In the matter of the petition of the Empire District Electric Company d/b/a Liberty to obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Qualified Extraordinary Costs and In the matter of the Petition of the Empire District Electric Company d/b/a Liberty to Obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Energy Transition Costs Related to the Asbury Plant; Empire District Electric Company d/b/a Liberty; Office Public Counsel v. Public Service Commission of the State of Missouri

Missouri Court of Appeals·Decided August 1, 2023·No. WD85800·Published

Opinion

MISSOURI COURT OF APPEALS WESTERN DISTRICT

IN THE MATTER OF THE PETITION ) OF THE EMPIRE DISTRICT ) ELECTRIC COMPANY d/b/a ) LIBERTY TO OBTAIN A FINANCING ) ORDER THAT AUTHORIZES THE ) ISSUANCE OF SECURITIZED ) UTILITY TARIFF BONDS FOR ) QUALIFIED EXTRAORDINARY ) COSTS AND IN THE MATTER OF ) THE PETITION OF THE EMPIRE ) DISTRICT ELECTRIC ) COMPANY d/b/a LIBERTY TO ) OBTAIN A FINANCING ORDER ) THAT AUTHORIZES THE ) ISSUANCE OF SECURITIZED ) UTILITY TARIFF BONDS FOR ) ENERGY TRANSITION COSTS ) RELATED TO THE ASBURY PLANT; ) EMPIRE DISTRICT ELECTRIC ) COMPANY d/b/a LIBERTY, ) WD85800 Consolidated with ) WD85801

Appellant-Respondent, )

)

OFFICE OF PUBLIC COUNSEL, ) Filed: August 1, 2023 )

Respondent-Appellant, )

v. )

)

)

PUBLIC SERVICE COMMISSION OF ) THE STATE OF MISSOURI, )

)

Respondent. )

APPEAL FROM THE PUBLIC SERVICE COMMISSION

BEFORE DIVISION ONE: ANTHONY REX GABBERT, PRESIDING JUDGE, LISA WHITE HARDWICK, JUDGE, AND MARK D. PFEIFFER, JUDGE

The Empire District Electric Company, d/b/a Liberty (“Liberty”), appeals from the Amended Report and Order of the Public Service Commission (“Commission”) approving the securitization of costs in an amount less than Liberty requested. In Points I and III, Liberty contends the Commission’s calculation of the amount of energy transition costs for a retired plant that Liberty could recover through securitization violates the securitization statute, is not supported by substantial evidence, and is unreasonable. In Point II, Liberty asserts the Commission erroneously imposed a blanket reduction on the amount of fuel and power purchase costs in connection with a winter storm that Liberty could recover through securitization. For reasons explained herein, we affirm.

FACTUAL AND PROCEDURAL HISTORY Formerly known as Empire, Liberty is an electrical corporation and public utility regulated by the Commission. Liberty generates, purchases, distributes, and sells electricity in portions of Missouri, Arkansas, Kansas, and Oklahoma. Liberty’s customers include residents of 16 counties in southwest Missouri. Asbury Coal Plant Retirement In 1970, Liberty built Asbury, a 200-megawatt coal plant, located in Asbury, Missouri. Between 1970 and 2008, Liberty invested about $113 million to build and maintain Asbury. In 2008, Liberty installed a $33 million selective catalytic reduction system to reduce Asbury’s nitrogen oxide emissions. In 2014, Liberty retrofitted Asbury

with a $141 million Air Quality Control System to comply with federal environmental regulations. Liberty represented that these upgrades would extend Asbury’s operational life through 2035.

Liberty participates in the Southwest Power Pool’s (“SPP”) wholesale electricity market. Between 2010 and 2019, Asbury’s position in the SPP worsened, primarily due to decreasing natural gas prices and the declining cost and increasing use of wind resources. These market forces rendered Asbury uneconomic for Liberty to run most of the time. In the past decade, a third of the United States coal fleet retired under such market pressure. Asbury’s last day of generating power was December 12, 2019, when its coal supply was exhausted. Asbury was officially retired on March 1, 2020, after Liberty notified the SPP of the planned retirement, and the plant was decommissioned and dismantled.

For tax purposes, Liberty wrote off Asbury. Liberty claimed Asbury’s remaining accelerated depreciation as abandonment loss deductions in 2019 and 2020. Liberty received a $16.5 million tax benefit on the deductions. For ratemaking purposes, Liberty abandoned Asbury during a 2019 general rate case, Commission Case No. ER-2019-0374 (“2019 rate case”). The rates established in the 2019 rate case included the costs associated with operating Asbury. At that time, all the financial impacts of the abandonment could not be ascertained.

The parties in the 2019 rate case agreed the Commission should establish an Accounting Authority Order (“AAO”) for Asbury. An AAO is a form of Commission- approved deferral accounting in which specific costs are recorded as regulatory assets, for

possible recovery from customers, or regulatory liabilities, for possible credit to customers, and held for final Commission determination in a future rate proceeding. The Asbury AAO established a regulatory liability for various rate base and expense components, like rate of return on the Asbury plant, depreciation expense, operating and maintenance expenses, and property taxes. At the same time, Liberty established a regulatory asset that included Asbury’s remaining book depreciation, plus other retirement costs.

The Commission set a 6.77% rate of return for Liberty in the 2019 case. This represented Liberty’s weighted average cost of capital (“WACC”). Liberty’s 2019 rates included this rate of return applied to Liberty’s rate base, including Asbury.

Asbury was not included in the rates established in Liberty’s next rate case, Commission Case No. ER-2021-0312 (“2021 rate case”). Initially, Liberty had requested final rate treatment of the Asbury AAO in the 2021 rate case. Liberty had sought recovery of all of its Asbury costs, including a full return on the retired plant. Commission Staff (“Staff”) recommended a sharing of the responsibility for Asbury’s unrecovered capital costs as of its retirement date between Liberty’s shareholders and customers. Later in the 2021 rate case, however, Liberty abandoned its request for rate treatment of the Asbury AAO and decided to seek rate treatment for Asbury through securitization in the present case. Winter Storm Uri Between February 13 and 20, 2021, three severe winter storms collectively known as Winter Storm Uri struck portions of the United States. Much of the Midwest,

including Liberty’s service area, experienced unseasonably cold temperatures, resulting in rolling electrical blackouts and extreme natural gas spikes. The SPP’s grid nearly collapsed. Wholesale electricity prices surged. The SPP’s on-peak day-ahead locational marginal prices for February 15 through 19, 2021, averaged 11,280% higher than the five-year average for the period, reaching $3,821.05 per megawatt hour for February 18, 2021 delivery. Liberty incurred approximately $193 million in extraordinary fuel and purchased power costs to serve its Missouri customers during the storm. Recovery of Liberty’s $193 million in extraordinary fuel costs arising from Winter Storm Uri under the six-month recovery period established in Liberty’s Fuel Adjustment Charge (“FAC”) would create extreme customer rate impacts.1 Securitization In 2021, the legislature authorized securitization, a financing technique, for the first time in Missouri when it enacted Section 393.1700.2 Section 393.1700 allows utilities to petition the Commission for a financing order approving recovery of energy transition costs or qualified extraordinary costs through securitization. Energy transition costs relate to the retirement or abandonment of a power plant. § 393.1700.1(7). The statute defines these costs as “accrued carrying charges” and other costs “with respect to a retired or abandoned or to be retired or abandoned electric generating facility . . . where such early retirement or abandonment is deemed reasonable and prudent by the

1 The FAC is a ratemaking mechanism in Liberty’s tariff that allows the company to recover costs through a volumetric charge that appears on customer bills. 2 All statutory references are to the Revised Statutes of Missouri 2016, as updated by the 2022 Cumulative Supplement.

commission.” § 393.1700.1(7)(a). Qualified extraordinary costs relate to extreme events such as severe storms. The statute defines those costs as “prudently” incurred costs “of an extraordinary nature which would cause extreme customer rate impacts if reflected in retail customer rates recovered through customary ratemaking, such as but not limited to those related to purchases of fuel or power, inclusive of carrying charges during anomalous weather events.” § 393.1700.1(13).

Free access — add to your briefcase to read the full text and ask questions with AI

In the matter of the petition of the Empire District Electric Company d/b/a Liberty to obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Qualified Extraordinary Costs and In the matter of the Petition of the Empire District Electric Company d/b/a Liberty to Obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Energy Transition Costs Related to the Asbury Plant; Empire District Electric Company d/b/a Liberty; Office Public Counsel v. Public Service Commission of the State of Missouri, (Mo. Ct. App. 2023).

In the matter of the petition of the Empire District Electric Company d/b/a Liberty to obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Qualified Extraordinary Costs and In the matter of the Petition of the Empire District Electric Company d/b/a Liberty to Obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Energy Transition Costs Related to the Asbury Plant; Empire District Electric Company d/b/a Liberty; Office Public Counsel v. Public Service Commission of the State of Missouri (In the matter of the petition of the Empire District Electric Company d/b/a Liberty to obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Qualified Extraordinary Costs and In the matter of the Petition of the Empire District Electric Company d/b/a Liberty to Obtain a Financing Order that Authorizes the Issuance of Securitized Utility Tariff Bonds for Energy Transition Costs Related to the Asbury Plant; Empire District Electric Company d/b/a Liberty; Office Public Counsel v. Public Service Commission of the State of Missouri) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related