In the Matter of the Verified Application and Petition of Liberty Energy (Midstates) Corp d/b/a Liberty Utilities to Change its Infrastructure System Replacement Surcharge Missouri public Service Commission v. The Office of Public Counsel
Opinion
In the Missouri Court of Appeals Western District
IN THE MATTER OF THE VERIFIED ) APPLICATION and PETITION OF ) LIBERTY ENERGY (MIDSTATES) CORP ) d/b/a LIBERTY UTILITIES TO CHANGE ) ITS INFRASTRUCTURE SYSTEM ) REPLACEMENT SURCHARGE, )
)
MISSOURI PUBLIC SERVICE ) COMMISSION, )
Respondents, )
v. ) WD77089 )
THE OFFICE OF PUBLIC COUNSEL, ) FILED: July 29, 2014 Appellant. )
APPEAL FROM THE PUBLIC SERVICE COMMISSION
BEFORE DIVISION ONE: MARK D. PFEIFFER, PRESIDING JUDGE, LISA WHITE HARDWICK AND GARY D. WITT, JUDGES The Office of the Public Counsel appeals from the Missouri Public Service
Commission's order approving the request of Liberty Energy (Midstates) Corp. d/b/a/ Liberty Utilities ("Liberty") to change its Infrastructure System Replacement Surcharge ("ISRS"). Public Counsel contends the Commission's order is unlawful because it allows Liberty to recover costs that are not authorized by the ISRS statutes. For reasons explained herein, we affirm.
FACTUAL AND PROCEDURAL HISTORY
The Commission is the state administrative agency responsible for regulating public utilities, including gas corporations, in Missouri. In re Laclede Gas Co., 417 S.W.3d 815, 817 (Mo. App. 2014). Liberty is a Missouri corporation and a natural gas provider. It is a "gas corporation" and "public utility" under Sections 386.020(18) and (43), RSMo Cum. Supp. 2013,1 and, therefore, is subject to the Commission's regulatory power. Id. Public Counsel is a state agency that has the discretion to represent the interests of consumers in all utility proceedings before the Commission and in all appeals of Commission orders. Id.
In 2012, Liberty purchased substantially all of the assets that Atmos Energy Corporation ("Atmos") used to provide natural gas and transportation services in Missouri. The Commission issued new certificates of convenience and necessity to Liberty for the service areas formerly served by Atmos, and the Commission approved Liberty's adoption of Atmos's tariffs.
Among the tariffs that Liberty adopted were Atmos's ISRS tariffs for each of its three rate districts. The ISRS statutes, Sections 393.1009, 393.1012, and 393.1015, provide a method for gas corporations to recover eligible infrastructure system replacement costs between general rate cases through a surcharge on their customers' bills. Section 393.1009(3) defines "eligible infrastructure system replacements" as gas utility plant projects that:
(a) Do not increase revenues by directly connecting the infrastructure replacement to new customers;
(b) Are in service and used and useful;
1 All statutory references are to the Revised Statutes of Missouri 2000, as updated by the 2013 Cumulative Supplement.
(c) Were not included in the gas corporation's rate base in its most recent general rate case; and
(d) Replace or extend the useful life of an existing infrastructure[.]
Section 393.1009(5) defines "gas utility plant projects," in pertinent part, as:
(a) Mains, valves, service lines, regulator stations, vaults, and other pipeline system components installed to comply with state or federal safety requirements as replacements for existing facilities that have worn out or are in deteriorated condition;
(b) Main relining projects, service line insertion projects, joint encapsulation projects, and other similar projects extending the useful life or enhancing the integrity of pipeline system components undertaken to comply with state or federal safety requirements[.]
In July 2013, Liberty filed a petition with the Commission to change its ISRS to recover costs incurred due to infrastructure system replacements that Liberty made from June 1, 2012 through May 31, 2013. Pursuant to Section 393.1015.2(1), when a petition to establish or change an ISRS is filed, the Commission is required to conduct an examination of the proposed ISRS. The Commission's Staff may examine the petitioning gas corporation's information to confirm that the costs are in accordance with the ISRS statutes and that the proposed charges are properly calculated. § 393.1015.2(2). Staff may then submit a report of its examination to the Commission no later than sixty days after the petition was filed. Id. The Commission may hold a hearing on the petition and must "issue an order to become effective not later than one hundred twenty days after the petition [was] filed." § 393.1015.2(3).
In this case, Staff from the Commission's Auditing and Energy Units conducted an investigation of Liberty's ISRS petition. Liberty sought to recover costs for 275 distinct projects. Of these 275 projects, Staff's investigation included reviewing 36
Liberty work orders totaling approximately $2.2 million, which was about 58% of the amount that Liberty requested in its ISRS petition.2 The work orders that Staff examined provided enough information to demonstrate that the projects involved replacement of steel or polyethylene pipe. Some projects included the installation of either gas safety valves or excess flow valves. The work orders noted the age of the pipe being replaced and any corrosion or other defects. Staff determined that the work orders involved pipe replacements that improved the integrity of the system, rather than maintenance expenses, such as merely wrapping a pipe.
Additionally, Staff reviewed Liberty's project sub-ledger, which designated whether a project included material, supplies, overhead, or labor, and whether the project was performed for the integrity of the system or for growth. The costs included in the project sub-ledger were detailed enough for Staff to understand the activities and costs incurred for each job.
In reviewing Liberty's initial calculations, Staff noticed that Liberty had included some growth projects, which are not eligible for recovery in an ISRS under Section 393.1009(3)(a). Staff removed those projects when it performed its own calculations. Staff also identified other errors and omissions in the data provided by Liberty, including summation errors; errors in accumulated depreciation, deferred income taxes, property taxes, depreciation rates, and conversion factors; and formula errors. Staff filed a report, with two subsequent updates, recommending several adjustments to Liberty's ISRS petition to correct the identified errors and omissions. Staff then calculated an
2 According to Staff, if this were a general rate case and not an ISRS request, it would be able to examine significantly more project work orders because Staff has more time to conduct its investigation in a general rate case.
adjusted ISRS. Liberty agreed with Staff's recommendations and calculations in the adjusted ISRS.
Public Counsel filed a motion requesting that the Commission reject Liberty's ISRS petition or schedule an evidentiary hearing. In its motion, Public Counsel asserted, among other things, that Liberty was seeking to recover expenses in its proposed ISRS that were not authorized by Section 393.1009(5).
The Commission held an evidentiary hearing, and the parties argued their positions in post-hearing briefs. One of the arguments that Public Counsel made was that Liberty should not be allowed to recover its expenses for infrastructure that was replaced because it was accidentally or negligently damaged by a third party, such as a when a contractor accidentally struck a main or service line while digging. Public Counsel contended that the replacement of a pipe that was accidentally damaged during excavation activity did not satisfy Section 393.1009(5)(a)'s requirement that the replacement was for "existing facilities that have worn out or are in deteriorated condition." (Emphasis added.)
Free access — add to your briefcase to read the full text and ask questions with AI
In the Matter of the Verified Application and Petition of Liberty Energy (Midstates) Corp d/b/a Liberty Utilities to Change its Infrastructure System Replacement Surcharge Missouri public Service Commission v. The Office of Public Counsel (In the Matter of the Verified Application and Petition of Liberty Energy (Midstates) Corp d/b/a Liberty Utilities to Change its Infrastructure System Replacement Surcharge Missouri public Service Commission v. The Office of Public Counsel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.