Industrial Marine, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 5, 2026
Docket63975
StatusPublished

This text of Industrial Marine, Inc. (Industrial Marine, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Marine, Inc., (asbca 2026).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Industrial Marine, Inc. ) ASBCA No. 63975 ) Under Contract No. N00383-21-P-P034 )

APPEARANCE FOR THE APPELLANT: Mr. Justin Hawkins Vice President

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney Georgia E. Russell, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE GOVERNMENT’S MOTION TO DISMISS

The government moves to dismiss a portion of appellant’s complaint (Claim 2), asserting that the Board lacks jurisdiction over a portion of the appeal because the claim was not previously submitted to the contracting officer (CO) for final decision. We agree and grant the government’s motion. Claim 2 is dismissed from appellant’s complaint; the initial claim (Claim 1) remains.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. NAVSUP 1 Weapon Systems Support (NAVSUP WSS or the government) awarded Contract No. N00383-21-P-P034 to Industrial Marine, Inc. (IMI or appellant) on November 23, 2020, for the evaluation, repair and/or modification of shuttle assemblies (R4, tab 1 at 1-2). 2 A shuttle assembly is part of the “crucial shipboard system enabling the launch and/or recovery of aircraft” (R4, tab 1 at 4-5). The contract incorporated by reference Federal Acquisition Regulation (FAR) clause 52.233-1, DISPUTES (MAY 2014) (R4, tab 1 at 53).

1 Naval Supply Systems Command (R4, tab 6 at 90). 2 The Rule 4 file is Bates stamped with the prefix “IMI” followed by zeros. The prefix and leading zeros are omitted from citations to the Rule 4 file. 2. IMI is represented in this appeal, pro se, by its Vice President, Mr. Justin Hawkins. IMI submitted correspondence to the Board by email on September 20, 2024. Mr. Hawkins stated in his email:

We are a small business and have a dispute over a contract (N0038321PP034) regarding government delays. It should have only taken a couple of months to complete, but instead has been strung out for 3.5 years due to delayed government responses (or no response at all), agency restructuring, disputes between government agencies, etc. and the government will not agree to pay for the delay costs. There have been several contracting officer/specialists over this contract in the time since it was awarded, and finally after a year of complete silence from the government a Branch Chief/Supervisory Contracting Officer finally contacted us to cancel the contract.

However, she will not pay us for the delays nor discuss the extensive delay details we provided, she unilaterally signed a mod without any discussion that ignores the costs we seek, she ignores all questions regarding why the government disappeared on this contract, and will not issue a final decision notice.

How should we proceed from here?

(Bd. corr. email dtd. September 20, 2024) (emphasis added) The Board docketed this as IMI’s notice of appeal on September 24, 2024.

3. The government’s Rule 4 file did not include any tabs specifically identifying the claim at issue in this appeal (R4, index). By Order dated October 30, 2024, the Board requested that the government identify the claim in its Rule 4 file or supplement the Rule 4 with the claim. By correspondence dated November 12, 2024, the government responded stating that it did “not believe or concede that any of those documents constitute[d] a properly filed claim sufficient to establish Board jurisdiction” (Bd. corr. ltr. dtd. November 12, 2024).

4. During a conference call conducted by the Board with the parties, Mr. Hawkins, identified the delay costs described in the emails at Rule 4, tabs 13 and 16 as IMI’s claim. The Board noted that appellant had requested contracting officer final decisions (COFDs) on two occasions in the record (R4, tab 14 at 168, tab 22 at 208) and the government confirmed on the call that no COFDs had been issued. The government maintained its position that there was no proper Contract Disputes

2 Act (CDA) claim submitted. The parties were ordered to brief the issue. (Mem. of Conference Call and Order dtd. November 20, 2024)

5. Prior to the due date for the government’s opening brief, by correspondence dated December 17, 2024, the government stated it “d[id] not contest the submission of a claim” in the appeal and requested that the previously enacted stay be lifted (Bd. corr. ltr. dtd. December 17, 2024). This request was granted by Board Order dated December 19, 2024; appellant filed its complaint citing two claims on February 25, 2025. Claim 1 of appellant’s complaint is for delay costs and Claim 2 is for “work that was removed from the scope” of the contract. (Compl. ¶ 1)

6. Tab 13 of the Rule 4 file includes a string of email correspondence between appellant’s representative and the government from February 27, 2023, to July 14, 2023 (R4, tab 13 at 157-64). In the index submitted along with the Rule 4 file, the government described tab 13 as “7/14/23 - IMI explanation of ‘inflation’ calculation in proposal and email Correspondence (2/2023 - 7/14/23)” (R4, index). In the emails, the parties are discussing costs for specific shuttle repairs and a contract modification (R4, tab 13 at 157-64). In response to a May 1, 2023, email from the government’s contract specialist “follow[ing] up in regards to getting the mod signed,” Mr. Hawkins stated that “[t]he mod is missing the additional $10,228.20” (R4, tab 13 at 161). After some discussion about agenda setting and scheduling for a conference call, the government in an email dated June 29, 2023, requested an “event log” which Mr. Hawkins had “stated had specifics in regards to the Government delays ”that “had led to needing [an] additional $10,228.20” (R4, tab 13 at 159). In an email to the government dated July 14, 2023, Mr. Hawkins described the following:

Per your request, the inflation amount was calculated from the award date to now, and is detailed below. The percentage used was taken from the Bureau of Labor and Statistics (bls.gov).

Eval of Shuttle 1716: $24,656.71 + Eval of Shuttle 2104: $35,509.16 Total: $60,165.87 17% Inflation: $10,228.20

You are correct that a FFP contract does not allow us to recoup costs of our own doing (the work itself took longer than expected, scheduling conflicts, underestimated material/tooling/special processes, ran into trouble and/or made mistakes in manufacturing or repair, etc.); however, that is not the situation that we find ourselves in. The delays were caused by the Government, and are so 3 excessive that they are outside of any reasonable expectation that could have been factored into a bid. No margin of error could have accounted for what has transpired thus far, and the fault lies with the government alone, not the small business contractor.

Recap of the most notable delays: 456 days From solicitation to award (For background. This figure is not used in the inflation calculation, nor the total delay time). 197 days From award to completed post award conference. 366 days From our initial pass/fail report to concurring REI. 347 days Time it took to get a set screw needed for the evaluation. 120+ days Days since full evaluation report was submitted, as of 7/7/2023. 885+days Cumulative Government delays since award, as of 7/7/2023.

(R4, tab 13 at 157) (emphasis in original)

7. After some additional discussion and follow-up from Mr. Hawkins, the government responded on August 22, 2023: “The defin mod for SN 1716 was sent to you for signature on 12 July 2023” (R4, tab 14 at 168-69). Mr. Hawkins responded,

I know a mod was sent, but it does not address the other costs that we discussed . . . . [T]he only response to IMI’s and DCMA’s requests for status is to tell us about an unresolved mod predating the 7/14/23 email? The mod means nothing until we can come to terms, and we cannot do so without communication.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haines v. Kerner
404 U.S. 519 (Supreme Court, 1972)
Keene Corp. v. United States
508 U.S. 200 (Supreme Court, 1993)
The Tolliver Group, Inc. v. United States
20 F.4th 771 (Federal Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Industrial Marine, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-marine-inc-asbca-2026.