS 1345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-pipe-inc-v-plaquemines-parish-council-lactapp-2014.