Industrial Communications v. Town of Alton

2010 DNH 175
District Court, D. New Hampshire·Decided October 4, 2010·No. CV-07-82-JL·Published·Cited by 1 cases

Opinion

Industrial Communications v. Town of Alton CV-07-82-JL 10/4/10

UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

Industrial Communications and Electronics, Inc. et al.

v. Civil N o . 07-cv-082-JL Opinion N o . 2010 DNH 175 Town of Alton, David Slade, and Marilyn Slade

MEMORANDUM ORDER

David and Marilyn Slade, who intervened in this action by wireless service providers challenging the Town of Alton’s decision denying a variance to construct a cellphone tower as a violation of the Telecommunications Act of 1996 (“TCA”), move to stay the court’s order granting the variance with certain modifications. The order entered on the joint request of the providers and the town, who agreed to its terms as a settlement of the providers’ claims. As a result of that settlement--which did not include any claims by the Slades--this court directed the entry of final judgment in this action. Indus. Commc’ns & Elecs., Inc. v . Town of Alton, 2010 DNH 081 (“Order for Judgment”). This was done over the Slades’ objections, including that judgment could not enter before they were permitted to

resolve their own purported claims, and that the settlement violated the procedural requirements of local land use law.

As fully explained infra, the Slades’ motion to stay is denied. In support of their motion, the Slades rely on their pursuit of unspecified “remedies” against the construction of the tower in state court, arguing that the providers have invoked the Order for Judgment as “preempting” those proceedings. Whether the providers are correct, however, is an issue to be decided by the state court, not by this court, so that situation does not support the requested stay.

The Slades also suggest that, should those proceedings result in the relief they seek--which, presumably, includes an order preventing the construction of the tower--allowing construction to proceed in the interim threatens “unnecessary waste and costly land reclamation processes.” But this concern does not justify staying this court’s order because (1) the burdens of that waste and cost will fall exclusively on the providers, should they elect to proceed with the construction in the face of a lawsuit that seeks to enjoin i t , and (2) this court cannot meaningfully assess the Slades’ likelihood of prevailing in such a lawsuit, because they have provided virtually no information about i t . For largely the same reasons, the fact

that the Slades have appealed the Order for Judgment to the court of appeals also does not justify staying i t .

I. Background This case began when the providers challenged a decision by the town denying them the variance necessary to construct a cellphone tower as a violation of the TCA, specifically 47 U.S.C. §§ 332(a)(7)(B)(i)(II) and 332(a)(7)(B)(iii). About three months later, the Slades, who own property abutting the site of the proposed tower, moved to intervene both as of right and permissively. See Fed. R. Civ. P. 2 4 . The motion was granted without any objection from the providers or explanation by the court. See Order of Aug. 2 , 2007 (Barbadoro, J . ) .

The providers and the town proceeded to engage in extensive motion practice over the next two and a half years. The Slades, meanwhile, filed nothing of substance, including any pleading setting forth whatever claims they wished to assert. Eventually, the providers advised the court that they had settled their claims against the town, and filed, together with the town, an “Agreement for Entry of Consent Decree.” Among other things, the proposed consent decree ordered the town’s decision denying the variance for the tower to be “vacated . . . amended and modified to grant” the variance subject to certain conditions, and

directed the providers to “submit revised site plans for site plan review by the Alton Planning Board” in connection with the proposed tower. The court then ordered the Slades—-who had refused to join in the settlement—-“to file a memorandum regarding their continued standing in this matter following [the] settlement under applicable law.” Order of Mar. 9, 2010.

In response, the Slades argued that they “retain[ed] their right to press their claims that the proposed communications tower violates local zoning ordinances and that the . . . decision [to deny the variance] does not contravene the [TCA].” They further argued that entering the consent decree granting the variance would “create an independent claim” by the Slades under the TCA and would also violate New Hampshire law. Importantly, the Slades did not ask the court to conduct a hearing on the fairness or appropriateness of the proposed consent decree.

The court subsequently issued the Order for Judgment, entering--with one alteration described infra--the consent decree proposed by the providers and the town as the final judgment in this matter. The court overruled the Slades’ purported “objections” to the settlement, noting that an intervenor cannot “‘preclude other parties from settling their own disputes and thereby withdrawing from the litigation.’” Order for Judgment at 3 (quoting Local N o . 9 3 , Int’l Ass’n of Firefighters v . City of

Cleveland, 478 U.S. 5 0 1 , 528-29 (1986)). The court also noted that “‘approval of a consent decree between some of the parties . . . cannot dispose of the claims of nonconsenting intervenors; if properly raised, these claims remain and may be litigated by the intervenor.’” Id. at 4 (quoting Local N o . 9 3 , 478 U.S. at 529). The court ruled, however, that the Slades “have not ‘properly raised any claims of their own . . . . Like the intervenors in Local [No.] 9 3 , [they] ‘did not allege any causes of action or assert any claims against’ any of the original parties to the lawsuit.” Id. (quoting 478 U.S. at 5 0 7 ) .

The court rejected the Slades’ attempt to raise, for the first time in their “recently filed briefing on whether judgment could enter without their consent,” a claim that the town’s denial of the variance for the tower did not violate the TCA. Id. at 4-5. The court reasoned that, because the Slades had previously “submitted nothing whatsoever on the merits of the provider’s TCA claims,” yet had intervened more than two years ago, “[t]his unexplained delay is enough to conclude that the Slades cannot now start pursuing a claim that [the town’s] decision to disallow the proposed tower complied with the TCA.” Id. at 5-6 (footnote omitted).

The court acknowledged that, while the Slades’ “purported claim that the proposed tower violates local zoning law” did not

become “ripe until [the town] agreed to allow the provider to put up a cell tower as a settlement of the case and therefore could not have been asserted earlier, . . . it does not follow that the Slades can now bring that claim in this court.” Id. at 7 . The court observed that, “once the claim that originally gave rise to federal subject-matter jurisdiction is dismissed, the court cannot adjudicate the intervenor’s claim unless it provides ‘a separate and independent basis for jurisdiction.’” Id. (quoting Benavidez v . E u , 34 F.3d 825, 830 (9th Cir. 1994) (further quotation marks omitted)). The court ruled that, while the Slades expressly acknowledged this requirement, they failed to comply with i t . See id. Although the Slades claimed that the town’s decision to allow the tower violated both the TCA and local zoning law, that first claim was forfeited because it did not appear until their reply memorandum and, in any event, was foreclosed by both the language of the TCA and unanimous caselaw, see id. at 8-9, and the second claim “did not itself present any federal question,” id. at 7-8 (citing Coyne v . City of Somerville, 972 F.2d 4 4 0 , 444 (1st Cir. 1992)).

Free access — add to your briefcase to read the full text and ask questions with AI

Industrial Communications v. Town of Alton, 2010 DNH 175 (D.N.H. 2010).

2010 DNH 175 (Industrial Communications v. Town of Alton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Industrial Tower and Wireless v. Town of Epping, et al.
2010 DNH 180 (D. New Hampshire, 2010)