Industrial Customers of Northwest Utilities v. Oregon Department of Energy

241 P.3d 352, 238 Or. App. 127, 2010 Ore. App. LEXIS 1231
CourtCourt of Appeals of Oregon
DecidedOctober 20, 2010
Docket330-150-0030, 330-160-0030 A138472 (Control), A140416
StatusPublished
Cited by3 cases

This text of 241 P.3d 352 (Industrial Customers of Northwest Utilities v. Oregon Department of Energy) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Customers of Northwest Utilities v. Oregon Department of Energy, 241 P.3d 352, 238 Or. App. 127, 2010 Ore. App. LEXIS 1231 (Or. Ct. App. 2010).

Opinion

*129 ORTEGA, J.

Pursuant to ORS 183.400(1), petitioner challenges the validity of OAR 330-160-0030, a rule adopted by the Oregon Department of Energy (ODOE) that establishes a system of renewable energy certificates for utilities. Petitioner filed two rule challenges, A138472 for OAR 330-150-0030 and A140416 for OAR 330-160-0030, that are consolidated here. ODOE repealed the first rule, OAR 330-150-0030, after failing to file it as a final rule in a timely manner. ODOE then adopted the virtually identical rule, OAR 330-160-0030. We now dismiss the first rule challenge, A138472, as moot, and proceed to address A140416.

OAR 330-160-0030 provides that “qualifying electricity” that may be used for renewable energy certificates must be generated on or after January 1, 2007; energy generated before January 1, 2007, may not be used. 1 Petitioner asserts that ODOE exceeded its statutory authority because, in petitioner’s view, ORS 469A.020(1) allows for “qualifying electricity” generated by facilities that were operational on or after January 1,1995. We conclude that the rule is valid.

We may invalidate a rule only if we find that, in adopting the rule, the agency violated the constitution, exceeded its statutory authority, or failed to comply with applicable rulemaking procedures. ORS 183.400(4). Here, petitioners argue only that ODOE exceeded its statutory authority. When we examine whether an agency exceeded its statutory authority, our record on review “consists of two things only: the wording of the rule itself (read in context) *130 and the statutory provisions authorizing the rule.” Wolf v. Oregon Lottery Commission, 344 Or 345, 355, 182 P3d 180 (2008) (citing ORS 183.400(3)). We consider whether the agency’s adoption of the rule exceeded the authority granted by statute and, further, whether the agency “departed from a legal standard expressed or implied in the particular law being administered, or contravened some other applicable statute.” Friends of Columbia Gorge v. Columbia River, 346 Or 366, 377, 213 P3d 1164 (2009) (quoting Planned Parenthood Assn. v. Dept. of Human Res., 297 Or 562, 565, 687 P2d 785 (1984) (internal quotation marks omitted)). “The question in determining if a rule exceeds statutory authority is whether the rule corresponds to the statutory policy as we understand it.” Managed Healthcare Northwest v. DCBS, 338 Or 92, 96, 106 P3d 624 (2005) (quoting Planned Parenthood Assn., 297 Or at 573 (internal quotation marks and brackets omitted)). In order to determine legislative intent, we examine the text and context of the statute along with legislative history offered by the parties that “may be used to confirm seemingly plain meaning and even to illuminate it * * * ” State v. Gaines, 346 Or 160, 172, 206 P3d 1042 (2009).

We begin with the pertinent statutes, which were enacted as part of the Oregon Renewable Energy Act, Senate Bill (SB) 838 (2007). The purpose identified in that act was

“to promote research and development of new renewable energy sources * * *[,] to decrease * * * reliance on fossil fuels * * *[,] and to increase * * * use of renewable energy sources [and] accelerate the transition to a more reliable and more affordable energy system!.]”

Or Laws 2007, ch 301, relating clause. ORS 469A.130(1) then provides that ODOE

“shall establish a system of renewable energy certificates that can be used by an electric utility or electricity service supplier to establish compliance with the applicable renewable portfolio standard. * * * The department may allow use of renewable energy certificates that are issued, monitored, accounted for or transferred by or through a regional system or trading program, including but not limited to the Western Renewable Energy Generation Information System [WREGIS].”

*131 The legislature identified “qualifying electricity” for a renewable energy certificate as, among other things, “electricity generated from a renewable energy source [that] may be used to comply with a renewable portfolio standard only if the facility that generates the electricity meets the requirements of ORS 469A.020.” ORS 469A.010; see also ORS 469A.005(9) (“ ‘Qualifying electricity’ means electricity described in ORS 469A.010.”). ORS 469A.020 (2007) 2 further explained that “electricity may be used * * * only if the electricity is generated by a facility that becomes operational on or after January 1,1995.” (Emphasis added.)

Petitioner argues that the statutes identify “qualifying electricity” as all electricity generated by a renewable energy facility that began operations on or after January 1, 1995, meaning that all electricity generated by such a facility since January 1, 1995, necessarily qualifies for renewable energy certificates. It contends that the legislative history of ORS 469A.010 and ORS 469A.020 demonstrates an intent that both qualifying electricity and renewable facilities use the January 1, 1995, date. 3 Additionally, petitioner argues *132 that the legislature merely granted ODOE authority to develop a system for tracking renewable energy certificates and that ODOE exceeded that authority when it “redefined” the term “qualifying electricity” as limited to energy generated after January 1, 2007. We disagree.

The statutes unambiguously provide that the 1995 date applies to the operational age of the facility, not, as petitioners contend, to the generation date of the electricity itself. The legislature provided a time requirement for only the facility operational date; the statutes are silent regarding when the electricity must be generated by a qualifying facility. ORS 469A.020

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Siletz Anglers Assn. v. ODFW
336 Or. App. 272 (Court of Appeals of Oregon, 2024)
Indus. Customers of Northwest v. Odoe.
241 P.3d 352 (Court of Appeals of Oregon, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
241 P.3d 352, 238 Or. App. 127, 2010 Ore. App. LEXIS 1231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-customers-of-northwest-utilities-v-oregon-department-of-energy-orctapp-2010.