Indiana Department of Natural Resources v. Solar Sources, Inc.

701 N.E.2d 1244, 1998 Ind. App. LEXIS 2045, 1998 WL 802668
CourtIndiana Court of Appeals
DecidedNovember 20, 1998
DocketNo. 63A05-9708-CV-346
StatusPublished
Cited by1 cases

This text of 701 N.E.2d 1244 (Indiana Department of Natural Resources v. Solar Sources, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indiana Department of Natural Resources v. Solar Sources, Inc., 701 N.E.2d 1244, 1998 Ind. App. LEXIS 2045, 1998 WL 802668 (Ind. Ct. App. 1998).

Opinion

OPINION

RUCKER, Judge.

On request by Solar Sources, Inc. the Indiana Department of Natural Resources issued a ruling interpreting certain provisions of the Indiana Surface Mining Control and Reclamation Act. An Administrative Law Judge affirmed. Finding the interpretation arbitrary, capricious, and contrary to law the trial court set aside the decision. The Indiana Department of Natural Re[1245]*1245sources now appeals raising several issues for our review which we consolidate and rephrase as whether the trial court erred in setting aside the Administrative Law Judge’s decision. We affirm.

Solar Sources, Inc. (Solar) operates a number of coal mines within the state of Indiana under several permits issued by the Department of Natural Resources (DNR). The permits were issued pursuant to Indiana’s Surface Mining Control and Reclamation Act (SMCRA) Ind.Code §§ 13-4.1-1-1 to 13-4.1-15-14.1 By terms of SMCRA and regulations promulgated thereunder, an application for a permit must contain a “blasting plan” for the proposed permitted area. The plan must include the following:

(1) the maximum ground vibration and air-blast limits the permittee will not exceed during blasting operations;
(2) the bases for the establishment of the proposed ground vibration and airblasts limits;
(3) the methods to be applied to control the adverse effects of blasting operations;
(4) description of the blasting warnings and site access control equipment and procedures to be used; and
(5) description of the procedures for recording and retention of [blasting operations].

310 IAC 12-3-43. The regulations promulgated under SMCRA also set forth three methods by which an operator may prove compliance with ground vibration limits: (1) the sealed distance equation, (2) the maximum peak particle-velocity limits, or (3) the blasting level chart. 310 IAC 12-5-36(h). A blast may or may not violate ground vibration limits depending on which method is utilized. For example a blast that would violate the blasting chart would not violate the peak particle-velocity limits and vice ver-sa.

For a number of years the permits under which Solar operated contained language that allowed Solar to decide which of the three blasting limits would apply after the blast and after the seismographic data from the blast has been received.2 On August 23, 1994, the Director of the Reclamation Division of DNR sent a letter to Solar directing the company to submit a nonspecific revision for each of its permits. More specifically Solar was directed to revise the permits to identify which of the three methods would be used to prove compliance with ground vibration limits when seismic monitoring occurs. According to the letter “the intent of 310 IAC 12-5-36(h) is to allow the permittee to choose which one of the three methods will be used to prove compliance with ground vibration limits. It is not intended for the permittee to use whichever method happens to meet the compliance needs at the time.” R. at 321(emphasis in the original). Thereafter Solar requested a Special Status Determination.3 DNR’s response was adverse to Solar’s position. In part DNR determined “[wjhile all options in the regulations are designed to prevent damage, the permittee must determine prior to blasting, how compliance with ground vibrations will be met and at which times the different options will be employed.... Solar’s choice of a method in demonstrating compliance after the blast has occurred is contrary to the intent of both Federal and Indiana SMCRA.” R. at 151 (emphasis in the original). Solar then sought administrative review. An Administrative Law Judge (ALJ) affirmed DNR’s Special Status Determination. Thereafter Solar sought judicial review. After conducting a hearing the trial court entered an order setting aside the ALJ’s decision on grounds that [1246]*1246the decision was arbitrary, capricious, and contrary to law. This appeal followed.

Upon judicial review of an administrative decision the trial court is limited to determining whether the agency action is:

(1) Arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law;
(2) Contrary to constitutional right, power, privilege, or immunity;
(3) In excess of statutory jurisdiction, authority, or limitations, or short of statutory right;
(4) Without observance of procedure required by law; or
(5) Unsupported by substantial evidence.

Ind.Code § 4-21.5-5-14(d); Natural Resources Comm’n of the State of Indiana v. AMAX Coal Co., 638 N.E.2d 418, 423 (Ind.1994). On appeal, we review the trial court’s decision to determine whether the trial court followed the law. Id. Whenever an agency interprets its own statute, the courts accord its interpretation great weight. However if an agency misconstrues a statute that it is charged with enforcing, then the trial court is required to reverse the agency’s action as being arbitrary and capricious. Peabody Coal Co. v. Indiana Dept. of Natural Resources, 606 N.E.2d 1306, 1308 (Ind.Ct.App.1992).

Pointing to the language of Indiana’s SMCRA and nearly identical language in its federal counterpart, DNR argues that the ALJ properly interpreted the agency’s rule. According to DNR the plain language of the statutes requires that blasting procedures and standards with which the operator must comply must be set forth in the permit before any explosions are detonated. Thus, according to DNR, the trial court erred in setting aside the ALJ’s determination. Citing the same state and federal statutes Solar counters that operators are allowed flexibility in conducting their blasting operations. According to Solar the trial court correctly determined that 310 IAC 12 — 5—36(H) allows operators to specify in their permits alternate methods of demonstrating compliance. At the heart of both parties’ argument lies the question: at what point does an operator have to specify the precise method by which the operator proves compliance with ground vibration limits. DNR contends it has the authority to require an operator to make the decision pre-blast. Solar argues an operator can make the decision post-blast. DNR is correct. However in this case it has chosen the incorrect method of insisting on the pre-blast determination.

In part, the purpose of Indiana’s SMCRA is to implement and enforce the federal Surface Mining Control and Reclamation Act of 1977. Ind.Code § 14-34-1-3. In so doing DNR may not adopt a rule that is more stringent than corresponding provisions under the federal Act. Ind.Code § 14-34-1-4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
701 N.E.2d 1244, 1998 Ind. App. LEXIS 2045, 1998 WL 802668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indiana-department-of-natural-resources-v-solar-sources-inc-indctapp-1998.