Industrial Communications v. Town of Alton CV-07-82-JL 10/4/10
UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE
Industrial Communications and Electronics, Inc. et al.
v. Civil N o . 07-cv-082-JL Opinion N o . 2010 DNH 175 Town of Alton, David Slade, and Marilyn Slade
MEMORANDUM ORDER
David and Marilyn Slade, who intervened in this action by
wireless service providers challenging the Town of Alton’s
decision denying a variance to construct a cellphone tower as a
violation of the Telecommunications Act of 1996 (“TCA”), move to
stay the court’s order granting the variance with certain
modifications. The order entered on the joint request of the
providers and the town, who agreed to its terms as a settlement
of the providers’ claims. As a result of that settlement--which
did not include any claims by the Slades--this court directed the
entry of final judgment in this action. Indus. Commc’ns &
Elecs., Inc. v . Town of Alton, 2010 DNH 081 (“Order for
Judgment”). This was done over the Slades’ objections, including
that judgment could not enter before they were permitted to resolve their own purported claims, and that the settlement
violated the procedural requirements of local land use law.
As fully explained infra, the Slades’ motion to stay is
denied. In support of their motion, the Slades rely on their
pursuit of unspecified “remedies” against the construction of the
tower in state court, arguing that the providers have invoked the
Order for Judgment as “preempting” those proceedings. Whether
the providers are correct, however, is an issue to be decided by
the state court, not by this court, so that situation does not
support the requested stay.
The Slades also suggest that, should those proceedings
result in the relief they seek--which, presumably, includes an
order preventing the construction of the tower--allowing
construction to proceed in the interim threatens “unnecessary
waste and costly land reclamation processes.” But this concern
does not justify staying this court’s order because (1) the
burdens of that waste and cost will fall exclusively on the
providers, should they elect to proceed with the construction in
the face of a lawsuit that seeks to enjoin i t , and (2) this court
cannot meaningfully assess the Slades’ likelihood of prevailing
in such a lawsuit, because they have provided virtually no
information about i t . For largely the same reasons, the fact
2 that the Slades have appealed the Order for Judgment to the court
of appeals also does not justify staying i t .
I. Background
This case began when the providers challenged a decision by
the town denying them the variance necessary to construct a
cellphone tower as a violation of the TCA, specifically 47 U.S.C.
§§ 332(a)(7)(B)(i)(II) and 332(a)(7)(B)(iii). About three months
later, the Slades, who own property abutting the site of the
proposed tower, moved to intervene both as of right and
permissively. See Fed. R. Civ. P. 2 4 . The motion was granted
without any objection from the providers or explanation by the
court. See Order of Aug. 2 , 2007 (Barbadoro, J . ) .
The providers and the town proceeded to engage in extensive
motion practice over the next two and a half years. The Slades,
meanwhile, filed nothing of substance, including any pleading
setting forth whatever claims they wished to assert. Eventually,
the providers advised the court that they had settled their
claims against the town, and filed, together with the town, an
“Agreement for Entry of Consent Decree.” Among other things, the
proposed consent decree ordered the town’s decision denying the
variance for the tower to be “vacated . . . amended and modified
to grant” the variance subject to certain conditions, and
3 directed the providers to “submit revised site plans for site
plan review by the Alton Planning Board” in connection with the
proposed tower. The court then ordered the Slades—-who had
refused to join in the settlement—-“to file a memorandum
regarding their continued standing in this matter following [the]
settlement under applicable law.” Order of Mar. 9, 2010.
In response, the Slades argued that they “retain[ed] their
right to press their claims that the proposed communications
tower violates local zoning ordinances and that the . . .
decision [to deny the variance] does not contravene the [TCA].”
They further argued that entering the consent decree granting the
variance would “create an independent claim” by the Slades under
the TCA and would also violate New Hampshire law. Importantly,
the Slades did not ask the court to conduct a hearing on the
fairness or appropriateness of the proposed consent decree.
The court subsequently issued the Order for Judgment,
entering--with one alteration described infra--the consent decree
proposed by the providers and the town as the final judgment in
this matter. The court overruled the Slades’ purported
“objections” to the settlement, noting that an intervenor cannot
“‘preclude other parties from settling their own disputes and
thereby withdrawing from the litigation.’” Order for Judgment at
3 (quoting Local N o . 9 3 , Int’l Ass’n of Firefighters v . City of
4 Cleveland, 478 U.S. 5 0 1 , 528-29 (1986)). The court also noted
that “‘approval of a consent decree between some of the parties
. . . cannot dispose of the claims of nonconsenting intervenors;
if properly raised, these claims remain and may be litigated by
the intervenor.’” Id. at 4 (quoting Local N o . 9 3 , 478 U.S. at
529). The court ruled, however, that the Slades “have not
‘properly raised any claims of their own . . . . Like the
intervenors in Local [No.] 9 3 , [they] ‘did not allege any causes
of action or assert any claims against’ any of the original
parties to the lawsuit.” Id. (quoting 478 U.S. at 5 0 7 ) .
The court rejected the Slades’ attempt to raise, for the
first time in their “recently filed briefing on whether judgment
could enter without their consent,” a claim that the town’s
denial of the variance for the tower did not violate the TCA.
Id. at 4-5. The court reasoned that, because the Slades had
previously “submitted nothing whatsoever on the merits of the
provider’s TCA claims,” yet had intervened more than two years
ago, “[t]his unexplained delay is enough to conclude that the
Slades cannot now start pursuing a claim that [the town’s]
decision to disallow the proposed tower complied with the TCA.”
Id. at 5-6 (footnote omitted).
The court acknowledged that, while the Slades’ “purported
claim that the proposed tower violates local zoning law” did not
5 become “ripe until [the town] agreed to allow the provider to put
up a cell tower as a settlement of the case and therefore could
not have been asserted earlier, . . . it does not follow that the
Slades can now bring that claim in this court.” Id. at 7 . The
court observed that, “once the claim that originally gave rise to
federal subject-matter jurisdiction is dismissed, the court
cannot adjudicate the intervenor’s claim unless it provides ‘a
separate and independent basis for jurisdiction.’” Id. (quoting
Benavidez v . E u , 34 F.3d 825, 830 (9th Cir. 1994) (further
quotation marks omitted)). The court ruled that, while the
Slades expressly acknowledged this requirement, they failed to
comply with i t . See id. Although the Slades claimed that the
town’s decision to allow the tower violated both the TCA and
local zoning law, that first claim was forfeited because it did
not appear until their reply memorandum and, in any event, was
foreclosed by both the language of the TCA and unanimous caselaw,
see id. at 8-9, and the second claim “did not itself present any
federal question,” id. at 7-8 (citing Coyne v . City of
Somerville, 972 F.2d 4 4 0 , 444 (1st Cir. 1992)).
Relatedly, the court ruled that the Slades’ argument that
the town’s “agreement to issue the required permit[] for the
tower[] as a settlement . . . is in violation of state law
requiring land use permits to issue only as the result of public
6 meetings and the like” did not prevent the court from “entering
the judgment[] that the providers and the town[] have requested.”
Id. at 1 0 . The court reasoned that it “need no more inquire into
any aspect of the settlement[] here--including the [town’s] legal
authority to enter into [it]--than this court need inquire into
any party’s legal authority to enter into a settlement of any
case.” Id. at 1 1 . The court also relied on a decision by the
court of appeals that “expressly upheld--in circumstances
similar, if not identical, to those here--a district court’s
approval of a settlement agreement in a case under the TCA that
called for the issuance of ‘injunctive relief in the form of an
order requiring that the wrongfully withheld permit issue,’
despite objections that this course violated ‘the procedural
strictures of Massachusetts zoning law.’” Id. at 12 (quoting
Brehmer v . Planning Bd. of Town of Wellfleet, 238 F.3d 117 (1st
Cir. 2001)).
The court was careful to note, however, that it was
expressing no view on the merits of the Slades’ state-law
arguments--because, again, those arguments simply had no bearing
on the court’s ability to enter final judgment in the case. Id.
at 1 1 . Indeed, the court specifically cautioned that it was “not
saying that [the Slades] have no remedy for the injury they claim
the proposed tower will cause them, only that this court would
7 have no jurisdiction to provide it (assuming they are entitled to
one, an issue on which this court expresses no opinion
whatsoever).” Id. at 10 n.2. Furthermore, the court added a
proviso to the proposed judgment that “‘[n]othing in this order
shall prevent this court from staying or otherwise granting
relief from it according to applicable law.’”1 Id. at 1 3 .
The Slades then filed a timely appeal of the judgment.
Indus. Commc’ns & Elecs., Inc. v . Town of Alton, N o . 10-1738 (1st
Cir. June 2 1 , 2010). The providers filed a “Motion for Summary
Disposition for Lack of Standing,” see 1st Cir. R. 27.0(c),
arguing that the Slades had no standing to maintain the appeal
under Article III of the Constitution. The court of appeals
denied the motion, ruling that the Slades had “alleged sufficient
individualized concrete harm to satisfy the actual injury prong
of Article III standing.” Order of Aug. 1 9 , 2010. So the court
ordered full briefing, with the Slades filing their opening brief
on September 7 , 2010, and the providers’ brief due 10 days later.
1 The relevant paragraph of the proposed judgment stated that “[n]otwithstanding the provisions of [N.H. Rev. Stat. Ann. § ] 677:15 or any other law or regulation . . . the filing of any appeal or challenge to any decision or action of the [town] Planning Board shall [not] operate as a stay.” This refers to the fact that, before construction of the tower can commence, the providers need to obtain site plan approval from the Alton Planning Board. Their application for that relief is pending, but the Planning Board has yet to act or even hold a public hearing on i t .
8 II. Analysis
In support of their motion, the Slades rely solely on cases
considering whether a federal court should “for reasons of comity
and efficiency stay an action when a suit is pending in a state
court between the same parties which will conveniently and
authoritatively dispose of the issues in dispute between the
federal litigants.”2 Centronics Data Computer Corp. v . Merkle-
Korff Indus., 503 F. Supp. 1 6 8 , 169-70 (D.N.H. 1980); see also
Companion Life Ins. C o . v . Matthews, 547 F. Supp. 836, 837-38
(S.D.N.Y. 1982); Alameda Room, Inc. v . Pitta, 538 F. Supp. 1072,
1077 (S.D.N.Y. 1982); Universal Gypsum of Ga., Inc. v . Am.
Cyanamid Co., 390 F. Supp. 8 2 4 , 826 (S.D.N.Y. 1975). But that
does not aptly describe the relationship between this action and
the state-court litigation commenced by the Slades, which
presumably (again, they have provided virtually no information
about it) challenges the variance for the tower as at odds with
state land use law. This court has already entered judgment
2 The Slades also rely on a Supreme Court case discussing whether to stay a lower federal court judgment pending certiorari. Barnes v . E-Sys., Inc. Med. & Surgical Ins. Plan, 501 U.S. 1301 (1991). If that case provides any guidance here at all, it is by way of analogy to the issue of staying an order pending appeal, discussed infra.
9 here, and did so without considering the merits of any state-law
claim by the Slades. See Order for Judgment at 1 0 . This is not
a situation, then, where a state and federal court simultaneously
have similar issues under consideration, threatening “‘economy of
time and effort for [the courts], for counsel, and for
litigants’” if both actions proceed. Centronics, 503 F. Supp. at
170 (quoting Landis v . N . Am. Co., 299 U.S. 2 4 8 , 254-55 (1936)).
In fact, unlike in the cases they cite, the Slades do not
seek to stay this litigation--which has already ended--but to
stay the implementation of the court’s order which ended i t .
They need this relief, they suggest, “so as to allow the State
proceedings to proceed unimpeded,” because the providers and the
town have argued to the state court that the this court’s Order
for Judgment “preempts State action.” Though the Slades do not
explain further, the providers say that they have argued to the
state court that “the Slades cannot use state law or state or
local forums to mount a collateral attack on a federal court
judgment.” Thus, the Slades seem to want this court to stay its
Order for Judgment so that the providers can no longer make this
argument to the state court.
If granted, however, that relief would effectively usurp the
state court’s authority to decide the merits of the providers’
argument. And there is no question that the authority to make
10 that decision belongs to the state court, not this one. 3 The
court of appeals has held that raising a federal court’s consent
decree as a defense to state-law claims in state court does not
create federal subject-matter jurisdiction where it does not
otherwise exist—-and reached that conclusion specifically in the
case of a decree resolving TCA claims by directing the issuance
of a variance for a cell tower. See Metheny v . Becker, 352 F.3d
458, 460-61 (1st Cir. 2003). More generally, “[t]he first court
does not get to dictate to other courts the preclusion
consequences of its own judgment.” 18 Charles Alan Wright et
a l . , Federal Practice & Procedure § 4405, at 82 (2d ed. 2002)
(footnote omitted).
Accordingly, if the Slades want to argue that this court’s
order does not foreclose their state-law claims--whatever those
claims are; again, the Slades do not say--they must make that
argument to the state court, which is the forum with the
jurisdiction to consider i t . Indeed, the Slades essentially
concede as much, arguing that the state court “has appropriate
jurisdiction to hear” their claims. So this court will not,
under the guise of staying the Order for Judgment, decide its
3 According to the providers, the state court has scheduled hearing on the merits of their argument for October 6, 2010.
11 effect on the Slades’ yet-unidentified state-law claims. This
court expresses no view on that subject.4
In seeking the stay, the Slades also argue that “[i]t would
lead to unnecessary economic waste and costly land reclamation
processes if [the providers] were to build the intended phone
tower t o , only then, be ordered to remove it,” presumably as a
result of the state-court proceedings should the Slades prevail
in them. Because this court’s order, in relevant part,
effectuates the variance needed to build the tower, staying the
order pending the outcome of the state-court litigation would
certainly prevent any such waste or cost. To achieve a stay for
that purpose, however, the Slades would need to show that “the
harm caused [them] without the stay, in light of [their]
likelihood of eventual success on the merits [in the state-court
action], outweighs the harm the stay will cause the non-moving
party.” Acevedo-Garcia v . Vera-Monroig, 296 F.3d 1 3 , 17 (1st
4 This court is nevertheless constrained to point out that the Slades’ motion grossly mischaracterizes the order as “noting that the Slades had clearly articulated a state claim to [sic] which they were entitled to pursue at this point.” The order could not have been clearer that this court was expressing no view as to the Slades’ “entitlement” to any state-law relief. See Order for Judgment at 10 n.2 (“this court is not saying that they have no remedy for the injury they claim the proposed tower will cause them, only that this court would have no jurisdiction to provide it (assuming they are entitled to one, an issue on which this court expresses no opinion whatsoever)”) (emphasis added), 11 (“This court, however, expresses no views on the merits of [the Slades’ state-law] arguments”).
12 Cir. 2002) (quotation marks and bracketing omitted). They have
failed to make that showing.
First, the Slades have not explained how leaving the order
in place while they pursue the state-court action threatens any
harm to them (aside from their point that staying the order would
stop the providers from arguing that it precludes their state-law
claims which, again, needs to be considered by the state
tribunal, not this o n e ) . Indeed, the harm from any “waste” or
“costs” that would follow should the providers begin to build the
tower--only to be told to stop if the Slades ultimately prevail
before the state court--fall on the providers, not on the
Slades.5 Second, this court cannot meaningfully assess the
Slades’ likelihood of prevailing in the state-court litigation
because, again, they have provided virtually no information about
it. Third, the providers quite plausibly assert that they will
suffer harm from a stay, in the form of further delays to the
construction of the tower.
The Slades also point out that they have appealed the Order
for Judgment to the court of appeals, though they stop short of
specifically arguing that this court should stay the order
5 Furthermore, as discussed supra at note 1 , construction of the tower cannot commence until the providers obtain site plan approval from the town’s planning board—-which has yet even to hold a hearing on that application--so any harm to the Slades from the construction remains speculative at this point.
13 pending the outcome of that appeal. See Fed. R. Civ. P. 62(c). 6
In any event, they would not be entitled to that relief, which
depends, again, on “(1) whether the stay applicant has made a
strong showing that he is likely to succeed on the merits; (2)
whether the applicant will be irreparably injured absent a stay;
(3) whether issuance of the stay will substantially injure the
other parties interested in the proceeding; and (4) where the
public interest lies.” Hilton v . Braunskill, 481 U.S. 7 7 0 , 776
(1987). The Slades cannot satisfy these criteria, largely for
the reasons just discussed: any injury to them as a result of
variance effectuated through the Order for Judgment can be
remedied by taking the tower down, should the providers start
building only to lose the appeal, while further delays pending
the appeal would injure both the providers and the public
interest in improved wireless coverage in the area.
The Slades’ only argument for their likelihood of success on
appeal is based on the ruling by the court of appeals denying the
provider’s motion for summary disposition; that decision, they
say, “demonstrates a higher likelihood of success on appeal than
may have been assumed by either the [providers] or the District
6 In relevant part, this rule provides that “[w]hen an appeal is taken from . . . final judgment granting . . . an injunction, the district court in its discretion may suspend an injunction during the pendency of the appeal.” 14 Court.” Yet, as discussed supra, the providers’ motion for
summary disposition argued only that the Slades lacked Article
III standing to pursue the appeal, and the order by the court of
appeals denying the motion addressed only that argument. This
court’s order entering judgment over the Slades’ objections,
however, was not based on any lack of standing but, as discussed
at length above, their failure to raise a claim within this
court’s subject-matter jurisdiction in a timely manner o r ,
indeed, at any point up to and including their briefing on
whether the judgment could enter without their consent. So the
court of appeals’ ruling that the Slades “have alleged sufficient
individualized concrete harm to satisfy the actual injury prong
of Article III standing” says little if anything about their
chances of success on appeal. It says only that their appeal
will not be dismissed for lack of Article III standing.
Aside from their reliance on the order denying the motion
for summary disposition, the Slades do not attempt to demonstrate
that they are likely to succeed on appeal but, needless to say,
this court does not believe that they are. In their opening
brief, the Slades argue principally that (1) they have Article
III standing and (2) this court erred by failing to grant them an
evidentiary hearing to contest the “fairness” of the consent
15 judgment. In this court’s view, these arguments are unlikely to
succeed in overturning the judgment.
First, as just explained, this court never ruled that the
Slades lacked Article III standing. Instead, this court ruled
that the Slades lacked a properly presented claim falling within
the court’s subject-matter jurisdiction, which they explicitly
acknowledged was necessary in order to continue litigating as
intervenors after the providers and the town settled their
claims. Rather than addressing this ruling, the Slades’
appellate brief extensively discusses a number of state-law
claims, without explaining how this court would have subject-
matter jurisdiction over them.7 Second, the Slades never asked
this court to conduct an evidentiary hearing on the “fairness,”
or any other aspect, of the proposed consent judgment. “If any
principle is settled in [the] circuit, it is that, absent the
most extraordinary circumstances, legal theories not raised
squarely in the lower court cannot be raised for the first time
on appeal.” Boroian v . Mueller, ___ F.3d ___, 2010 WL 3168654,
at *8 (1st Cir. Aug. 1 2 , 2010) (quotation marks omitted).
7 The Slades also argue that they can bring a claim challenging the tower under the TCA. As this court ruled, however, that argument was not timely raised here, is inconsistent with the language of the TCA, and has been uniformly rejected by the caselaw. Order for Judgment at 7-9. The Slades’ appellate brief does not address these deficiencies.
16 Finally, in support of their motion for stay, the Slades
rely on the fact that the Order for Judgment modified the
proposed consent decree to add that “[n]othing in this order
relief from it according to applicable law.” The court inserted
that provision, however, in the paragraph of the proposed decree
stipulating that any appeal from the Alton Planning Board’s
decision on the providers’ application for site plan review, see
note 1 , supra, would not operate as a stay of the decree. Thus,
the provision does not contemplate that an appeal of the variance
(as opposed to any site plan approval or disapproval) would
potentially justify a stay. In any event, the provision simply
allows a stay “according to applicable law,” and, as just
discussed, the Slades have failed to demonstrate their
entitlement to stay under the applicable standards.
III. Conclusion
For the foregoing reasons, the Slades’ motion to stay8 is
DENIED.
Document n o . 7 8 .
17 SO ORDERED.
/se ___ h N. Laplante Jo nited States District Judge
Dated: October 4 , 2010
cc: Steven E . Grill, Esq. Anthony S . Augeri, Esq. Katherine Blackall Miller, Esq. Robert D. Ciandella, Esq. Robert M . Derosier, Esq. Paul T . Fitzgerald, Esq.