In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation, and In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation.

CourtCourt of Appeals of Minnesota
DecidedFebruary 9, 2015
DocketA14-438, A14-439
StatusUnpublished

This text of In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation, and In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation. (In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation, and In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation, and In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation., (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-0438 A14-0439

In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation,

and

In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation.

Filed February 9, 2015 Affirmed Bjorkman, Judge

Minnesota Public Utilities Commission File No. E-002/M-13-603

Charles N. Nauen, David J. Zoll, Kristen G. Marttila, Lockridge Grindal Nauen P.L.L.P., Minneapolis, Minnesota; and

Thomas Melone (pro hac vice), Minneapolis, Minnesota (for relators Garvin Wind, LLC, Gadwell Wind, LLC, Greenhead Wind, LLC, Watonwan Wind, LLC, Highwater Wind, LLC, Ecos Energy, LLC, Summit Wind, LLC, Jeffers South, LLC, and Hurricane Wind, LLC)

Michael C. Krikava, Thomas Erik Bailey, Anna E. Jenks, Briggs and Morgan, PA, Minneapolis, Minnesota; and

Kari L. Valley, Assistant General Counsel, Xcel Energy, Inc., Minneapolis, Minnesota (for respondent Northern States Power Company, d/b/a Xcel Energy, Inc.)

Lori Swanson, Attorney General, Elizabeth M. Jones, Anjali Shankar, Assistant Attorneys General, St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission) Sten-Erik Hoidal, Christina K. Brusven, Fredrikson & Byron, P.A., Minneapolis, Minnesota (for respondent Geronimo Wind, LLC d/b/a Geronimo Energy, LLC)

Considered and decided by Connolly, Presiding Judge; Halbrooks, Judge; and

Bjorkman, Judge.

UNPUBLISHED OPINION

BJORKMAN, Judge

Relators challenge respondent Minnesota Public Utilities Commission’s approval

of respondent Northern States Power Company d/b/a Xcel Energy’s (Xcel) petitions to

acquire wind-powered electricity, arguing that they were entitled to a contested-case

hearing and that the commission’s approval is inconsistent with Xcel’s statutory

obligation to make reasonable efforts to fulfill its renewable-energy requirements using

community-based energy-development projects. We affirm.

FACTS

Relators1 are Minnesota-based wind-power companies, formed to develop

community-based energy-development (C-BED) projects on land owned and farmed by

member-owners. Relators’ wind-power projects qualify for C-BED status under Minn.

Stat. § 216B.1612 (2014), which was enacted to provide rural communities with the

opportunity to share in the economic benefits of large energy-production projects.

In February 2013, Xcel solicited bids for up to 200 megawatts (MW) of wind

power. This request for bids was precipitated in part by Xcel’s need to acquire additional

1 Relators include Ecos Energy, LLC, Summit Wind, LLC, Jeffers South, LLC, Greenhead Wind, LLC, Garvin Wind, LLC, Gadwall Wind, LLC, Watowan Wind, LLC, Hurricane Wind, LLC, and Highwater Wind, LLC, who jointly filed a petition to intervene in the wind-acquisition proceedings.

2 wind-generated electricity to comply with state renewable-energy standards. The

standards require Xcel to produce 25% of its electricity from wind power by 2020. Minn.

Stat. § 216B.1691, subd. 2a(b) (2014). Xcel must also submit a renewable-energy plan to

the commission specifying how it will meet its renewable-energy requirements. Id.,

subd. 10 (2014). The commission approved Xcel’s current renewable-energy plan in

2009 after a public hearing.

Xcel received 57 bids for wind projects located in six states. Xcel initially

screened the bids by calculating the levelized cost2 of each project and setting a $29 per

megawatt-hour (MWh) cutoff. Sixteen projects came in below the levelized-cost cutoff.

Relators’ C-BED projects were among the initial 57 bids, but none fell below the

$29/MWh threshold. The closest C-BED bid was $29.55/MWh.

After further review, Xcel petitioned the commission to approve four projects,

representing a total of 750 MW of wind power. Xcel believed this large acquisition was

warranted due to its need to acquire significant wind resources to comply with the

renewable-energy standards, and due to historically low prices. Relators successfully

petitioned to intervene in the approval proceeding, and objected to the proposed

acquisitions on the ground that Xcel did not make a reasonable effort to fulfill its wind-

energy needs through C-BED projects. Relators also asked the commission to refer the

matter to the Office of Administrative Hearings for a contested-case proceeding.

In December 2013, the commission approved Xcel’s proposals, concluding that

they represent a reasonable and prudent approach to meet Xcel’s obligations under the

2 Levelized cost is the average cost of power calculated over the life of the investment.

3 state’s renewable-energy standards. The commission rejected relators’ request for a

contested-case proceeding. Relators filed a petition for reconsideration, which the

commission denied. Relators bring this certiorari appeal.

DECISION

This court will affirm an administrative agency’s decision unless its findings,

inferences, conclusions, or decisions are:

(a) in violation of constitutional provisions; or (b) in excess of the statutory authority or jurisdiction of the agency; or (c) made upon unlawful procedure; or (d) affected by other error of law; or (e) unsupported by substantial evidence in view of the entire record as submitted; or (f) arbitrary or capricious.

Minn. Stat. § 14.69 (2014); see Minn. Stat. § 216B.52, subd. 1 (2014). A party

challenging an agency’s findings must establish that they are not supported by the record

evidence. Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 825 (Minn. 1977). If an

agency engages in reasoned decision-making, we will affirm, even if we may have

reached a different conclusion had we been the fact-finder. Cable Commc’ns Bd. v. Nor–

West Cable Commc’ns P’ship, 356 N.W.2d 658, 669 (Minn. 1984).

We presume that an agency’s decision is correct, and defer to an agency’s

conclusions in its area of expertise. Id. at 668. An agency is also presumed to have the

expertise necessary to decide technical matters within the scope of its authority, and

deference is extended to any agency decision-maker “in the interpretation of statutes that

the agency is charged with administering and enforcing.” In re Excess Surplus Status of

4 Blue Cross & Blue Shield of Minn., 624 N.W.2d 264, 278 (Minn. 2001). But when a

decision turns on the meaning of words in a statute or regulation, a legal question is

presented, and we are not bound by the agency’s decision. St. Otto’s Home v. Minn.

Dep’t of Human Servs., 437 N.W.2d 35, 39-40 (Minn. 1989).

On appeal, relators raise two primary arguments: (1) the commission improperly

denied their request for a contested-case proceeding and (2) Xcel did not make a

reasonable effort to meet its renewable-energy requirements through C-BED projects by

affording them special considerations during the bidding process. We address each

argument in turn.

I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Excess Surplus Status of Blue Cross & Blue Shield of Minnesota
624 N.W.2d 264 (Supreme Court of Minnesota, 2001)
Reserve Mining Co. v. Herbst
256 N.W.2d 808 (Supreme Court of Minnesota, 1977)
In the Matter of Petition of N. St. Power
676 N.W.2d 326 (Court of Appeals of Minnesota, 2004)
Cable Communications Board v. Nor-West Cable Communications Partnership
356 N.W.2d 658 (Supreme Court of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 600 MW of Wind Generation, and In the Matter of the Petition of Xcel Energy for Approval of the Acquisition of 150 MW of Wind Generation., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-the-petition-of-xcel-energy-for-approval-of-the-minnctapp-2015.