In the matter of the verified application and petition of Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to change its infrastructure system replacement surcharge, Missouri Public Service Commission v. The Office of Public Counsel

CourtSupreme Court of Missouri
DecidedJune 16, 2015
DocketSC94470
StatusPublished

This text of In the matter of the verified application and petition of Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to change its infrastructure system replacement surcharge, Missouri Public Service Commission v. The Office of Public Counsel (In the matter of the verified application and petition of Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to change its infrastructure system replacement surcharge, Missouri Public Service Commission v. The Office of Public Counsel) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the matter of the verified application and petition of Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to change its infrastructure system replacement surcharge, Missouri Public Service Commission v. The Office of Public Counsel, (Mo. 2015).

Opinion

SUPREME COURT OF MISSOURI en banc

IN THE MATTER OF THE VERIFIED ) APPLICATION and PETITION OF ) LIBERTY ENERGY (MIDSTATES) CORP. ) d/b/a LIBERTY UTILITIES TO CHANGE ) ITS INFRASTRUCTURE SYSTEM ) REPLACEMENT SURCHARGE, ) ) MISSOURI PUBLIC SERVICE ) COMMISSION, ) ) Respondents, ) ) v. ) No. SC94470 ) THE OFFICE OF PUBLIC COUNSEL, ) ) Appellant. )

APPEAL FROM THE MISSOURI PUBLIC SERVICE COMMISSION

Opinion issued June 16, 2015

The Office of the Public Counsel (hereinafter, “Public Counsel”) appeals from an

order entered by the Missouri Public Service Commission (hereinafter, “the PSC”),

granting Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities’ (hereinafter,

Liberty”)1 request for an increase to its Infrastructure System Replacement Surcharge

(hereinafter, “ISRS”). Because the PSC failed to follow the plain language of its

1 In October 2013, the PSC granted Liberty’s application for the name change from Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to Liberty Utilities (Midstates Natural Gas) Corp. d/b/a Liberty Utilities, effective November 1, 2013. statutory mandates, its order is unlawful. This Court reverses the PSC’s order, and the

case is remanded.

Background

Liberty is a natural gas provider. It is a “public utility” and a “gas corporation.”

Sections 386.020(43) and 386.020(18), RSMo Supp. 2013. 2 The PSC is a Missouri

administrative agency charged with the regulation of all public utilities. Sections 386.040

and 386.250(1), RSMo 2000; see also State ex rel. MoGas Pipeline, LLC v. Missouri

Pub. Serv. Comm’n, 366 S.W.3d 493, 496 (Mo. banc 2012). Public Counsel is appointed

by the director of the department of economic development and may represent the public

interest in any proceeding before the PSC and in appeals from the PSC’s orders. Sections

386.700 and 386.710, RSMo 2000; Pub. Serv. Comm’n of State v. Missouri Gas Energy,

388 S.W.3d 221, 224 (Mo. App. W.D. 2012).

In 2012, the PSC authorized Liberty’s purchase of substantially all of the assets

that Atmos Energy Corporation (hereinafter, “Atmos”) used to provide natural gas and

transportation services in Missouri. The PSC issued new certificates of convenience and

necessity to Liberty for the service areas Atmos previously served. Further, the PSC

approved Liberty’s adoption of Atmos’ ISRS tariff. 3

Gas corporations are permitted to recover certain infrastructure system

replacement costs outside of a formal rate case though a surcharge on their customers’

2 All further statutory references herein are to RSMo Supp. 2013, unless otherwise indicated. 3 Like its predecessor Atmos, Liberty has a specific ISRS rate for each of its three districts. bills. When a petition to modify an ISRS is filed, the PSC staff must conduct an

examination of the proposed ISRS. Section 393.1015.2, RSMo Supp. 2003. The

examination may scrutinize the petitioning gas corporation’s information to confirm the

costs are in accordance with the ISRS code provisions and confirm the proposed charges

are calculated properly. A report of the examination may be submitted to the PSC no

later than sixty days after the petition was filed. Section 393.1015.2(2).

In July 2013, Liberty filed a petition with the PSC seeking an adjustment of its

ISRS rate schedule. Liberty sought the adjustment to recover costs incurred in

connection with ISRS-eligible infrastructure system replacements made from June 1,

2012, through May 31, 2013. After Liberty filed its petition for an adjustment of its ISRS

rate schedule, the PSC staff conducted an investigation.

During the examination of Liberty’s petition, the PSC staff inspected thirty-six of

the two hundred seventy-five projects for which Liberty sought recovery. The projects

investigated compromised approximately fifty-eight percent of the costs for which

Liberty sought recovery. 4 The PSC staff also examined Liberty’s project sub-ledger,

which indicated, inter alia, whether a project was performed for the integrity of the

overall system or was for growth.

The PSC staff submitted its report to the PSC on September 3, 2013. The report

noted that Liberty included some growth projects in its application, which are not eligible

for recovery in an ISRS. The PSC staff removed those projects from its calculations.

4 Due to the time constraints in an ISRS request, the PSC staff only could investigate a limited number of projects. 3 The PSC staff also identified other errors and omissions in Liberty’s data, including:

summation errors; errors in accumulated depreciation; deferred income taxes, property

taxes depreciation rates, and conversion factors; and formula errors. The report was

updated on September 20, 2013, and September 26, 2013, providing amended revenue

figures and customer class rates based on additional data from Liberty.

On September 9, 2013, Public Counsel filed a motion, requesting the PSC reject

Liberty’s ISRS petition or schedule an evidentiary hearing. Public Counsel asserted,

inter alia, Liberty was seeking to recover expenses in its ISRS application that were not

authorized by section 393.1009(5). The PSC held an evidentiary hearing on September

26, 2013.

At the evidentiary hearing, Liberty’s president testified that the requested ISRS

rate increase included costs to cover damage to Liberty’s facilities caused by a contractor

or another third party. Public Counsel argued that Liberty should not recover expenses

for its infrastructure that was replaced because it was damaged accidentally or negligently

by a third party. Public Counsel maintained that Liberty’s replacement of the pipe that

was damaged accidently during excavation did not satisfy the section 393.1009(5)(a)

requirement that the replacement was for “existing facilities that have worn out or are in a

deteriorated condition.”

The PSC approved the ISRS increase for Liberty, concluding that “damaged”

infrastructure is synonymous with “deteriorated.” The PSC found replacing the pipes

that were damaged by a third party qualified as a “gas utility project” pursuant to section

393.1009(5)(a), and the projects were “extending the useful life or enhancing the integrity

4 of the pipeline system components” pursuant to section 393.1009(5)(b). Accordingly,

Liberty filed a new ISRS tariffs in compliance with the PSC’s order, and the PSC

approved the tariffs.

Public Counsel filed an application for rehearing, which the PSC denied. Public

Counsel appealed, and the court of appeals affirmed. This Court granted transfer

pursuant to Mo. Const. art. V, sec. 10, after opinion by the court of appeals.

Discussion

Standard of Review

“This Court reviews the decision of the PSC rather than that of the circuit court.”

State ex rel. Praxair, Inc. v. Missouri Pub. Serv. Comm’n, 344 S.W.3d 178, 184 (Mo.

banc 2011). Appellate review of a PSC order is two-pronged: first, to determine whether

the PSC’s order is lawful; and second, to determine whether the PSC’s order is

reasonable. MoGas Pipeline, LLC, 366 S.W.3d at 495-96; see also section 386.510. The

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. AG Processing, Inc. v. Public Service Commission
120 S.W.3d 732 (Supreme Court of Missouri, 2003)
American Healthcare Management, Inc. v. Director of Revenue
984 S.W.2d 496 (Supreme Court of Missouri, 1999)
State Ex Rel. MoGas Pipeline LLC v. Missouri Public Service Commission
366 S.W.3d 493 (Supreme Court of Missouri, 2012)
WEHRENBERG, INC. v. Director of Revenue
352 S.W.3d 366 (Supreme Court of Missouri, 2011)
State Ex Rel. Praxair, Inc. v. Missouri Public Service Commission
344 S.W.3d 178 (Supreme Court of Missouri, 2011)
Balloons Over the Rainbow, Inc. v. Director of Revenue
427 S.W.3d 815 (Supreme Court of Missouri, 2014)
Public Service Commission v. Missouri Gas Energy
388 S.W.3d 221 (Missouri Court of Appeals, 2012)
Bateman v. Rinehart
391 S.W.3d 441 (Supreme Court of Missouri, 2013)
Office of the Public Counsel v. Missouri Public Service Commission
409 S.W.3d 371 (Supreme Court of Missouri, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
In the matter of the verified application and petition of Liberty Energy (Midstates) Corp. d/b/a Liberty Utilities to change its infrastructure system replacement surcharge, Missouri Public Service Commission v. The Office of Public Counsel, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-the-verified-application-and-petition-of-liberty-energy-mo-2015.