Independent Iron Works, Inc. v. E. E. Black, Ltd.

92 F. Supp. 6, 1950 U.S. Dist. LEXIS 2461
CourtDistrict Court, D. Hawaii
DecidedSeptember 14, 1950
DocketCiv. No. 909
StatusPublished

This text of 92 F. Supp. 6 (Independent Iron Works, Inc. v. E. E. Black, Ltd.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent Iron Works, Inc. v. E. E. Black, Ltd., 92 F. Supp. 6, 1950 U.S. Dist. LEXIS 2461 (D. Haw. 1950).

Opinion

METZGER, Chief Judge.

The plaintiff, a California corporation, brought its action on April 11, 1949, against defendant, an Hawaiian corporation, and alleged, inter alia, that on July 9, 1948, defendant was indebted to it, by reason of an agreement of March 25, 1948, in the sum of $104,475.62, against which defendant thereafter, on October 8, 1948, paid $19,253.45, and on March 18, 1949 paid $52,799.95, leaving an unpaid balance at the time action was brought of $32,502.-24, and an additional charge of $80 for blueprints, with interest of 7% per annum on $85,222.19 from July 9, 1948, until March 18, 1949, and on $32,422.24 from March 18, 1949, until paid, together with costs and reasonable attorneys’ fees. A copy of the contract between the parties, as of March 25, 1948, is attached to the Complaint as Exhibit “A”.

The defendant answered on April 29, 1949, with denial and counterclaims: Denied that plaintiff performed its agreement with defendant, but that defendant was forced to rectify deficiencies, counterclaiming as ■ follows: (a) $1,310.50 for steel which it alleges was short in delivery; (b) $447.80, the cost of corrections for installing galbestos, caused by alleged faulty [8]*8fabrication; (c) $7,645.25 which defendant paid the Territory as 2%% gross income tax on imported and used fabricated steel supplied by plaintiff, and (d) $9,795.-95 which it alleges is a balance due it under its contract with Industrial Development Company for erecting the steel for fulfillment of which plaintiff is bond security for faithful and complete erection by Industrial Development Company of wharf sheds and for any labor and material furnished for that purpose by third parties.

Defendant denies liability for all the $32,422.24 claimed by plaintiff and the additional sum of $80 later added, and asserts as follows: That plaintiff claims a delivery and billed it for 28.2395 tons more steel at $200 per ton than the weights calculated by Harbor Board engineers; that a further 22.748 tons were expressly excluded from payment by the contract between defendant and Harbor Board; that plaintiff claims 1.5675 more steel at $197 per ton than the Harbor Board computed and'allowed, besides 1.0515 tons of this steel was expressly excluded by the Territory contract; that these discrepancies and exclusions amount to $10,712.24. Further, defendant denies liability for a charge of $1,444.55 for revisiqns of and additional shop drawings and additional items of $383.90 and $37.58 for the same, also $744.-48 for additional shop welding, and $80 for 160 additional blueprints demanded of plaintiff by the Harbor .Board.

The action was at issue May 17, 1949 and came on for two days hearing in February 1950, dealing at that time with the practice of ascertaining weights in the purchase of steel; practice on the Pacific Coast and in the United States with reference to charging for wastage in shop fabrication, mill over-runs, under-runs and theoretical weights, etc., and the weight and durability of “shop paint”, and the use of American Institute of Steel Construction Code (AISC) as a guide and authority in'those matters, and finally, the fact that the Territory paid the contractor (defendant) on the basis of its Harbor Board engineers’ computation of weights as provided in its contract specifications, which differed materially from the plaintiff’s weights as billed by it to the defendant. Further trial was thereafter continued from time to time until August 14, 1950, continuing for seven days through August 22, 1950.

The. only exhibits put in evidence in the February hearing were (1) the defendant’s contract with the Territorial Harbor Board for Job H.C. 750 for wharf shed construction at Hilo, (2) four sheets showing weights of structural steel, bolts, nuts, welds, washers, etc., and field welds, as the basis of plaintiff’s billing to defendant, and (3) plaintiff’s business card upon which E. E. Black had written “230.00 ton erected”, as being an oral offer given him by W. G. Meagher for Independent Iron Works, Inc., before defendant submitted its bid for the wharf shed job. A copy of the written agreement between the parties was attached as an exhibit to plaintiff’s Complaint.

At the time of the February hearing neither the written proposals submitted to the defendant by the plaintiff nor the written contract finally entered into between the parties were discussed or specifically by their terms brought to the court’s attention by argument or otherwise, and the court drew the inference that the defendant’s contract with the Harbor Board covered the entire matter of the compensation, so far as weights were concerned, that plaintiff was entitled to, and the court stated that the contractor should pay the subcontractor for same weights that the Harbor Board had contracted to pay the defendant.

During the later and main hearing of facts in August such revealing evidence was submitted as to present a new and different picture as to the contractural relations between the plaintiff and defendant.

It appears quite certain that in the first negotiations there was an agreement as to a per ton price as to steel, fabrication and erection at $230 per ton; that this was later changed to $200 and $197 per ton for the fabricated steel delivered and $30 per ton for erection, the erection to be done under a separate contract between defendant and a concern associated with plain[9]*9tiff, named Industrial Development Company, which had been created in 1944 for similar erection work by members of the families of the owners of Independent Iron Works, Inc. The defendant expressed willingness in late July or August, 1947 to make separate subcontracts between itself and the parties named at the prices named, “so long as the work did not cost it more than $230 per ton of steel in place”.

Contracts between the parties were drawn and redrawn and finally agreed to and executed March 25, 1948, relating back to September 1, 1947, the defendant, under advice of its attorney, requiring the plaintiff to indemnify it by bond in the sum of $50,000 for the faithful performance of erection work by the Industrial Development Company and inure to the benefit of materialmen and labor performed on the job.

From all the legal and relevant evidence, nearly all of which I found to be highly credible, it is impossible for me to arrive at any conclusion with respect to a complete agreement or anything which could be enforced as a valid and subsisting contract covering the entire transaction other than the written agreement between the parties which was finally signed on March 25, 1948, relating back to September 1, 1947. True, from the beginning there was an oral proposal, followed by a written proposal (Exhibit Z-2), as to the prices per ton and the ton prices were agreeable to the defendant who promised a subcontract to the plaintiff in the event defendant obtained the contract with the Harbor Board. Both parties seemed to think that was the essential thing to get settled and neither have ever disputed those ton prices. The difference arises principally as to the number of tons furnished and the manner of computing weights.

The plaintiff’s bargainer, W. G. Meagher, testified that he told the defendant’s bargainer, George M. Collins, at the beginning that he computed weights in accordance with AISC code and that the defendant in making its bid to the Territory should add about 5% to Harbor . Board’s estimated weights. Mr. Collins denied all memory of such a conversation and says it did not take place within his hearing. Mr. E. E. Black says he knew nothing of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
92 F. Supp. 6, 1950 U.S. Dist. LEXIS 2461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-iron-works-inc-v-e-e-black-ltd-hid-1950.