Industrial Construction Management v. DeSoto Independent School District

785 S.W.2d 160, 1989 Tex. App. LEXIS 3250, 1989 WL 192966
CourtCourt of Appeals of Texas
DecidedDecember 28, 1989
Docket05-89-00449-CV
StatusPublished
Cited by24 cases

This text of 785 S.W.2d 160 (Industrial Construction Management v. DeSoto Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Construction Management v. DeSoto Independent School District, 785 S.W.2d 160, 1989 Tex. App. LEXIS 3250, 1989 WL 192966 (Tex. Ct. App. 1989).

Opinion

OPINION

CARVER, Justice.

Industrial Construction Management appeals from a summary judgment in which the trial court found that “the suit filed by the Plaintiff (Industrial) ... founded upon a breach of contract theory is barred in its entirety as a matter of law because the doctrine of sovereign immunity bars the filing of suit against independent school districts without legislative permission.” We disagree, reverse, and remand for trial.

The live pleadings of Industrial at the entry of the summary judgment alleged that Industrial and DeSoto Independent School District entered into a written contract on October 14, 1985, by which Industrial agreed to provide labor, materials, and equipment for the construction of the cafeteria addition project at Beltline Elementary School for the lump sum of $711,644, such contract being attached to and made a part of said pleading. Industrial pleaded that it had been paid save for:

(1) $15,469.80 deducted from its payment for relocation of power lines even though its contract did not require this work from Industrial;
(2) $2,722.97 deducted from its payment for relocating telephone service even though its contract did not require this work from Industrial;
(3) $3,193.11 expended by Industrial for labor and material to paint masonry walls, which was unspecified, additional work under the contract;
(4) $1,336.00 expended by Industrial for labor and material to furnish and install flashing, which was unspecified, additional work under the contract;
(5) $10,000.00 for expense, labor and material to construct an electrical transformer pad, which was unspecified, additional work under the contract;
(6) an amount unspecified for obstruction, hindrance and delay by DeSoto because (a) DeSoto furnished Industrial incomplete plans and specifications; (b) De-Soto failed to obtain necessary approvals and permits from the City of DeSoto for 86 days; and (c) DeSoto delayed the installation of the electrical transformer thus denying power to Industrial at project site;
(7) and reasonable attorney’s fees incurred by Industrial to protect itself against these violations of the contract by DeSoto.

In response to the foregoing active pleading of Industrial, DeSoto filed a motion for “Partial Summary Judgment” in the body of which it urged that Industrial sought damages for breach of contract; that De-Soto asserted its sovereign immunity as an affirmative defense; that DeSoto, as an independent school district, is an agency of the State and is not answerable for damages, whether in contract or tort; that such immunity had not been waived by DeSoto or the legislature; that Industrial could not amend so as to state a cognizable claim; and that, consequently, the Court should “deny all relief for damages to which Plaintiff has claimed in its petition.” The trial court, apparently deeming this prayer as controlling over the label, granted DeSoto final summary judgment that Industrial “take nothing.”

On appeal, Industrial urges that the trial court correctly held that its several claims “sounded in contract,” but incorrectly concluded that DeSoto was entitled to sovereign immunity so as to bar such claims. DeSoto responds that, while the trial court *162 correctly concluded that all claims of Industrial were barred, the trial court mistakenly labeled Industrial’s claims for delay damages and for attorney’s fees as “sounding in contract” when such claims “sounded in tort” and were barred in any event. The parties here do not dispute, and it so appears from precedent, that school districts are immune from suits sounding in tort unless that immunity is waived. See Barr v. Bernhard, 562 S.W.2d 844, 846 (Tex.1978); Tex.Civ.PRAc. & Rem.Code Ann. §§ 101.021 & 101.051 (Vernon 1986). Therefore, we must first resolve the nature of Industrial’s claims.

DeSoto concedes all of Industrial’s claims “sound in contract” save those for attorney’s fees and for delay. In general, the prevailing party may not recover attorney fees unless such a recovery is authorized by contract or statute. Prudential Insurance Co. of American v. Burke, 614 S.W.2d 847, 849-50 (Tex.Civ.App. — Texarkana), writ ref'd n.r.e. per curiam, 621 S.W.2d 596 (Tex.1981). Article 2226 of the Texas Revised Civil Statutes, now codified as Texas Civil Practice and Remedies Code sections 38.001 through 38.006, provides for attorney’s fees to, or against, persons and corporations. Tex.Civ.PRAC. & Rem. Code Ann. §§ 38.001-38.006 (Vernon 1986) (formerly Tex.Rev.Civ.Stat.Ann. art. 2226). Answering a contention that “municipal” corporations were not intended to be included in this statute by our legislature, our Supreme Court held, in Gates v. City of Dallas, 704 S.W.2d 737 (Tex.1986), that “the underlying purpose of the statute is to encourage contracting parties to pay their just debts and discourage the very type of vexatious, time-consuming and unnecessary litigation in which Gates was forced to engage.” Gates, 704 S.W.2d at 740. 3 We conclude that Industrial’s right, if any, to attorney’s fees under this statute arises out of the parties’ contract and the performance thereof; that is, this claim “sounds in contract” and the trial court correctly so held.

DeSoto also argues that the claim for delay damages is not contractual but “sounds in tort.” DeSoto cites no precedent aiding the determination of the nature of such claims. Industrial points out that Board of Regents of the University of Texas v. S & G Construction Co., 529 S.W.2d 90 (Tex.Civ.App. — Austin 1975, writ ref’d n.r.e.), held that, in every construction project, the law presumes that all of the parties to a contract will not hinder the performance of the others. See Board of Regents of the University of Texas, 529 S.W.2d at 95-96. Further, in City of Houston v. R.F. Ball Construction Co., Inc., 570 S.W.2d 75 (Tex.Civ.App. — Houston [14th Dist.] 1978, writ ref’d n.r.e.), in a dispute over delay in the construction of airport facilities, the court held that:

[A] contractor, such as Ball, is entitled to recover damages from a contractee, such as the City, for losses due to delay and hindrance of work if it proves (1) that its work was delayed or hindered, (2) that it suffered damages because of the delay or hindrance, and (3) that the con-tractee was responsible for the act or omission which caused the delay or hindrance.

City of Houston, 570 S.W.2d at 77. The contract of the parties here specifically provided that some types of delay would be remedied by extension of the completion time as limited in the contract, but also provided:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Texas Southern University
997 F. Supp. 2d 613 (S.D. Texas, 2014)
in Re Laura Dobbins
Court of Appeals of Texas, 2009
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 2005
Opinion No.
Texas Attorney General Reports, 2005
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
American Nat. Ins. v. Intern. Bus. MacH.
933 S.W.2d 685 (Court of Appeals of Texas, 1996)
American National Insurance Co. v. International Business Machines Corp.
933 S.W.2d 685 (Court of Appeals of Texas, 1996)
Ntreh v. University of Texas at Dallas
936 S.W.2d 649 (Court of Appeals of Texas, 1996)
Jensen Construction Co. v. Dallas County
920 S.W.2d 761 (Court of Appeals of Texas, 1996)
Texas Southern University v. Federal Sign
889 S.W.2d 509 (Court of Appeals of Texas, 1994)
Green International, Inc. v. State
877 S.W.2d 428 (Court of Appeals of Texas, 1994)
Alcorn v. Vaksman
877 S.W.2d 390 (Court of Appeals of Texas, 1994)
Texas Department of Health v. Texas Health Enterprises, Inc.
871 S.W.2d 498 (Court of Appeals of Texas, 1993)
Fadia v. Unauthorized Practice of Law Committee
830 S.W.2d 162 (Court of Appeals of Texas, 1992)
Courtney v. University of Texas System
806 S.W.2d 277 (Court of Appeals of Texas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
785 S.W.2d 160, 1989 Tex. App. LEXIS 3250, 1989 WL 192966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-construction-management-v-desoto-independent-school-district-texapp-1989.