India & Owners v. Donald

49 F. 76, 1 C.C.A. 174, 1891 U.S. App. LEXIS 1108
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 7, 1891
StatusPublished
Cited by11 cases

This text of 49 F. 76 (India & Owners v. Donald) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
India & Owners v. Donald, 49 F. 76, 1 C.C.A. 174, 1891 U.S. App. LEXIS 1108 (5th Cir. 1891).

Opinion

Locke, District Judge.

This vessel, the owners of which are appel-

lants herein, being at Limerick, was chartered to appellees, Donald Bros. &Co., of Mobile, to proceed with dispatch to Pensacola or Ship island, at the option of charterers, there to load with sawn timber or boards, as the shipper might direct. The terms of the charter-party, as far as necessary to a determination of the questions in this case, are:

“The shippers shall supply, if legal, and if required by the master, a deck-load, to consist (at shippers’ option) of sawn timber and or deals and or boards at full freight. The cargo shall be delivered along-side vessel, at her ordered loading berth, at shippers’ risk and'expense; the master giving shippers a written notice of three clear working days before cargo is required, after vessel being at her ordered loading berth. * * * Eighteen weather working days shall be allowed the shippers in which to deliver the cargo along-side of vessel at port of loading, which is understood to mean actual ‘ delivery of cargo along-side,’ and not ‘completion of loading,’ and the cargo to be unloaded with all customary dispatch at port of discharge. Ten like days shall be allowed on demurrage at the rate of 4d. per ton register per day. Eor all such like days as the vessel may be wrongfully detained after such demur-rage days, damages for detention shall be paid at the rate of 4d. per ton register per day. Any demurrage or damages for detention shall bé settled at the place where incurred. In the computation of lay-days at port of loading shall be excluded any time lost by reason of quarantine, drought, flood, storms, strikes, fire, or any extraordinary occurrence beyond the control of the shippers. The master shall sign shippers’ bills of lading as presented, without prejudice to this charter-party, but any difference in freight shall be settled on signing bills of lading. ”

The ship, having arrived at Ship island under the charter-party, December 25, 1890, discharged ballast, and the master reported as ready to receive cargo, mailing the letter giving notice the 14th January, 1891. This letter it appears from the evidence was received at 9 o’clock the morning of the 16th January. The vessel remained taking in cargo as delivered along-side until March 6th, when she completed her loading. The charterers and shippers presented a clear bill of lading for the master to sign, but he, considering and claiming that his ship had been detained beyond the legal lay-days, and that he was justly entitled to demurrage, refused to sign such clear bill of lading; whereupon a libel was filed, alleging that owing to storms and high winds and stormy bad weather the number of weather working days of the shipper were never exhausted; that storms and high winds and bad weather affected the points where the libelants had under the custom of the port collected and'prepared the cargo; and that they were by these causes prevented from delivering the cargo within 18 consecutive days subsequent to the notice; but that these causes were wTholly beyond their control, and they had delivered the cargo within the first 18 weather working days, and that the master had refused to sign a clear hill of lading, but had protested against said clear bill of lading, which had destroyed its negotia[78]*78bility, and tbe salability of the cargo, greatly to their damage. To this the owners of the vessel, appellants, filed a cross-libel, alleging that the lay-days, the 18 weather working days allowed by the charter, expired on the 12th of February, and that their vessel had been wrongfully detained, and that there was due them for 10 days’ demurrage and 8 days’ detention the amount of $1,162. In answer to this cross-libel, appellees alleged that “in the computation of lay-days there shall be excluded any time lost by reason of quarantine, drought, floods, storms, strikes, fire, or any extraordinary occurrences beyond the control of shippers; and that, owing to droughts, storms, and floods, they were unable to have their timber delivered at Moss Point, the port where or from which the cargo is ordinarily delivered to Ship island, and that owing to said circumstances, which were wholly beyond their control, they were excused from sooner delivering said cargo.” They also denied that, owing to the condition of the weather from the 16th January to the 6th March, the 18 weather working days had expired at the time the delivery of the cargo was completed. Upon these pleadings, the case being heard, judgment was found for libelants for one cent and costs, and the claimants’ cross-libel was dismissed, with costs, from which the claimants have appealed.

Besides the question of demurrage, other questions arose in the court below, as to certain minor claims of the master of the vessel, for an amount paid as quarantine fees; for damage for breaking a knee of the vessel; and for a difference in exchange; but none of these have been assigned in error, and they will receive no consideration. There appears to be much uncertainty in the allegations of the libelants both in the libel and the answer to the cross-libel as to what condition of facts was to be relied upon; whether droughts, storms, or floods; and whether, according to the allegations of the libel, it was to be understood that the cargo was collected at Moss'Point, and they were prevented from delivering it, or, according to the answer to the cross-libel, they were unable to collect it there; but, taken in connection with the evidence, there are plainly presented two questions for examination: Whether there were more than 18 weather working days between the time when the lay-days commenced to run (three clear working da}'s after notice by the master) and the final delivery of the cargo; and, if so, whether such time should be excluded from the time subject to demurrage under the eighth article of the charter-party.

The term “working day” has so entered into commercial language and received judicial construction that its force and meaning is beyond a question or doubt. It has ceased to be an ambiguous phrase; but when the expression is further modified or limited by the word “weather” we find the new combination not so general in its use or so well established in its force; but its construction, and the manner and connection of its use, can permit but one meaning, namely, a day, otherwise a working day, when the weather would reasonably permit the carrying on of the work contemplated. In this case the kind of work contemplated was towing timber in rafts or lumber on lighters and delivering it along-side [79]*79of vessel. This is an exceptive term, withdrawing from ordinary working days certain days in which it is claimed that one is unable to work, and the burden of proof is upon him who alleges the exception. The presumption is that every working day is a day in which work may be done, and he who alleges to the contrary takes the affirmative.

Upon the question of the number of weather working days which elapsed between the master’s notice and the completion of loading, several witnesses have testified generally to the bad character of the weather during the months of January, February, and March, hut their testimony is so uncertain and conflicting that it cannot be relied upon in determining any question of any particular day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haigh Hall Steamship Co. v. Andersen
246 Mass. 34 (Massachusetts Supreme Judicial Court, 1923)
W. R. Grace & Co. v. Hansen
273 F. 486 (Ninth Circuit, 1920)
Hind, Rolph & Co. v. Ostrander
271 F. 406 (Ninth Circuit, 1920)
Pyman S. S. Co. v. One Hundred Tons of Kainit
164 F. 364 (S.D. Georgia, 1908)
Jonasen v. Keyser
112 F. 443 (Fifth Circuit, 1901)
Sorensen v. Keyser
52 F. 163 (Fifth Circuit, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
49 F. 76, 1 C.C.A. 174, 1891 U.S. App. LEXIS 1108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/india-owners-v-donald-ca5-1891.