Industrial Customers of Northwest Utilities v. Public Utility Commission

100 P.3d 1072, 196 Or. App. 46, 2004 Ore. App. LEXIS 1397
Court of Appeals of Oregon·Decided October 27, 2004·No. 02C-18320; A121791·Published·Cited by 2 cases

Opinion

*49 BREWER, J.

Plaintiffs appeal a circuit court judgment affirming an order of the Public Utility Commission (PUC or the commission) that allowed intervenor PacifiCorp to include in its rates approximately $131 million in deferred excess power costs. Although this is an appeal from the circuit court judgment, we review PUC’s order and may reverse only if the order is unlawful, unreasonable, or not supported by substantial evidence. ORS 756.594; ORS 756.598; Pacific Northwest Bell Telephone Co. v. Eachus, 135 Or App 41, 44, 898 P2d 774, rev den, 322 Or 193 (1995). We afiirm.

To place the facts of this case in context, a brief discussion of the general legal principles in play is helpful. Utility rates are set prospectively based on a utility’s anticipated costs and revenues; ordinarily, utilities bear the risk of unforeseen costs but also receive the benefit when revenues are higher then predicted. However, ORS 757.259 provides that, in certain instances, utilities may defer accounting for costs or revenues, usually when one or the other is extraordinarily higher than anticipated. A utility may then apply to PUC for permission to recover (or refund) the deferred amounts through amortization in future rates. When a utility seeks to recover costs, ORS 757.259(5) 1 requires PUC to conduct an earnings review to determine whether the utility can afford to absorb the costs and a rate change proceeding under ORS 757.210(1) to determine whether the proposed rate increase is “just and reasonable.” “The commission’s final determination on the amount of deferrals allowable in the rates of the utility is subject to a finding by the commission that the amount was prudently incurred by the utility.” ORS 757.259(5).

We take the following facts from PUC’s order and the record. PacifiCorp operates a large network of power generation and transmission facilities and serves customers in six states. Demand on the company’s system is not constant. For example, average monthly systemwide demand is higher *50 during the summer and winter months than it is during spring and fall. Demand also varies as a daily matter; usage is higher during the day than it is at night. Demand also varies by region. In warmer states, demand is higher during the summer. In others, like Oregon, demand is higher during the winter. To manage this complex system, PacifiCorp uses a combination of company-owned generating resources and long-term wholesale purchases 2 to meet its average load, which includes both retail and wholesale customers. During peak periods, PacifiCorp augments its long-term resources with purchases made in the short-term wholesale market. Conversely, during off-peak periods, the company has surplus power that it sells in the short-term market. Because the cost of power from the short-term market is more volatile than from other sources, reliance on that market entails some risk. Thus, in planning its resource needs, PacifiCorp historically has attempted to balance its long-term resources and load as closely as possible, generally erring on the side of maintaining a net surplus.

From 1990 to 1995, 3 PacifiCorp’s average long-term resources exceeded its average load; in other words, the company sold more short-term power than it bought. During the early part of the 1990s, the company also was able to purchase several new generating plants at favorable terms, giving it an even greater power surplus. Rather than simply disposing of the excess power in the short-term market, PacifiCorp entered into new long-term wholesale sales contracts, which produce more revenue than short-term sales do. The company timed the contracts to expire as retail demand grew so that the power would be available when needed by retail customers. In 1996, based on its projections of its resource/load balance, the company determined that it could enter into 12 new long-term wholesale sales contracts between 1996 and 1998 and serve those contracts from surplus resources. Each new contract was timed to expire after three to five years.

*51 PacifiCorp’s resource/load projections proved to be inaccurate. Beginning in 1996, the company experienced a net resource deficit. By 1996, however, changes had begun to occur in the wholesale power market. The addition of new entrants into the market increased competition among suppliers, resulting in lower prices. Heavier than normal hydroelectric output added further downward pressure on prices. PacifiCorp concluded that it could rectify its resource deficit more cost effectively by increasing market purchases than by increasing its internally generated output.

In 2000 and 2001, extremely low rainfall, a catastrophic generator failure at its “Hunter 1” plant, and the sale of its Centraba, Washington, plant reduced PacifiCorp’s generating capacity significantly. During the same period, retail demand grew more quickly than PacifiCorp had anticipated. Had it not been for those events, by the end of2000, as a number of its long-term sales contracts expired, the company would have returned to a net surplus power position in the short-term market. Instead, PacifiCorp’s reliance on the short-term market grew substantially in 2000 and lessened only slightly in 2001. Because the “western power crisis” was under way, market prices were extremely high.

In 2000, PacifiCorp sought permission from PUC to defer the excess power costs incurred in the short-term market. PUC granted the request for a period of approximately 10 months beginning on November 1, 2000. 4 After the deferral period ended in 2001, PacifiCorp sought to amortize approximately $160 million through subsequent rate increases. Plaintiffs objected, contending that the costs were in part attributable to the long-term wholesale sales contracts. In plaintiffs’ view, the contracts reflected an aggressive and risky management strategy designed to increase Pacificorp’s market share in order to boost profits. They argued, among other things, that the wholesale contracts *52 were intended solely to benefit PacifiCorp’s shareholders. Industrial Customers of Northwest Utilities (ICNU) contended that, as part of a prudence review, PUC must examine “whether the costs that the utility seeks to include in rates provide a net benefit to the Company’s customers.” ICNU argued that costs associated with utility activities that do not benefit ratepayers are not recoverable in rates.

Free access — add to your briefcase to read the full text and ask questions with AI

Industrial Customers of Northwest Utilities v. Public Utility Commission, 100 P.3d 1072, 196 Or. App. 46, 2004 Ore. App. LEXIS 1397 (Or. Ct. App. 2004).

100 P.3d 1072 (Industrial Customers of Northwest Utilities v. Public Utility Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gearhart v. Public Utility Commission
299 P.3d 533 (Court of Appeals of Oregon, 2013)
Utility Reform Project v. Oregon Public Utility Commission
170 P.3d 1074 (Court of Appeals of Oregon, 2007)