Independent Mechanical Contractors, Inc. v. Gordon T. Burke & Sons, Inc.

635 A.2d 487, 138 N.H. 110, 1993 N.H. LEXIS 174
CourtSupreme Court of New Hampshire
DecidedDecember 23, 1993
DocketNo. 92-306
StatusPublished
Cited by65 cases

This text of 635 A.2d 487 (Independent Mechanical Contractors, Inc. v. Gordon T. Burke & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent Mechanical Contractors, Inc. v. Gordon T. Burke & Sons, Inc., 635 A.2d 487, 138 N.H. 110, 1993 N.H. LEXIS 174 (N.H. 1993).

Opinion

JOHNSON, J.

The defendant, Gordon T. Burke & Sons, Inc. (Burke), a general contractor, appeals from a jury’s award of damages in Superior Court (Mohl, J.) to the plaintiff, Independent Mechanical Contractors, Inc. (IMC), for breach of contract and defamation. We affirm the award for breach of contract because IMC’s injuries were a reasonably foreseeable consequence of Burke’s breach and because lost profits were proved with reasonable certainty. We reverse the verdict against Burke for defamation.

On April 11,1980, the Bartlett School District engaged Burke as a general contractor at a cost of almost $900,000 to make additions and alterations to the Josiah Bartlett Elementary School. Burke subcontracted the project’s plumbing, heating, and ventilation requirements to IMC. The contract between IMC and Burke targeted December 1, 1980, for completion and required Burke to supervise the project to prevent conflicts and delays. Burke, however, never devised a schedule allotting time for the work of the different trades on the job. Delays caused by other trades stalled IMC’s progress for approximately one month during the summer of 1980 and compressed the already short period for its work. Despite this delay, IMC substantially completed its work and received “punch list” assignments from Burke in the early spring of 1981. IMC notified Burke that certain items on the punch list were not within the scope of its contract. Burke nonetheless ordered IMC to work on the items. IMC refused, and school district officials ordered IMC off the site in February 1982. The record supports an inference that the officials acted according to Burke’s direction.

Litigation between the parties began in June 1981, when Burke filed a petition for declaratory judgment. IMC filed counterclaims [113]*113seeking damages for loss of reputation, lost profits, and other economic hardships allegedly caused by Burke’s breach of the contractual duty of supervision and by Burke’s defamation of IMC. The trial court denied Burke’s motion to dismiss, and a jury awarded IMC $100,000 for breach of contract and $150,000 for defamation. The trial court denied Burke’s motions to set aside the verdict, for judgment notwithstanding the verdict, and for remittitur. Burke appealed.

I. Breach of Contract

Burke does not deny that a breach occurred but contends there was insufficient proof that the breach was a proximate cause of IMC’s injuries, or that these injuries were reasonably foreseeable. Because the test of proximate cause is foreseeability, 5 A. CORBIN, CONTRACTS § 1006, at 70 (1964), we address these two contentions together. Burke also argues that IMC’s proof of lost profits was speculative. We view the evidence in a light most favorable to IMC and affirm the jury’s verdict if there is sufficient evidence in the record to support it. See Petrie-Clemons v. Butterfield, 122 N.H. 120, 124, 441 A.2d 1167, 1170 (1982).

The breach for which the jury awarded damages was Burke’s failure to supervise the project. The construction project manual, which was incorporated into the parties’ contract, provided that Burke “shall coordinate and supervise the work performed by Subcontractors to the end that the work is carried out without conflict between trades and so that no trade, at any time, causes delay to the general progress of the work.” A reasonable jury could find a breach of this provision in Burke’s failure to schedule the job and to coordinate the work of different trades, resulting in a month-long delay during the summer of 1980. A reasonable jury could also determine that Burke misassigned punch list items to IMC and that this misassignment was a breach of Burke’s duty of supervision.

At trial, IMC alleged that this breach caused it injuries, including loss of reputation, lost profits, and other economic harms. According to IMC, the delay during the summer of 1980 forced it to lay off employees. Moreover, IMC argued, it suffered a loss of reputation and a sudden drop in income coinciding with its involvement in the Bartlett school project. Finally, IMC stated that it subsequently lost its ability to obtain a line of credit and bonding, and failed to garner certain jobs, although its bids were competitive.

[114]*114 We first address whether there is a sufficient causal connection between Burke’s breach and IMC’s injuries to warrant holding Burke responsible for them; that is, whether IMC’s losses were a reasonably foreseeable consequence of the breach. See 5 Corbin, supra §§ 997-98, 1006-07. Damages are available only if the harm was a reasonably foreseeable result at the time the parties entered into the contract. See Salem Engineering & Const. Corp. v. Londonderry School Dist., 122 N.H. 379, 383, 445 A.2d 1091, 1094 (1982). One way a plaintiff may satisfy this requirement is by specifically proving that the defendant “had reason to know the facts” at the time the parties contracted and to foresee that the injury would be a probable consequence of a breach. Petrie-Clemons v. Butterfield, 122 N.H. at 124, 441 A.2d at 1170 (quotation omitted). IMC satisfied this test.

We observe that when Burke engaged IMC in April 1980, construction work was scarce. The Bartlett school project promised to be high-profile work, especially because its progress would be discussed at local school board meetings. IMC, a family-run business, had been in business for less than a year. A jury could infer Burke was familiar with IMC’s size and brief history at the time of contracting because Burke had previously worked with the father of IMC’s principals and because a bidder’s references, history, and qualifications are generally reviewed before a bid is accepted. Moreover, Burke should have known that an outsider might assume the punch list items were correctly assigned to IMC, thus making IMC’s refusal to complete those items look like an unwillingness to perform its duties. Considering all these factors, we conclude that the record supports a finding that Burke had reason to foresee that misassigning punch list items would probably harm IMC’s reputation and economic prospects.

Similarly, the record reveals a significant causal connection between Burke’s failure to coordinate the work of trades on the project and IMC’s diminished profits. Given the paucity of construction work at the time of contracting and the relatively tight time schedule Burke demanded of IMC, it was likely that such a failure to supervise the project adequately would delay IMC’s work, thus damaging its reputation, thereby lowering its profits. The evidence sustains a finding that Burke had reason to foresee that IMC’s injuries would be a probable consequence of its breach.

These facts differ materially from those influencing our decision in Salem Engineering, on which Burke heavily relies. We reversed an [115]*115award of consequential damages in that case in part because the defendant could not have reasonably foreseen at the time of contracting that the plaintiff general contractor would suffer a loss of reputation and a deterioration in its ability to remain a going concern if a fraction of the contract price were wrongfully withheld. Salem Engineering, 122 N.H. at 384, 445 A.2d at 1094.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Doe v. P Trustees of Dartmouth College
2022 DNH 085 (D. New Hampshire, 2022)
Martin v. Mooney
D. New Hampshire, 2020
Lath v. City of Manchester, et al.
2018 DNH 075 (D. New Hampshire, 2018)
Gregory Gould & a. v. Northern Human Services & a.
Supreme Court of New Hampshire, 2016
Audette v. Cummings
82 A.3d 1269 (Supreme Court of New Hampshire, 2013)
Rand v. Town of Exeter
976 F. Supp. 2d 65 (D. New Hampshire, 2013)
Collins v. University of New Hampshire
664 F.3d 8 (First Circuit, 2011)
Glynn v. Impact Science & Technology, Inc.
807 F. Supp. 2d 391 (D. Maryland, 2011)
Collins v. UNH
D. New Hampshire, 2010
State v. Gibson
999 A.2d 240 (Supreme Court of New Hampshire, 2010)
Caouette v. OfficeMax
2005 DNH 008 (D. New Hampshire, 2005)
T&M Associates, Inc. v. Goodrich
834 A.2d 369 (Supreme Court of New Hampshire, 2003)
Moss v. Camp Pemigewassett, Inc.
312 F.3d 503 (First Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
635 A.2d 487, 138 N.H. 110, 1993 N.H. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-mechanical-contractors-inc-v-gordon-t-burke-sons-inc-nh-1993.