Industrial Communications v. Town of Alton

2010 DNH 175
CourtDistrict Court, D. New Hampshire
DecidedOctober 4, 2010
DocketCV-07-82-JL
StatusPublished
Cited by1 cases

This text of 2010 DNH 175 (Industrial Communications v. Town of Alton) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Communications v. Town of Alton, 2010 DNH 175 (D.N.H. 2010).

Opinion

Industrial Communications v. Town of Alton CV-07-82-JL 10/4/10

UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

Industrial Communications and Electronics, Inc. et al.

v. Civil N o . 07-cv-082-JL Opinion N o . 2010 DNH 175 Town of Alton, David Slade, and Marilyn Slade

MEMORANDUM ORDER

David and Marilyn Slade, who intervened in this action by

wireless service providers challenging the Town of Alton’s

decision denying a variance to construct a cellphone tower as a

violation of the Telecommunications Act of 1996 (“TCA”), move to

stay the court’s order granting the variance with certain

modifications. The order entered on the joint request of the

providers and the town, who agreed to its terms as a settlement

of the providers’ claims. As a result of that settlement--which

did not include any claims by the Slades--this court directed the

entry of final judgment in this action. Indus. Commc’ns &

Elecs., Inc. v . Town of Alton, 2010 DNH 081 (“Order for

Judgment”). This was done over the Slades’ objections, including

that judgment could not enter before they were permitted to resolve their own purported claims, and that the settlement

violated the procedural requirements of local land use law.

As fully explained infra, the Slades’ motion to stay is

denied. In support of their motion, the Slades rely on their

pursuit of unspecified “remedies” against the construction of the

tower in state court, arguing that the providers have invoked the

Order for Judgment as “preempting” those proceedings. Whether

the providers are correct, however, is an issue to be decided by

the state court, not by this court, so that situation does not

support the requested stay.

The Slades also suggest that, should those proceedings

result in the relief they seek--which, presumably, includes an

order preventing the construction of the tower--allowing

construction to proceed in the interim threatens “unnecessary

waste and costly land reclamation processes.” But this concern

does not justify staying this court’s order because (1) the

burdens of that waste and cost will fall exclusively on the

providers, should they elect to proceed with the construction in

the face of a lawsuit that seeks to enjoin i t , and (2) this court

cannot meaningfully assess the Slades’ likelihood of prevailing

in such a lawsuit, because they have provided virtually no

information about i t . For largely the same reasons, the fact

2 that the Slades have appealed the Order for Judgment to the court

of appeals also does not justify staying i t .

I. Background

This case began when the providers challenged a decision by

the town denying them the variance necessary to construct a

cellphone tower as a violation of the TCA, specifically 47 U.S.C.

§§ 332(a)(7)(B)(i)(II) and 332(a)(7)(B)(iii). About three months

later, the Slades, who own property abutting the site of the

proposed tower, moved to intervene both as of right and

permissively. See Fed. R. Civ. P. 2 4 . The motion was granted

without any objection from the providers or explanation by the

court. See Order of Aug. 2 , 2007 (Barbadoro, J . ) .

The providers and the town proceeded to engage in extensive

motion practice over the next two and a half years. The Slades,

meanwhile, filed nothing of substance, including any pleading

setting forth whatever claims they wished to assert. Eventually,

the providers advised the court that they had settled their

claims against the town, and filed, together with the town, an

“Agreement for Entry of Consent Decree.” Among other things, the

proposed consent decree ordered the town’s decision denying the

variance for the tower to be “vacated . . . amended and modified

to grant” the variance subject to certain conditions, and

3 directed the providers to “submit revised site plans for site

plan review by the Alton Planning Board” in connection with the

proposed tower. The court then ordered the Slades—-who had

refused to join in the settlement—-“to file a memorandum

regarding their continued standing in this matter following [the]

settlement under applicable law.” Order of Mar. 9, 2010.

In response, the Slades argued that they “retain[ed] their

right to press their claims that the proposed communications

tower violates local zoning ordinances and that the . . .

decision [to deny the variance] does not contravene the [TCA].”

They further argued that entering the consent decree granting the

variance would “create an independent claim” by the Slades under

the TCA and would also violate New Hampshire law. Importantly,

the Slades did not ask the court to conduct a hearing on the

fairness or appropriateness of the proposed consent decree.

The court subsequently issued the Order for Judgment,

entering--with one alteration described infra--the consent decree

proposed by the providers and the town as the final judgment in

this matter. The court overruled the Slades’ purported

“objections” to the settlement, noting that an intervenor cannot

“‘preclude other parties from settling their own disputes and

thereby withdrawing from the litigation.’” Order for Judgment at

3 (quoting Local N o . 9 3 , Int’l Ass’n of Firefighters v . City of

4 Cleveland, 478 U.S. 5 0 1 , 528-29 (1986)). The court also noted

that “‘approval of a consent decree between some of the parties

. . . cannot dispose of the claims of nonconsenting intervenors;

if properly raised, these claims remain and may be litigated by

the intervenor.’” Id. at 4 (quoting Local N o . 9 3 , 478 U.S. at

529). The court ruled, however, that the Slades “have not

‘properly raised any claims of their own . . . . Like the

intervenors in Local [No.] 9 3 , [they] ‘did not allege any causes

of action or assert any claims against’ any of the original

parties to the lawsuit.” Id. (quoting 478 U.S. at 5 0 7 ) .

The court rejected the Slades’ attempt to raise, for the

first time in their “recently filed briefing on whether judgment

could enter without their consent,” a claim that the town’s

denial of the variance for the tower did not violate the TCA.

Id. at 4-5. The court reasoned that, because the Slades had

previously “submitted nothing whatsoever on the merits of the

provider’s TCA claims,” yet had intervened more than two years

ago, “[t]his unexplained delay is enough to conclude that the

Slades cannot now start pursuing a claim that [the town’s]

decision to disallow the proposed tower complied with the TCA.”

Id. at 5-6 (footnote omitted).

The court acknowledged that, while the Slades’ “purported

claim that the proposed tower violates local zoning law” did not

5 become “ripe until [the town] agreed to allow the provider to put

up a cell tower as a settlement of the case and therefore could

not have been asserted earlier, . . . it does not follow that the

Slades can now bring that claim in this court.” Id. at 7 . The

court observed that, “once the claim that originally gave rise to

federal subject-matter jurisdiction is dismissed, the court

cannot adjudicate the intervenor’s claim unless it provides ‘a

separate and independent basis for jurisdiction.’” Id. (quoting

Benavidez v .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Tower and Wireless v. Town of Epping, et al.
2010 DNH 180 (D. New Hampshire, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2010 DNH 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-communications-v-town-of-alton-nhd-2010.