Industrial Customers of Northwest Utilities v. Bonneville Power Administration

388 F. App'x 586
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 16, 2010
Docket09-70290, 09-70390, 09-70393
StatusUnpublished
Cited by1 cases

This text of 388 F. App'x 586 (Industrial Customers of Northwest Utilities v. Bonneville Power Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Customers of Northwest Utilities v. Bonneville Power Administration, 388 F. App'x 586 (9th Cir. 2010).

Opinion

MEMORANDUM *

Petitioners, the Industrial Customers of Northwest Utilities, Georgia-Pacific, LLC, and Clatskanie People’s Utility District, seek review of the Bonneville Power Administration’s (“BPA”) Tiered Rate Methodology, as approved via the Tiered Rate Methodology Record of Decision. Petitioners seek a ruling by this court that the Tiered Rate Methodology Record of Decision be vacated and this case remanded for further proceedings. They contend the decision violates the Pacific Northwest Electric Power Planning and Conservation Act of 1980 (the “Northwest Power Act”). The Tiered Rate Methodology sets a new method by which BPA will calculate future rates charged to its customers when their current contracts expire.

*588 It is undisputed that the Tiered Rate Methodology Record of Decision is a “final action” within the meaning of the Northwest Power Act, 16 U.S.C. §§ 839-839h, which vests this court with original jurisdiction to review challenges to final actions or the implementation of final actions by the BPA. 16 U.S.C. § 839f(e)(5).

First, the petitioners challenge the Tiered Rate Methodology under section 7(b)(4) of the Northwest Power Act. 16 U.S.C. § 839e(b)(4). The petitioners contend that the Tiered Rate Methodology will result in the BPA charging the same market-based rate for some “contracted-for or committed-to” load as it charges for new large single loads, thus violating a statutory mandate in the Northwest Power Act that such rates be different. See 16 U.S.C. § 839a(13). The petitioners also contend that the resulting rates will not be of “general application.” See 16 U.S.C. § 839e(b)(l).

In determining whether a challenge is ripe for review, we must distinguish “between challenges to contractual provisions on the grounds that those provisions will affect future rate-making and cost allocation decisions, and challenges premised on the contention that the agency lacks statutory authority to agree to specific contractual terms.” Pacific Northwest Generating Co-op. v. Dep’t of Energy, 680 F.3d 792, 806 n. 20 (9th Cir.2009). The former challenges constitute rate determinations that are not ripe until “confirmation and approval by the Federal Energy Regulatory Commission [“FERC”].” 16 U.S.C. § 839f(e)(4)(D); see 16 U.S.C. § 839e(m)(2). The BPA has not set rates pursuant to the new Tiered Rate Methodology, nor has FERC approved such rates or the method of calculating those rates.

Because the BPA has not yet completed a rate-making proceeding, and the petitioners’ challenge under section 7(b)(4) is based on future rate-making and cost allocation decisions, this challenge is not ripe for review. See California Energy Res. Conserv. & Dev. Comm’n v. Johnson, 807 F.2d 1456, 1463 (9th Cir.1986) (“A decision at this juncture would resolve a dispute about hypothetical rates.”). Similar challenges were brought to a new method of calculating rates by the BPA in 1983, again before the actual rates were set and approved by FERC. We dismissed those petitions for lack of jurisdiction:

The issue is whether we have jurisdiction to consider the petitions. 16 U.S.C. § 839f(e)(l) provides that only “final actions” are subject to judicial review, and lists “final rate determinations” as being among these reviewable actions. 16 U.S.C. § 839f(e)(4)(D) provides that rate determinations are final only upon confirmation by FERC. 16 U.S.C. § 839f(e)(5) gives jurisdiction to courts of appeals to hear suits challenging these final actions. Thus, unless there was a final action as of the date the petition was filed, we do not have jurisdiction.

City of Seattle v. Johnson, 813 F.2d 1364, 1367 (9th Cir.1987) (per curiam). After FERC approved the 1983 rates, we then had jurisdiction to hear the petitions for review challenging such rates and the method under which those rates were calculated. CP Nat’l Corp. v. Jura, 876 F.2d 745, 747 (9th Cir.1989). 1 Because the petitioners’ challenge is not ripe for review, there is no “case or controversy” and thus we have no jurisdiction to review the merits of the petitions. See U.S. Const, art III, § 2, cl. 1; see CP Nat’l Corp., 876 F.2d at 747.

*589 Because the BPA has not yet completed a rate-making proceeding, and the petitioners are not challenging an actual rate made in violation of a controlling statute, these particular challenges are not ripe for decision. See Cal. Energy Res. Conserv. & Dev. Comm’n v. Johnson, 807 F.2d at 1463 (“[a] decision at this juncture would resolve a dispute about hypothetical rates.”). Because the petitions are not ripe for review, there is no “case or controversy” and thus we have no jurisdiction to review the merits of the petitions. See id.

Second, Georgia Pacific contends that the Tiered Rate Methodology effects an unconstitutional taking. Assuming without deciding that we otherwise have jurisdiction over this claim under the Northwest Power Act and the Tucker Act, see 16 U.S.C. § 839f(e)(5); 28 U.S.C. § 1491(a)(1), we conclude that this claim also is unripe. It is clear that any alleged taking resulting from a change in rates will not occur until FERC approves such rates. See City of Seattle, 813 F.2d at 1367. Thus, Georgia Pacific’s challenge is not ripe, and we lack jurisdiction to consider it. See id.

Once the BPA sets the new rates and FERC approves such rates, the petitioners may be able to file new petitions for review with this court. See Pacific Northwest Generating Co-op., 580 F.3d at 805-06 (quoting Pub. Utils. Comm’r of Or. v. BPA, 767 F.2d 622

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
388 F. App'x 586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-customers-of-northwest-utilities-v-bonneville-power-ca9-2010.